BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Administrative Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Administrative Court) Decisions >> AQUIND Ltd, R (On the Application Of) v Secretary of State for Business, Energy and Industrial Strategy [2023] EWHC 98 (Admin) (24 January 2023) URL: http://www.bailii.org/ew/cases/EWHC/Admin/2023/98.html Cite as: [2023] EWHC 98 (Admin) |
[New search] [Printable PDF version] [Help]
KING'S BENCH DIVISION
ADMINISTRATIVE COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
THE KING (on the application of) AQUIND LIMITED |
Claimant |
|
- and - |
||
SECRETARY OF STATE FOR BUSINESS, ENERGY AND INDUSTRIAL STRATEGY |
Defendant |
|
- and - |
||
PORTSMOUTH CITY COUNCIL |
Interested Party |
____________________
Mr James Strachan KC and Mr Mark Westmoreland Smith (instructed by Government Legal Department) for the Defendant
Ms Celina Colquhoun (instructed by Portsmouth City Council) for the Interested Party
Hearing dates: 22 and 23 November 2022
____________________
Crown Copyright ©
Mrs Justice Lieven DBE :
Grounds of Challenge
(i) made or was misled by his officials into making a material error of fact as to the potential feasibility of Mannington as a grid connection point for the proposed development; (Ground 1a)
(ii) failed to take account of material evidence as to the feasibility of Mannington as a grid connection point; (Ground 1b)
(iii) failed to comply with the approach to decision-making mandated by section 104 PA; (Ground 2)
(iv) failed to apply his own NPS EN-1 policies to the proposed development; (Ground 3)
(v) failed in breach of his duty to take reasonable steps to inform himself as to the feasibility of Mannington so as to be able to discharge the requirements of section 104 PA; (Ground 4)
(vi) adopted a decision-making procedure which was procedurally unfair, causing the Claimant material prejudice; (Ground 5) and
(vii) failed to give proper, adequate and intelligible reasons for his decision (Ground 6).
The Facts
"2.4.2.4. Utilising the above outlined criteria for the assessment and selection of the substation connection options, NGET discounted seven of the ten substations. This discounting was based on the limited thermal capacity of substations and/or feasibility to extend them to provide the required thermal capacity, and difficulties with access for the marine cable onto the shore and/or potential onshore cable routes."
The Supplementary ES
a. 1.1.1.8 points to the linear nature of the project where the changing of one aspect impacts on another, with cross over between the choices of different elements;
b. 2.2.1.10 states that the Claimant carried out the assessment of alternatives, but the decision took into account information provided by National Grid regarding connection points;
c. Chapter 3 deals with the approach taken to the consideration of alternatives and 3.1.1.1 states the approach was whether there was a realistic prospect of delivering the same infrastructure capacity in the same timescale, mirroring the language in EN-1;
d. 4.1.2.7 refers to the cables being the largest part of the capital expenditure for the project, and therefore minimising the cable length being an important consideration;
e. 4.1.3 sets out initial discussions with NGET and 4.1.3.5 states:
"4.1.3.5 To the west of but within this search region, the 970MW Navitus Bay wind farm, off the Isle of Wight, was due to connect into Mannington substation. Further west, the FABLink 1400MW interconnector was due to connect into Exeter substation. NGET informed that the connection of a new interconnector in this region would have the effect of overloading the transmission lines, due to the power flows travelling from the west to east i.e. heading towards the major load centre of London."
f. Section 5 deals with the grid connection points (i.e. the substations) and the process of reaching Lovedean. Reference is made to the initial ten locations and at 5.1.1.4 it states three were selected to be taken forward to identify whether they were feasible connection points. 5.1.1.5 and 5.1.1.7 state:
"5.1.1.5. Whilst the position of NGET was that the other substations represented similar connection issues to the sites taken forward, save for Bolney which was excluded because that part of the NETS was already constrained due to existing and planned future connection, the Applicant's preliminary views at the time on the suitability of the remaining substations were as follows:
…
Mannington – the shared connection point with the 970MW Navitus Bay wind farm raised technical concerns;
…
5.1.1.7. As mentioned above at paragraphs 4.1.3.5 and 5.1.1.5, a connection agreement for the 970MW Navitus Bay offshore wind farm was in place in relation to the Mannington substation when the feasibility study was carried out, and therefore it was not considered to be suitable for the proposed connection. Although that project was later abandoned, the connection agreement remained in place with the developers of Navitus Bay offshore wind farm for some time following the feasibility study, during which significant progress was made advancing the proposals for Proposed Development. As a result it was not reasonable for the Applicant to re-consider the potential for a connection at Mannington at that later stage, and this was not considered further."
