BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £5, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Administrative Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Administrative Court) Decisions >> Kenson Contractors (Benington) Ltd v London Borough of Haringey [2019] EWHC 1230 (Admin) (20 May 2019) URL: http://www.bailii.org/ew/cases/EWHC/Admin/2019/1230.html Cite as: [2019] EWHC 1230 (Admin) |
[New search] [Printable PDF version] [Help]
QUEENS BENCH DIVISION
ADMINISTRATIVE COURT
B e f o r e :
____________________
KENSON CONTRACTORS (BENINGTON) LIMITED |
Claimant |
|
- and - |
||
LONDON BOROUGH OF HARINGEY |
Defendant |
____________________
Ewan West (instructed by Haringey Council Legal Service) for the Defendant
Stephen Kosmin (instructed by CMS Cameron McKenna Nabarro Olswang LLP, Solicitors)
for the Interested Party
____________________
Crown Copyright ©
INTRODUCTION
PROCEDURAL HISTORY
THE CONTRACT WORKS
"1.3.2 Currently, the route is used by pedestrians, local residents, Tottenham Hotspur fans and cyclists. There are issues with Anti-Social Behaviour and street drinking, which the proposals aim to address. The existing drainage network has insufficient capacity to manage a storm event with localised flooding and large areas of ponding. The latter is exacerbated by the site's very slight longitudinal fall.
1.3.3 The Council plan to improve the link, introduce a pocket park to activate the space and install Sustainable Urban Drainage… to increase drainage capacity.
1.3.4 The project is funded through Mayor's Regeneration Fund… Council Capital funding, Section 106 and Section 278 contributions."
THE LEAD-UP TO THE ISSUE OF PROCEEDINGS
THE QUESTION OF PERMISSION
THE CORRECT APPROACH TO INJUNCTIVE RELIEF IN THIS CASE
Serious issue to be tried
"15.6. Criteria for the Grant of Interim Relief
15.6.1. When considering whether to grant interim relief while a judicial review claim is pending, the judge will consider:
15.6.1.1. Whether there is a real issue to be tried. In practice, in judicial review claims, that involves considering whether there is a real prospect of succeeding at the substantive hearing, that is to say a more than a fanciful prospect of success;
15.6.1.2. Whether the balance of convenience lies in granting the interim order;
15.6.1.3.Any other factors the Court considers to be relevant.
15.6.2. Generally, there is a strong public interest in permitting a public authority's decision to continue, so the applicant for interim relief must make out a strong case for relief in advance of the substantive hearing."
Balance of Convenience
"18-013 Moreover, questions as to the adequacy of damages as an alternative remedy will usually be less, or not at all, relevant because of the absence of any general right to damages for loss caused by unlawful administrative action per se. Conversely, the defendant does not usually suffer financial loss from the inability to implement its policies for a period. It follows that in cases involving the public interest, for example where a party is a public authority performing public duties, the decision to grant or withhold interim injunctive relief will usually be made not on the basis of the adequacy of damages but on the balance of convenience test. In such cases, the balance of convenience must be looked at widely, taking into account the interests of the general public to whom the duties are owed. The courts will be vigilant to prevent a claimant from seeking an injunction against an interested party in judicial review proceedings when the dispute is really one suitable for a private law claim.
18-014 Another difference from private law proceedings is that in judicial review, there is less likely to be a dispute of issues of fact. Where the only dispute is as to law, the court may have to make the best prediction it can of the final outcome and give that prediction decisive weight in resolving the interlocutory issue."
Relevance of the Merits
JUSTICIABILITY
"… It is critical to identify the decision and the nature of the attack on it. Unless there was a public law element in the decision and unless the allegation involves suggested breaches of duties or obligation owed as a matter of public law, the decision will not be reviewable."
(1) The nature and status of the particular public body concerned: this may be relevant because some such bodies may have an obviously greater public importance than others;
(2) The subject matter of the contract in question: this will include the status and nature of the other party or tenderers, along with the nature and scope of the works and the extent to which they might be described as "public-facing" and/or for the benefit of the public; also relevant is the source of funding; however, it must be borne in mind that as the contract put out to tender is being awarded by a public body, there will usually be some element of public funding and the contract will usually have some public connection;
(3) The source of the tender process used: that is to say, whether the particular process employed was specifically mandated to the defendant body, for example by statute or some other binding provision, as opposed to one essentially devised by that body; it will be relevant to know whether the body was purporting to comply with any statutory obligation in seeking tenders for this contract or whether it was simply empowered to do so;
(4) The nature of the challenge: this can take a variety of forms, including arguments that:
(a) there was a failure by the relevant body to comply with some aspect of the mandated process or some other statutory obligation relating to it;
(b) the particular policy or process adopted by it was itself unlawful in a public law sense;
(c) the actual decision in question involved fraud, corruption or bad faith on the part of the relevant body;
(d) in carrying out the process (in particular the scoring of rival bidders) the relevant body acted unfairly or irrationally.
