BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Administrative Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Administrative Court) Decisions >> Anderson v Secretary of State for Communities and Local Government & Ors [2015] EWHC 3005 (Admin) (23 October 2015) URL: http://www.bailii.org/ew/cases/EWHC/Admin/2015/3005.html Cite as: [2015] EWHC 3005 (Admin) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
PLANNING COURT
Oxford Row Leeds LS1 3BG |
||
B e f o r e :
____________________
COLIN WILLIAM ANDERSON |
Claimant |
|
- and - |
||
(1) SECRETARY OF STATE FOR COMMUNITIES AND LOCAL GOVERNMENT (2) KIRKLEES METROPOLITAN BOROUGH COUNCIL (3) YORKSHIRE WATER SERVICES LIMITED |
Defendants |
____________________
Justine Thornton (instructed by Government Legal Department) for the First Defendant
John Barrett (instructed by Squire Patton Boggs (UK) LLP) for the Third Defendant
The Second Defendant was not represented at the hearing
Hearing date: 7 October 2015
____________________
Crown Copyright ©
Judge Behrens :
1. Introduction
2. The facts
Butterley Reservoir
Dr Hughes's inspections
The Planning Application
"Reconstruction of a section of the masonry spillway at Butterley reservoir. The spillway is grade II listed.
• replacement of the existing walls with new raised walls in reinforced concrete to approximately 2.6 metres high;
• overlaying the base of the spillway with a reinforced concrete slab, complete with small steps similar to the finish of the existing base;
• reconstruction of the existing stepped cascade section to form a constant gradient to match the upper section of the channel;
• cladding the outside of the walls with masonry. Cladding to include the use of reclaimed masonry from existing walls;
• stone copings on top of the raised walls. Existing copings to be reclaimed and reused on top of the new raised walls where possible;
• using masonry effect 'formliner' on the inside face of the walls. '"
Accordingly, having regard to the advice at paragraphs 132 and 133 of the Framework and in the Planning Practice Guidance, I am in no doubt that the harm that would be caused to the special interest and significance of the spillway could only be described as substantial. Indeed, the scale of harm in this regard was a matter of common ground. In relation to the other assets, the harm would, by and large, be to their setting and would be less than substantial.
The Appeal
The Pre-Inquiry Meeting
"Inquiries are open to members of the public and, although you do not have a legal right to speak, the Inspector will normally allow you to do so. If you wish to speak at the Inquiry, you should notify the inspectorate's case officer, Mr Kozak as soon as possible, with dates of your likely availability/non-availability.
.. Some people prefer to make, or read out, a brief statement giving their views. In such cases, it is helpful to the Inspector and the parties to have a copy of that statement in advance."
Contact with Planning Inspectorate
The Inquiry
I believe that I have found 'reasonable means' of providing spillway provision at Butterley Reservoir. In terms of cost, I believe this solution and/or its variants will economically rival YW preferred option 5b.
To assist in the endeavour to find the best engineering solution, I am prepared to provide my service for free (I have no other teaching work after 1st February), to work collaboratively alongside a qualified engineer from YW to develop my scheme proposal and/or its variants as an engineering solution for Butterley spillway that satisfies both reservoir safety and as far as possible, landscape and heritage requirements (including the setting of the listed structure)."
I cannot receive any new information about other new options and you must remove them.'
His "proof" is in effect an attack on Dr Hughes. His proof further sets out a broad alternative scheme which in essence involves re-use of the existing spillway. However it was clear that his alternative scheme was not fixed and subject to significant additional work. I began to cross-examine Mr Anderson and asked him to what extent, if any he anticipated the wall height would have to be increased. He responded by saying he would not be drawn on detail. I asked why not and he said he was not prepared to be interrogated; that more work was required and that he was withdrawing his option. He was extremely agitated. I believe the Inspector asked him if he was sure about this and he said he was.
My (?) Option – withdrawn
+ Not prepared to be interrogated – more wk req –
I asked about wall height & he refused to be drawn
37. Mr Anderson was able to describe his alternative and I discussed that alternative with him when I was being cross-examined by him. His proposed alternative was no different to that considered during the Engineering Options Study. I explained to Mr Anderson why his alternative was not a viable solution. …
38. Mr Anderson put his alternative solution, which he had earlier declared as incomplete to me repeatedly during my cross-examination. I was not concerned it was incomplete because I was able to understand the concept he was proposing which involved pinning every block in the spillway – many hundreds of blocks. I repeatedly rejected the 'alternative' due to the risk of a single block coming loose which could then result in the whole of the spillway unravelling. It was at this point hat Mr Anderson became very emotional with my replies and suggested I was lying. …the Inspector gave Mr Anderson free reign to question me, re-question me and to ask additional questions when he appeared dissatisfied with my response.
39. Mr Anderson in his proof of evidence dismissed the Warmwitherns case history even though this is very relevant to the Butterley case and made reference to the need for doing CFD … modelling without having , it appears, any knowledge of what the BDS (British Dams Society) meeting, which was held the previous evening had concluded. During my cross-examination I made it clear that I had attended and chaired the meeting. Mr Anderson states that "good industry practice" recommends CFD modelling to be undertaken first followed by physical modelling to validate the CFD analysis. – this is not the case – it is not good industry practice.