5.1.1.7 (above) is an important paragraph, which Mr Strachan heavily relies upon;
g. There is then a detailed consideration of Chickerell, which included issues around landfall locations to serve that substation.
25 January 2021 letter from National Grid Electricity Systems Operator
""In the case of AQUIND Interconnector, the CION did not progress with 7 existing substations. Bolney, Botley Wood, Fawley, Marchwood, Nursling, Mannington and Fleet these substations were not taken forward to the next stage of the CION due to the following reasons:
1. Options to the West of Lovedean required all or nearly all the same network reinforcements as a connection at Lovedean plus additional reinforcements to either get the power to Lovedean or reinforcements to the west to Exeter substation and as far northwards as Minety.
…
With the above considerations in mind these 7 substations were not taken forward for further assessment. This is because these sites would likely have resulted in more overall reinforcements, which would therefore lead to more environmental impact, and increased costs to the GB consumer. The extent of these additional works will vary from site to site but may involve new overhead lines or cables, additional operational equipment and multiple substation extensions in addition to the works identified for a connection at Lovedean." [emphasis added]
"The Applicant understands that all of the sub-stations considered would have required system reinforcement because of the significant flows of power generated or imported in the South-West and South-East of England to load centres north of the "SC1" planning boundary (i.e. London) in any case and there was no connection location that would not have been encumbered by requirements for such additional works. While such additional works to be carried out by National Grid, would have been similar in nature, all substations, which were not taken for further assessment, would have presented their specific challenges and additional costs."
"Mannington sub-station may not be suitable for extension at all due to the position of existing Static Var Compensation (SVC) within the substation and because there are residential properties in close proximity on three sides. It is also relevant that Navitus Bay offshore wind farm of nearly 1GW capacity was planned to connect there. In the Applicant's opinion, connecting to Mannington sub-station would have been deemed not feasible."
"CONCLUSION
Among all the sub-substations along the south coast, Lovedean provides the most direct and least constrained route to evacuate power from AQUIND Interconnector towards consumption centres in the south as well as to the north, including London, as well as to supply AQUIND Interconnector with power since most generation is further north.
The selection of the other sub-stations would have resulted in the need for more extensive additional works which would increase the cost of such works to both the National Grid and the project and the time that it would take for the interconnector to become operational."
The Examining Authority's Report
a. a number of objections ("Relevant Representations") argued that the ES did not provide a robust consideration of alternatives (5.4.15);
b. NGESO confirmed the reasons behind discounting the other substations (5.4.24);
c. At 5.4.31 the ExA said:
"The ExA is mindful of references to the consideration of alternatives in the NPS EN-1 including, at paragraph 4.4.3 (bullet 8), that where third parties are proposing an alternative, it is for them to provide the evidence for its suitability. In such instances it is not necessarily expected that the Applicant would have assessed every alternative put forward by another party. In this case, the Applicant has detailed a considered approach and provided additional commentary [REP1 – 152] to explain its position. Whilst offering criticism of the Applicant's approach, no party has offered substantive reasoned evidence to demonstrate that an alternative would be technically feasible or would lead to lesser environmental effects compared to the Proposed Development." [emphasis added]
a. Temporary significant impacts on highways and traffic flows, which could be reduced to acceptable levels (9.2.17-19);
b. Some minor temporary noise and vibration effects (9.2.15);
c. A minor negative socio-economic effect (9.2.31);
d. Some adverse significant landscape and visual effects on the setting of the National Park and the landfall location. The ExA gave these impacts moderate weight (9.2.54);
e. Less than substantial harm to two heritage assets, to which the ExA gave considerable weight (9.2.62).