"68. It is necessary to examine the actual bases of challenge to answer the relevant question. For this reason I have found it helpful to have detailed submissions the grounds of challenge so as to inform the decision on jurisdiction…
76. … The stated aims of the pre-qualification procedure are not and could not be criticised. It follows that the complaints on the basis of irrationality and unfairness are confined to the nuts and bolts of parts of the exercise and their effect on the individual application of the claimant.
77. Under those circumstances, I find that there are no sufficient public law aspects to the challenge to make it amenable to judicial review…I do not go so far as to say that the public law challenge to a tendering pre-qualification process on the basis of irrationality could never be entertained. I think that the circumstances under which it could be entertained must be rare."
THE CLAIMS MADE HERE
Generally
(1) the errors, even if properly so-called, are not significant;
(2) see the full version of this sub-paragraph in the Confidential Annexe;
(3) so far as causation is concerned, the proposition that Kenson could actually have achieved a sufficiently high notional revised score so as to exceed that of MHL was speculative and unlikely to be correct;
(4) part of Kenson's case rested on, or derived further support from, an alleged breach of the EU principle of "effectiveness"; but in truth, there is no cross-border interest element here. This is not a case where the PCR applies and in those circumstances, EU general principles such as effectiveness have no role to play.
Justiciability
ANALYSIS
Serious Issue to be tried
(1) The substantive claim is weak - see paragraphs 54 and 55 above;
(2) There is a strong argument that the claim is not justiciable at all - see paragraph 56 above;
(3) There was an unjustifiable delay on the part of Kenson in bringing this claim. The delay was compounded by the way in which the relevant papers were provided to the Council and MHL; see paragraphs 15-23 above. Delay affects the merits because it can be an impediment to the grant of permission (irrespective of merits) or the grant of final relief even if the claim otherwise succeeds.
Balance of Convenience
(1) Any trial of this claim is not likely to take place for at least 3-4 weeks and then a judgment needs to be produced. That is likely to be an underestimate of the delay to the commencement of the works if the injunction is granted. It is true that there is presently a match planned for 4 August. While this means that there may already be some delay, or compression of the timetable for the works I do not accept that by itself it means that they cannot now be done in this closed season. But if there is a 4 week (or more) delay in starting them and indeed in doing any further preparatory works (which the injunction sought would prevent), the strong likelihood is that they will not be done in this closed season at all; this outcome cannot be avoided by delaying such landscaping as is permitted to be done at a later stage; the delay is too great and moreover is partly contributed to by when Kenson actually started this claim and sought interim relief;
(2) MHL has already invested significant sums in preparatory works; I do not consider that these were done deliberately to create "facts on the ground" so as to prevent the injunction; it had to get on with preparatory works in any event since it had been awarded the contract (albeit only it and not the Council had signed it as at 9 May); there was debate before me over how the letter of intent works in terms of the limit of £50,000, but that debate did not really assist on this point;
(3) Equally, since the Council instructed that the contract be made available for signature by MHL on 17 April (albeit it was not collected until later) it cannot be said that this was a step taken by the Council deliberately to defeat any injunction application. None had been made at that point and there had been no further response after the Council's letter of 11 April;
(4) It is no answer to say that at worst the works will be delayed until next year. There is a genuine public interest in getting on with them now. There is an important public and social dimension to them – affording much needed and critical public access to the new stadium, combating anti-social behaviour and addressing current inadequate drainage. These are existing problems, not simply ones which would arise if the works were attempted during part of the football season; and if a delay until next year is sought to be avoided by allowing the delayed contract works to run on this year into the 2019/2020 season there would be all the problems identified by Mr Phelps. It is not known at the moment if MHL would be able to undertake the works next year if they had to be delayed until then because of this injunction and yet the substantive claim failed;
(5) The Tainting Argument is to the effect that it may be that the sort of errors alleged in respect of this procurement exercise may well be repeated in a separate ongoing procurement exercise run by the Council where, again, both Kenson and MHL are bidding. This is for a very much larger contract where the works are valued at about £108m. However it is being run by a different procurement team at the Council. Nonetheless, Kenson says that unless the injunction is granted in respect of the instant exercise it might lose the bid on the other one because of similar (and unlawful) errors in the scoring and in that context, its losses would be very large and less easy to quantify. In my judgment, this is a hopeless contention. It is no part of an assessment of this injunction application, concerned with this procurement exercise, to second guess, in a speculative fashion, how a separate procurement exercise might be carried out even before it has finished. The two exercises are quite different, carried out by different teams from the Council albeit that Kenson and MHL are both bidders there also; that is so even if some of the scoring themes used are the same as here. If Kenson loses in the next exercise and considers that the Council acted unlawfully, it can then bring a claim in that context;
(6) The weakness of the claim; see paragraph 58 above;
(7) The status quo, for present purposes is not that nothing has yet happened. It is that the contract has been awarded, preparations have already started and there is a critical start date which was the Monday after the hearing ie 13 May. It cannot therefore be said that an injunction to stop all of that is simply "holding the ring";
(8) For the sake of completeness, if damages were available, then one must consider also if they would be an adequate remedy for Kenson. They clearly would be, because their lost profit is easily calculable and there is nothing in the Tainting Argument. But as indicated above, I proceed on the footing that they are not.
CONCLUSION