40 I am entirely confident that the physical model directed witnessed and reviewed by myself as panel Engineer provided the correct information on which to design the way forward at Butterley.
3. The decision
… my role in these appeals is to consider the scheme proposed on its own particular merits, not to consider whether some other option should be approved as an alternative. Those options, and other possibilities mooted at the Inquiry, are only relevant insofar as they may, or may not, provide evidence as to whether the scheme the subject of these appeals is 'necessary' having regard to the provisions of paragraph 133 of the National Planning Policy Framework.
1. That Parliament had expressly conferred on Panel Engineers such as Dr Hughes the responsibility to decide what safety measures are required.
2. The relevant standard for the design a Class A Dam is that the risk of failure due to flood is virtually eliminated. This is a higher test than the test of reasonable practicability.
3. Neither the Reservoirs Act nor the ICE guidance provide for the Engineer to balance considerations of safety against other factors such as heritage factors. The only consideration under the Act is public safety.
42. As set out in the Options Appraisal, and as confirmed in the evidence and cross-examination of Dr Hughes, the majority of the options assessed on a formal basis in relation to Butterley would, among other things, involve cutting through and breaching the clay core and/or the cut-off walls, introducing an increased short and long term risk of a potential flow path for the migration of water - if a leakage path is introduced around any new spillway, or any other overflow arrangement, substantial damage to the structure may ensue, posing a risk of catastrophic failure of the embankment. It is particularly difficult to measure the success of techniques such as this, other than by the detection of leakage once the reservoir has been refilled. I also understand that leaks could develop quickly, with few warning signs. Moreover, the risks at Butterley are likely to be greater than might otherwise be the case in this regard, because of known problems with the geology in this part of the valley, as encountered when the reservoir was first constructed.
43. Of the options that would not involve breaching the clay core, one involved decommissioning the reservoir. However, that would remove the flood alleviation properties of the reservoir and would have a major impact on the strategic water supply network for the Huddersfield area such that alternative provision would need to be made. The others would not meet the reservoir safety requirements.
44. Clearly, there are alternative development options that would deliver a more acceptable solution were preservation of the heritage asset the only consideration. However, the alterations proposed are required to address concerns of public safety by virtually eliminating the risk of failure. Whilst it might be that the required safety standards could, in principle, be capable of being met in more than one way, no substantiated evidence was before me to clearly demonstrate that any of the other feasible options in the Options.
49. On the basis of the evidence before me, the scheme proposed virtually eliminates the risk of failure of the dam whilst retaining the flood alleviation and water supply function of the reservoir. Moreover, the original function of the spillway would be retained, as would some of its original detailing. None of the other options have been demonstrated as being as safe and would not, therefore, virtually eliminate the risk of failure. All in all therefore, having regard to the provisions of the Reservoirs Act 1975, and the duty it imposes, I consider on balance, that the appeals should succeed.
4. Legal Principles
The Reservoirs Act 1975.
Sections 16(2) and 66(1) of the Planning (Listed Buildings and Conservation Areas) Act 1990 and the NPPF
Materiality
The decision maker ought to take into account a matter which might cause him to reach a different conclusion to that which he would reach if he did not take it into account. Such a matter is relevant to his decision making process. By the verb "might," I mean where there is a real possibility that he would reach a different conclusion if he did take that consideration into account.
If a matter is trivial or of small importance in relation to the particular decision, then it follows that if it were taken into account there would be a real possibility that it would make no difference to the decision and thus it is not a matter which the decision maker ought to take into account.
If the judge concludes that the matter was "fundamental to the decision," or that it is clear that there is a real possibility that the consideration of the matter would have made a difference to the decision, he is thus enabled to hold that the decision was not validly made. But if the judge is uncertain whether the matter would have had this effect or was of such importance in the decision-making process, then he does not have before him the material necessary for him to conclude that the decision was invalid.
The significance of the Rules
47. I would formulate the principle of natural justice or procedural fairness, which is in play in this appeal, as follows. Any participant in adversarial proceedings is entitled (a) to know the case which he has to meet and (b) to have a reasonable opportunity to adduce evidence and make submissions in relation to that opposing case.
(i) Any party to a planning inquiry is entitled (a) to know the case which he has to meet and (b) to have a reasonable opportunity to adduce evidence and make submissions in relation to that opposing case.
(ii) If there is procedural unfairness which materially prejudices a party to a planning inquiry that may be a good ground for quashing the Inspector's decision.
(iii) The 2000 Rules are designed to assist in achieving objective (i), avoiding pitfall (ii) and promoting efficiency. Nevertheless the Rules are not a complete code for achieving procedural fairness.
The Rules
Notification
Notices or documents required or authorised to be sent or supplied under these Rules may be sent or supplied—
(a) by post; or
(b) by using electronic communications to send or supply the notice or document (as the case may be) to a person at such address as may for the time being be specified by the person for that purpose.
The refusal to permit the giving of evidence.
The date for the accompanied site view.
5. Discussion
The Appendix
Did the Inspector close her mind?
Did the Inspector fail to have regard to material considerations?
Did Mr Anderson have a legitimate expectation that he could adduce the Appendix as evidence?
Was the exclusion of the Appendix procedurally unfair?
Breaches of the Rules
Mr Anderson's status as an expert
6. Conclusion