"9.3.10. The ExA is satisfied that the identified adverse effects would be mitigated as far as is reasonably practicable and that the necessary measures could be properly secured through the Recommended DCO and the associated control documents, such that the identified significant adverse effects would be largely time-limited and reversible.
9.3.11. Taking into account all relevant policy, the ExA concludes that the matters that are identified as disbenefits do not outweigh the significant benefits that are described, either alone or when considered together. The ExA therefore considers that the final balance indicates strongly in favour of granting development consent."
"overall, the need case for the Proposed Development strongly outweighs the identified benefits."
Third Information Request
"4. The Secretary of State notes that the document Environmental Statement Addendum-Appendix 3-Supplementary Alternatives Chapter states that ten existing substations were evaluated as part of a feasibility study carried out by National Grid Electricity Transmission. One of the substations which was assessed in the feasibility study was the substation at Mannington. That substation was not considered to be suitable for the proposed connection because, at the time of the feasibility study, there was already a connection agreement in place for the proposed Navitus Bay offshore wind farm. The Addendum notes that the Navitus Bay project was subsequently abandoned but the connection agreement remained in place "for some time following the feasibility study" during which "significant progress" was made on the AQUIND interconnector proposal meaning that it was not reasonable for the Applicant to re-consider the potential for a connection at Mannington at that later stage.
5. The Secretary of State is aware that the decision to refuse development consent for the Navitus Bay development was taken on 11 September 2015. He would be grateful for clarification from the Applicant in respect of how long the connection agreement for the Navitus Bay development remained in place following that refusal, what enquiries the Applicant made in respect of the potential use of the Mannington substation following the refusal of the Navitus Bay project and at what stage the development of the AQUIND interconnector project was when the connection agreement ended."
"In addition to NG ESOs reasons for why Mannington Substation was not taken forward for systems analysis, as is detailed at paragraph 5.1.1.5 of the Supplementary Alternatives Chapter the Applicant's preliminary view at the time on the suitability of Mannington Substation was that the shared connection point with the 970MW Navitus Bay offshore wind farm raised technical concerns."
"2.12. In this regard, having re-examined the precise chronology and to assist with explaining the Applicant's position that it was not reasonable and/or necessary to further consider Mannington Substation following the connection agreement for Navitus Bay offshore wind farm being confirmed to no longer be in place, the timeline was that the connection agreement remained for some time after the Feasibility Study request in December 2014.
2.13. During this period the significant progress made advancing the proposals for Proposed Development was the preparation of the Feasibility Study itself together with the optioneering work that was undertaken by the Applicant alongside this, and which is most clearly detailed in Chapter 5 of the Supplementary Alternatives Chapter in relation to assessment of the grid connection points and paragraph 2.4.3 of the Alternatives Chapter in relation to the consideration of the potential landfall sites.
2.14. Following the refusal of development consent for the Navitus Bay offshore wind farm, the Applicant made enquiries with NGET on 14th October 2015 regarding the impact of that refusal on the Feasibility Study which was being undertaken and known to be near completion. The Applicant has not been able to locate a response to this query, though it was understood by the Applicant that at this time that refusal would have been subject to the six week legal challenge period provided for by section 118 of the Act and as such the connection agreement for Navitus Bay would have remained in place.
2.15. At a meeting with NGET in January 2016, following the issue of the final version of the Feasibility Study report and prior to the further CION processes which led to the issue of the CION in March 2016, it was noted that the Navitus Bay offshore wind farm had formally been removed from the list of future connections. It was therefore at this point in time that the Applicant was aware that the connection agreement for Navitus Bay offshore wind farm to Mannington Substation was no longer in place.
2.16. As is noted above, the Feasibility Study including the cost benefit analysis exercise was completed in November 2015, with the final version of the Feasibility Study report issued in January 2016. To include Mannington Substation in the shortlist of grid connection points for the Feasibility Study at this stage would have required the Feasibility Study process to restart, resulting in a further 10-12 months of work and the Applicant would not have been able to progress with its regulatory and other submissions until the further process was complete. This would have meant that the place of the Proposed Development in the list of future connections would have been lost. In effect, the Proposed Development would have been significantly delayed and placed at a commercial disadvantage. It would also have resulted in the incurrence of significant cost in the form of NGET's fees and cost to the Applicant. The costs incurred to date for the Feasibility Study would also have become abortive.
