BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just Β£5, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Commercial Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Commercial Court) Decisions >> Torch Offshore Llc & Anor v Cable Shipping Inc. [2004] EWHC 787 (Comm) (07 April 2004) URL: http://www.bailii.org/ew/cases/EWHC/Comm/2004/787.html Cite as: [2004] 2 CLC 433, [2004] 2 All ER (Comm) 365, [2004] EWHC 787 (Comm), [2004] 2 Lloyd's Rep 446 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
COMMERCIAL COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
TORCH OFFSHORE LLC & ANR. |
Claimant |
|
- and - |
||
CABLE SHIPPING INC. |
Defendant |
____________________
Mr N Meeson, QC and Mr P Ferrer (instructed by Marine Legal Services, Solicitors) for the Defendant
Hearing dates: 5th and 6th April 2004
____________________
Crown Copyright ©
Mr Justice Cooke :
Introduction
i) A representation that the deck strength of the vessel throughout its clear deck area was 10mt/sqm (the first representation); andii) A representation that the vessel's deck could support, without the need for supporting pillars below deck, the concentrated loads imposed by Torch's modular pipe-laying system (MLS), the details of which had been set out in a fax dated 28th September 2001 from Torch's chief engineer, Mr Lecarme to the Owners (the second representation).
i) Whether the Tribunal erred in law in failing to apply the correct legal test in deciding that the first misrepresentation did not induce Torch to enter the charter.ii) Whether the Tribunal erred in law in deciding that the second misrepresentation did not induce Torch to enter the charterparty if, contrary to its primary submission under section 68, the arbitrator did address the issue.
iii) Whether the arbitrator erred in law in deciding that Torch was barred from rescinding the contract by reason of lapse of time.
The Background Facts as found by the Arbitrator
i) About 3.8 mt/sqm in way of the 20 metre insert between existing frames 34 and 35.ii) About 6 mt/sqm from frame 35 to frame 43.
iii) 10 mt/sqm from frame 43 aft to the transom.
The Test under section 68 of the Arbitration Act 1996
"68(1) A party to arbitral proceedings may . apply to the Court challenging an award in the proceedings on the ground of serious irregularity affecting the Tribunal, the proceedings or the award. A party may lose the right to object (see section 73) and the right to apply subject to the restrictions in sections 70(2) and (3).
(2) Serious irregularity means an irregularity of one or more of the following kinds which the Court considers has caused or will cause substantial injustice to the applicant.
.
(d) Failure by the Tribunal to deal with all the issues that were put to it."
"The Court does not have a general supervisory jurisdiction over arbitrations. We have listed the specific cases where a challenge can be made under this clause. The test of "substantial injustice" is intended to be applied by way of support for arbitral process, not by way of interference with that process. Thus it is only in those cases where it can be said that what has happened is so far removed from what could reasonably be expected of the arbitral process that we would expect the Court to take action. The test is not what would have happened had the matter been litigated. To apply such a test would be to ignore the fact that the parties have agreed to arbitrate, not litigate. Having chosen arbitration, the parties cannot validly complain of substantial injustice unless what has happened cannot on any view be defended as an acceptable consequence of that choice."
The sub-section has been considered in a number of authorities and I was referred to The Petro Ranger [2001] 2 LLR 348 where Cresswell J set out the effect of that report on the approach of the Court to section 68 of the 1996 Act. I was also referred to Hussman v Al Ameen [2000] 2 LLR 277 where Thomas J (as he then was) said that section 68(2)(d) did not require a Tribunal to set out each step by which it reached its conclusion or deal with each point made by a party in an arbitration. A failure in that respect was not a failure to deal with an issue that was put to it, although it might amount to a criticism of the reasoning. By contrast I was referred to the decision of Toulson J in Ascot Commodities v Olam [2002] CLC 277 where he held that a central point raised by a party which had not been dealt with by a Tribunal did amount to a serious irregularity and, because the issue was central, it was likely to give rise to serious injustice.
Sections 57 and 70 of the Arbitration Act 1996
"(1) The following provisions apply to an application for appeal under section 67, 68 or 69.
(2) An application or appeal may not be brought if the applicant or appellant has not first exhausted -
(b) Any available recourse under section 57 (correction of award or additional award)."
"The Tribunal may on its own initiative or on the application of a party
(a) correct an award so as to remove any clerical mistake or error arising from an accidental slip or omission or clarify or remove any ambiguity in the award, or(b) make an additional award in respect of any claim (including a claim for interest or costs) which was presented to the Tribunal but which was not dealt with in the award ..".
Section 68 the Reasoning of the Arbitrator
i) The fax of September 28th 2001 included the following question:-"2 Deck loading: the mentioned equipment heaviest concentrated load is the combination of a reel + product + under roller that is to say about 280 Te spread over an area of about 50 sqm. Does the ship requires under deck pillars to accept this load (maximum 3 reels)."ii) To this the answer was given in the e-mail of lst October:
"Regarding your point 2, the deck loading from the frame 31 to the aft is 10 ton/sqm. No pillars are required to keep this load."
"In Monsieur Lecarme's statement he said that it was crucial that there was a large deck area of over 1,000 square metres and that it had a deck strength of ten tonnes per square metre because he considered that deck strengths of this order 'was a minimum requirement for the type of sub-sea construction vessels sought by the charterers to enter the deep water market.' He also explained that he considered it important to establish where the pillars would need to be installed because if so, that would add to the costs which would be for the charterers' account, cause delays and also reduce the space available below deck for carrying equipment. In his statement he also said that if he had known of the true deck strength of the vessel and that additional pillars would have to be installed to support the MLS, then "I have no doubt that I would have advised . that the ship was not suitable" and that the charterers would not have entered into the charterparty."
The Section 69 Application for Permission to appeal
"
(3) Leave to appeal shall be given only if the Court is satisfied:
(a) that the determination of the question will substantially affect the rights of one or more of the parties,
(b) that the question is one which the tribunal was asked to determine
(c) that, on the basis of the findings of fact in the award
(i) the decision of the tribunal on the question is obviously wrong,or(ii) the question is one of general public importance and the decision of the tribunal is at least open to serious doubt, and
(d) that, despite the agreement of the parties to resolve the matter by arbitration, it is just and proper in all the circumstances for the court to determine the question."
"The Midnight Hunter was a large and, after her conversion, expensive and very sophisticated vessel. The charterers would have had many considerations in mind in deciding to charter her. No doubt the deck strength was in the words of Mr Justice Rix "a factor which is observed or considered by a plaintiff, or even supports or encourages a decision". However for all the above reasons, I was not persuaded that the warranted deck strength could properly be categorised as "a real and substantial part" of what induced them to enter into the charterparty. There was therefore no effective misrepresentation that would allow rescission."
Conclusion