2.17. It was the view of the Applicant that for it to be reasonable to restart the Feasibility Study exercise to further consider the potential for a connection to Mannington Substation, noting the significant delay and cost this would have incurred, there would have needed to be a convincing justification for why Mannington Substation may have been preferable to Lovedean Substation.
2.18. As is noted above, NGET had already identified that Mannington Substation was not preferable to Lovedean, on the basis that additional reinforcements would have been required to either get the power to Lovedean or reinforcements to the west to Exeter substation and as far northwards as Minety and that this would have led to more environmental impact, and increased costs to the GB consumer."
The Decision Letter
"3.4. In relation to the Application, the Secretary of State has had regard to the Overarching National Policy Statement for Energy ("NPS EN-1"). The Secretary of State has made his decision on the basis that making the Order would not be in accordance with his obligations under the Planning Act 2008.
3.5. The Secretary of State notes that the ExA also considered at length the question of the planning balance under section 104(7) of the Planning Act 2008 i.e. whether the need for the proposed Development outweighed the planning harms inherent in the scheme and concluded that this was the case. The Secretary of State notes that the ExA identified planning harms associated with the scheme, which include less than substantial harm to the Fort Cumberland Scheduled Monument and the Grade II listed cottage known as Scotland, as well as impacts on tourism receptors, sports pitches and the Victorious Festival. The compulsory purchase powers sought by the Applicant would also result in private losses and could cause delay to the North Portsea Island Coastal Defence Scheme due to the overlapping of construction compound areas between this scheme and the proposed Development. The proposed development also has other potential adverse effects which are summarised in the ExA's report in the consideration of the planning balance [ER 9.3]. The Secretary of State agrees these adverse effects weigh against the proposed development.
3.6. The Secretary of State has had regard to the case law in relation to the consideration of alternatives and is of the view that the alternatives, and in particular the Mannington substation initially considered by the Applicant, is an important and relevant consideration under s104(2)(d) of the Planning Act 2008. Given the adverse effects arising from the project and which have been noted above, and in particular the combination of impacts that result from the proposed landfall in an urban location, the Secretary of State considers that in the circumstances of this particular application it is exceptionally necessary to consider whether sufficient consideration has been given to whether there are more appropriate alternatives to the proposed route. In particular, consideration needs to be given to the alternative substations initially identified by the Applicant (and therefore alternative onshore routes avoiding the above harms) and whether these were adequately considered to determine whether the potential harms caused by the development from the selected route could have been avoided or reduced. In this regard the Secretary of State disagrees with the ExA's conclusion in relation to the consideration of alternatives and, as set out below, considers that there was a failure to adequately consider the original alternatives identified by the Applicant, such that it is not possible to conclude that the need for and benefits of the proposed Development would outweigh its impacts."
"With regard to the location of the substation at Lovedean, the Secretary of State notes that National Grid Electricity System Operator's [sic] ("NGESO") submitted a representation to the examination confirming the reasons behind discounting the other substations [ER 5.4.24]."
"4.8. The Secretary of State disagrees with the ExA's conclusion on this matter and considers that in this instance insufficient consideration was given by the Applicant to the alternative connection point at Mannington substation. The Secretary of State notes that the document Environmental Statement Addendum-Appendix 3-Supplementary Alternatives Chapter states that ten existing substations were evaluated as part of a feasibility study carried out by National Grid Electricity Transmission ("NGET"). The Secretary of State understands that the Applicant submitted a request to NGET for a Feasibility Study in December 2014, and that the final version of the Feasibility Study was issued in January 2016. The Mannington Substation was assessed as part of this Feasibility Study. The Feasibility Study notes that the substation was not considered to be suitable for the proposed connection because, at the time, there was already a connection agreement in place for the proposed Navitus Bay offshore wind farm. The Addendum notes that the Navitus Bay offshore wind farm project was subsequently abandoned but the grid connection agreement remained in place "for some time following the feasibility study" during which "significant progress" was made on the AQUIND interconnector project meaning that it was not reasonable, having regard to costs and delay, for the Applicant to re-consider the potential for a connection at Mannington at that later stage.
4.9. The decision to refuse development consent for the Navitus Bay development was taken by the Department of Energy and Climate Change on 11 September 2015. The Secretary of State requested information from the Applicant on 4 November 2021 in respect of how long the connection agreement for the Navitus Bay development remained in place following that refusal, what enquiries the Applicant made in respect of the potential use of the Mannington substation following the refusal of the Navitus Bay project, and at what stage the development of the proposed AQUIND Interconnector project was when the connection agreement ended.
4.10. The Applicant submitted their response to this request on 18 November 2021. At paragraph 2.6 of this response, the Applicant noted that the letter submitted by NG ESO on 25 January 2021 stated that "Options to the West of Lovedean required all or nearly all the same network reinforcements to either get the power to Lovedean or reinforcements to the west to Exeter substation and as far northwards as Minety", and that "these sites would likely have resulted in more overall reinforcements, which would therefore lead to more environmental impact, and increased costs to the GB consumer". At paragraph 2.7 of its response, the Applicant noted that in addition to these reasons from NG ESO as to why Mannington Substation was not taken forward for systems analysis, the shared connection point with the 970MW Navitus Bay offshore wind farm raised technical concerns around the suitability of Mannington Substation as well.
4.11. The Applicant advises that the connection agreement for the Navitus Bay offshore wind farm at Mannington Substation remained for some time after the Feasibility Study request in December 2014. The Applicant goes on to state at paragraph 2.14 of their response that, following refusal of development consent for the Navitus Bay offshore wind farm, the Applicant made enquiries with NGET on 14 October 2015 regarding the impact of that refusal on their Feasibility Study which was being undertaken and known to be near completion. However, the Applicant has not been able to locate a response to this enquiry, though the Applicant notes that it was understood that the refusal would have been subject to the six-week legal challenge period provided for by section 118 of the Planning Act 2008 and as such the connection agreement for Navitus Bay offshore wind farm would have remained in place. The Applicant was aware by January 2016 that the connection agreement was no longer in place (paragraph 2.15 of their response). The Application was submitted on 19 November 2019."
"The Secretary of State considers that the Applicant has access to any relevant information relating to discussions between the Applicant and NGET, and therefore considers that the Applicant would have submitted all available and relevant information on this matter and that there is therefore no requirement to seek views from NGET. The Applicant has had the opportunity to address the issue of this alternative and could have sought any information it required from NGET. It is the Secretary of State's view that it is not appropriate in the circumstances to further delay the decision for this purpose."
"4.16. The Secretary of State considers that at the point in the timeline (i.e. 11 September 2015) when consent for the Navitus Bay offshore wind farm was refused, that the Mannington Substation option should have been adequately explored. The Applicant states that it raised its enquiries with NGET around the impact of the refusal for Navitus Bay offshore wind farm on the Feasibility Study on 14 October 2015. At this point in time, the Feasibility Study had not yet been completed, and the six-week legal challenge period for Navitus Bay offshore wind farm was nine days away was expiry on 23 October 2015. The Secretary of State also notes that the Applicant's inability to provide a response to the enquiries it raised with NGET on 14 October 2015 regarding the impact on the Feasibility Study, means that the Secretary of State is unable to review in full the discussions that took place regarding this matter at the time.
4.17. The Secretary of State notes the Applicant's view that it was not reasonable or necessary to further consider Mannington Substation as the grid connection point for the proposed development following the completion of the Feasibility Study. However, the Secretary of State considers that the Applicant should have pursued further the option to include Mannington Substation in the Feasibility Study given that the Applicant was aware that consent had been refused for the Navitus Bay offshore wind farm. The Secretary of State notes that the Applicant understood the potential importance of the refusal of consent for Navitus Bay offshore wind farm at the time, as it raised queries with NGET regarding the impact of this on the Feasibility Study. The Secretary of State considers that the Applicant has provided insufficient detail as to why further investigation into Mannington Substation was not undertaken. Whilst the Secretary of State understands that this could have resulted in further work for the Applicant, and the Applicant may not have been able to progress with regulatory and other submissions until that process was complete, the Secretary of State considers that the potential adverse effects of the proposed development (as identified by the ExA) necessitate the adequate consideration of those alternatives that the Applicant had identified. The Secretary of State also notes that the refusal of Navitus Bay was in September 2015 and the Application would not be made until over four years later.
4.18. As noted above, NPS EN-1 states that potential alternatives should be identified wherever possible before an application is made to the Secretary of State so as to allow appropriate consultation and the development of suitable evidence base in relation to any alternatives which are particularly relevant. However, the Secretary of State disagrees with the ExA's conclusion on this matter and considers that the failure to adequately consider the alternative of the Mannington Substation as a connection point is a material consideration. The Secretary of State consideration that this weighs significantly against the proposed Development as he is unable to conclude that the proposed route is justified.
4.19. The Secretary of State also acknowledges the implications of the Applicant's consideration of alternatives and the compulsory acquisition powers it seeks as part of the Application. Blake Morgan LLP submitted comments to the Secretary of State on behalf of landowners the Carpenters on 15 December 2021 which raised the concerns around the possibility of an alternative connection point at Mannington Substation and the implications this has for the compulsory acquisition of the Carpenters' land. In their comments of 15 December 20201, Portsmouth City Council noted its concerns that the Applicant had not made any assessment of the private loss to be suffered in consequence of the different options available and had not weighed that loss against the public benefits of the proposed development.
4.20. The Secretary of State acknowledges that alternatives are material in exceptional circumstances only. The Secretary of State considers that this test is met given the combination of adverse impacts from the proposed route through a very densely populated urban area. He considers that the change in circumstances relating to Mannington Substation was known by the Applicant at a sufficiently early stage of the Feasibility Study, and that the change was of sufficient importance and scale. Therefore, further investigation should have been undertaken to ensure that sufficient evidence was available in its application documents to support the preferred choice of route taken forward by the Applicant.
4.21. The Secretary of State acknowledges that if the Applicant had investigated a connection at Mannington Substation further, it may have concluded that it was not a feasible option. However, in the absence of sufficient evidence on this matter, the Secretary of State cannot grant consent for the AQUIND Interconnector project taking into account the adverse effects identified by the ExA and the possibility that a connection point at Mannington Substation might potentially have resulted in less adverse impact."
a. DL 7.1 correctly states that for applications under s.104 PA the primary consideration is the policy set out in the NPS;
b. DL7.2 summarises the harm found by the ExA and agrees with their summary (Report 9.3.10), but then says "… a significant number of adverse effects remain. These remaining impacts, in the view of the SoS, make the consideration of alternatives exceptionally relevant to the SoS's decision in this case."
c. DL7.3 and 7.4 state:
"7.3. In addition to these impacts identified by the ExA, the Secretary of State considers that the Applicant's failure to adequately assess the feasibility of Mannington Substation as an alternative connection point, means that the planning balance weighs against the Order being made, given the proposed development's obvious impacts on the City of Portsmouth and the possibility that a connection at Mannington Substation might have resulted in less adverse impact.
7.4. Although the ExA found that the benefits of the proposed development would outweigh its adverse effects, the Secretary of State disagrees with this conclusion, as the alternative of a connection to the Mannington Substation has not been properly assessed and therefore he cannot conclude that the proposed route has been justified and determine the need for and benefits of the proposed Development would outweigh its impacts."
The law and policy
"104 Decisions in cases where national policy statement has effect
(1) This section applies in relation to an application for an order granting development consent if a national policy statement has effect in relation to development of the description to which the application relates.
(2) In deciding the application the Secretary of State must have regard to—
(a) any national policy statement which has effect in relation to development of the description to which the application relates (a "relevant national policy statement"),
…
(d) any other matters which the Secretary of State thinks are both important and relevant to the Secretary of State's decision.
(3) The Secretary of State must decide the application in accordance with any relevant national policy statement, except to the extent that one or more of subsections (4) to (8) applies.
(4) This subsection applies if the Secretary of State is satisfied that deciding the application in accordance with any relevant national policy statement would lead to the United Kingdom being in breach of any of its international obligations.
(5) This subsection applies if the Secretary of State is satisfied that deciding the application in accordance with any relevant national policy statement would lead to the Secretary of State being in breach of any duty imposed on the Secretary of State by or under any enactment.
(6) This subsection applies if the Secretary of State is satisfied that deciding the application in accordance with any relevant national policy statement would be unlawful by virtue of any enactment.
(7) This subsection applies if the Secretary of State is satisfied that the adverse impact of the proposed development would outweigh its benefits.
…"
"Given the level and urgency of need for infrastructure of the types covered by the energy NPSs set out in Part 3 of this NPS, the IPC should start with a presumption in favour of granting consent to applications for energy NSIPs. That presumption applies unless any more specific and relevant policies set out in the relevant NPSs clearly indicate that consent should be refused. The presumption is also subject to the provisions of the Planning Act 2008 referred to at paragraph 1.1.2 of this NPS."
"As in any planning case, the relevance or otherwise to the decision-making process of the existence (or alleged existence) of alternatives to the proposed development is in the first instance a matter of law, detailed guidance on which falls outside the scope of this NPS. From a policy perspective this NPS does not contain any general requirement to consider alternatives or to establish whether the proposed project represents the best option."
"However applicants are obliged to include in their ES, as a matter of fact, information about the main alternatives they have studied. This should include an indication of the main reasons for the applicant's choice, taking into account the environmental, social and economic effects and including, where relevant, technical and commercial feasibility; in some circumstances there are specific legislative requirements, notably under the Habitats Directive, for the IPC to consider alternatives. These should also be identified in the ES by the applicant; and in some circumstances, the relevant energy NPSs may impose a policy requirement to consider alternatives (as this NPS does in Sections 5.3, 5.7 and 5.9)."
"Where there is a policy or legal requirement to consider alternatives the applicant should describe the alternatives considered in compliance with these requirements. Given the level of urgency of need for new energy infrastructure, the IPC should, subject to any legal requirements (e.g. under the Habitats Directive) which indicate otherwise, be guided by the following principles when deciding what weight should be given to alternatives:
1. the consideration of alternatives in order to comply with policy requirements should be carried out in a proportionate manner;
2. the IPC should be guided in considering alternative proposals by whether there is a realistic prospect of the alternative delivering the same infrastructure capacity (including energy security and climate change benefits) in the same timescale as the proposed development;
3. …
4. alternatives not among the main alternatives studied by the applicant (as reflected in the ES) should only be considered to the extent that the IPC thinks they are both important and relevant to its decision;
5. as the IPC must decide an application in accordance with the relevant NPS (subject to the exceptions set out in the Planning Act 2008), if the IPC concludes that a decision to grant consent to a hypothetical alternative proposal would not be in accordance with the policies set out in the relevant NPS, the existence of that alternative is unlikely to be important and relevant to the IPC's decision;
6. alternative proposals which mean the necessary development could not proceed, for example because the alternative proposals are not commercially viable or alternative proposals for sites would not be physically suitable, can be excluded on the grounds that they are not important and relevant to the IPC's decision;
7. alternative proposals which are vague or inchoate can be excluded on the grounds that they are not important and relevant to the IPC's decision; and
8. it is intended that potential alternatives to a proposed development should, wherever possible, be identified before an application is made to the IPC in respect of it (so as to allow appropriate consultation and the development of a suitable evidence base in relation to any alternatives which are particularly relevant). Therefore where an alternative is first put forward by a third party after an application has been made, the IPC may place the onus on the person proposing the alternative to provide the evidence for its suitability as such as the IPC should not necessarily expect the applicant to have assessed it."
The Grounds
Ground One
a. There is a mistake on an existing fact;
b. The fact is uncontentious;
c. The claimant must not have been responsible for the mistake;
d. The mistake must have played a material part in the tribunal's reasoning.
Grounds Two and Three
"First, the purpose of the balancing exercise in section 104(7) is to establish whether an exception should be made to the requirement in section 104(3) that an application for development consent must be decided "in accordance with any relevant national policy statement". The exercise involves a straightforward balance, setting "adverse impact" against "benefits". It is not expressed as excluding considerations arising from national policy itself. It does not restrain the Secretary of State from bringing into account, and giving due weight to, the need for a particular type of infrastructure as recognised in a national policy statement, and setting it against any harm the development would cause (see the judgment of Sales L.J. in Thames Blue Green Economy Ltd., at paragraph 16)."
Ground Four
"the question for the court is, did the Secretary of State ask himself the right question and take reasonable steps to acquaint himself with the relevant information to enable him to answer it correctly?"
"The general principles on the Tameside duty were summarised by Haddon-Cave J in R (Plantagenet Alliance Ltd) v Secretary of State for Justice [2014] EWHC 1662 (Admin) at paras. 99-100. In that passage, having referred to the speech of Lord Diplock in Tameside , Haddon-Cave J summarised the relevant principles which are to be derived from authorities since Tameside itself as follows. First, the obligation on the decision-maker is only to take such steps to inform himself as are reasonable. Secondly, subject to a Wednesbury challenge, it is for the public body and not the court to decide upon the manner and intensity of enquiry to be undertaken: see R (Khatun) v Newham LBC [2004] EWCA Civ 55, [2005] QB 37 , at para. 35 (Laws LJ). Thirdly, the court should not intervene merely because it considers that further enquiries would have been sensible or desirable. It should intervene only if no reasonable authority could have been satisfied on the basis of the enquiries made that it possessed the information necessary for its decision. Fourthly, the court should establish what material was before the authority and should only strike down a decision not to make further enquiries if no reasonable authority possessed of that material could suppose that the enquiries they had made were sufficient. Fifthly, the principle that the decision-maker must call his own attention to considerations relevant to his decision, a duty which in practice may require him to consult outside bodies with a particular knowledge or involvement in the case, does not spring from a duty of procedural fairness to the applicant but rather from the Secretary of State's duty so to inform himself as to arrive at a rational conclusion. Sixthly, the wider the discretion conferred on the Secretary of State, the more important it must be that he has all the relevant material to enable him properly to exercise it."
Ground Five
"Procedure after completion of examination
19. …
(3) If after the completion of the Examining authority's examination, the decision-maker—
(a) differs from the Examining authority on any matter of fact mentioned in, or appearing to the decision-maker to be material to, a conclusion reached by the Examining authority; or
(b) takes into consideration any new evidence or new matter of fact, and is for that reason disposed to disagree with a recommendation made by the Examining authority, the decision-maker shall not come to a decision which is at variance with that recommendation without—
(i) notifying all interested parties of the decision-maker's disagreement and the reasons for it; and
(ii) giving them an opportunity of making representations in writing to the decision-maker in respect of any new evidence or new matter of fact."
Ground Six
"The reasons for a decision must be intelligible and they must be adequate. They must enable the reader to understand why the matter was decided as it was and what conclusions were reached on the "principal important controversial issues", disclosing how any issue of law or fact was resolved. Reasons can be briefly stated, the degree of particularity required depending entirely on the nature of the issues falling for decision. The reasoning must not give rise to a substantial doubt as to whether the decision-maker erred in law, for example by misunderstanding some relevant policy or some other important matter or by failing to reach a rational decision on relevant grounds. But such adverse inference will not readily be drawn. The reasons need refer only to the main issues in the dispute, not to every material consideration. They should enable disappointed developers to assess their prospects of obtaining some alternative development permission, or, as the case may be, their unsuccessful opponents to understand how the policy or approach underlying the grant of permission may impact upon future such applications. Decision letters must be read in a straightforward manner, recognising that they are addressed to parties well aware of the issues involved and the arguments advanced. A reasons challenge will only succeed if the party aggrieved can satisfy the court that he has genuinely been substantially prejudiced by the failure to provide an adequately reasoned decision."