BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £5, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Commercial Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Commercial Court) Decisions >> Global Technologies Racing Ltd v 5 West (t/a Alex Thomson Racing) [2020] EWHC 3334 (Comm) (04 December 2020) URL: http://www.bailii.org/ew/cases/EWHC/Comm/2020/3334.html Cite as: [2020] EWHC 3334 (Comm) |
[New search] [Printable PDF version] [Help]
Case No: LM-2018-000220 |
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
LONDON CIRCUIT COMMERCIAL COURT (QBD)
B e f o r e :
____________________
GLOBAL TECHNOLOGIES RACING LIMITED |
Claimant |
|
- and – |
||
5 WEST LIMITED (t/a ALEX THOMSON RACING) |
Defendant |
____________________
PETER LAND (instructed by Lester Aldridge LLP ) for the Defendant
Hearing dates: 13, 14, 15, 16, 17 and 20 July 2020
____________________
Crown Copyright ©
His Honour Judge Pearce:
Introduction
The Trial
(a) For the Claimant
i. Jamie Keogh, former Commercial Director of the Claimant, whose statement is dated 8 May 2020;
ii. Matt Easton, now Chief Engineer of the Claimant but at the time the Claimant's Lead Composite Design Engineer, whose statement is dated 8 May 2020; and
iii. Gareth Robinson, Technical and Commercial Director of the Claimant, whose statement is dated 8 May 2020.
(b) For the Defendant
i. Ryan Taylor, a sub-contractor employed by the Defendant, in a statement dated 8 May 2020;
ii. Alex Thomson, whose statements are dated 8 May 2020 and 22 May 2020; and
iii. Ross Daniel, Technical Director of the Defendant, whose statements are again dated 8 May 2020 and 22 May 2020.
Each of them was cross examined.
The Contract
"Carbon fibre curved boards with tips
- Geometry as per 3D Model of 07/06/16; HB60_DSS_2016_3105_stp.stp
- Structure based on 2D structural drawing
- Material – Carbon Fibre prepreg Uni direction T800, T800 Nano, M40J and T700n woven
- Process - half moulded using Autoclave/vac, CMC machined lower face
- Finish - delta surface film for the entire length of the shaft on both sides. Unfinished from start of elbow to end of tip.
- Delivery 8th August 2016."
(a) That the Claimant would produce and supply the hydrofoils "to agreed timescale and highest standard of workmanship;"
(b) That the Claimant would ensure that the Defendant's representative, Ryan Taylor, "is fully integrated into the build process and given full transparency throughout the build."
(a) £41,666.67 plus VAT on 27 July 2016;
(b) £41,666.67 plus VAT on 27 July 2016;
(c) £36,266.66 plus VAT on 4 August 2016.
(a) First place; £50,000;
(b) Second place: £30,000;
(c) Third place: £20,000.
An Overview of the Design and Engineering
The top of this diagram equates to the upper and inboard surface of the photograph above taking compressive force and hence is described at times as the compression side. Correspondingly the bottom is that taking the greatest tensile forces and is called the tension side. The leading edge, that which is nearest the front of the boat, is to the right and the trailing edge to the left.
(The seven layers shown are lettered in black from a to g, though it is not easy to make this out.)
With no shear connection, one can see how the laminates tend to debond creating a ragged end of separate layers, whereas with good shear connection, the laminates stay bonded in a neat line. The capacity of the material to do this is called inter-laminar shear strength.
(a) The compressive force is greatest on upper side of the foil (letter a in the diagram referred to at paragraph 43 above);
(b) The tensile forces are greatest on the lower side (letter g);
(c) The compressive and tensile forces reduce as one moves from the outer surface to the middle, such that, at a point known as the neutral axis (letter d above), both forces are zero;
(d) The shear forces are maximum at the neutral axis.
"4.2.3 A laminate is composed of fibres and matrix. We could start by thinking of the fibres as being like a ponytail and the matrix as a strong hair-gel.
4.2.4 If we want to carry a load in tension, say lifting a bucket out of a well, we could cut off the ponytail, attach our load to each end then pull. The load we could carry would be proportional to the number of hairs, and aside from the difficulty of attaching the load to the ends of the hairs, we wouldn't really need a matrix to contribute to the tensile strength - each hair would take its share of the tensile load.
4.2.5 If on the other we want to carry a load in compression, as in the case of a table leg, the bundle of hairs would be no use at all as individual strands would buckle and collapse. Gluing the hairs together with gel (like a punk spike hairstyle), would resist the tendency of the individual hairs to buckle and increase the capacity of a given bundle to resist compressive loads. If the matrix properly bonds to each strand and there are sufficient hairs in the bundle we could make a table leg capable of supporting the top and whatever is on it. The matrix is therefore important for compressive strength."
The Manufacturing Process
Events during the Manufacture
Events on the Solent in September 2016
(a) To test the bearing mechanism, including the deployment and retraction of the foil;
(b) To test the fit, adjustment and operation of the foil under increasing load;
(c) To test the performance of the foil, in particular the optimal angle of attack.
"On our third run the foil angle of attack was changed from 2.8° to 3.8° and boat was sailing at around 26 knots downwind when there was a huge bang and the boat heeled violently. The helmsman reacted very quickly and turned the boat downwind and the boat slowed. When deployed the foil curves out from the side of the boat. Looking over the side of the boat we could immediately see the foil had broken. It was not completely separated but it was hinging up and down at the break point. We managed to get a halyard on the end of the foil to support it clear of the water and returned to port. The load cell was averaging 11.5 tons and reached its maximum reading of 13 tonnes when the foil broke."
"The load pins that were measuring the load in the foil were working and recording what I believe to be accurate loads. The pins were supposed to be setup to read up to 16 tons, however there was a mistake and the limit during the testing was set at 13 tons. This meant that any load over 13 tons appeared as 13 tons. When we reinstalled the V1 foils the pins were set up to 16 tons. The data recorded during the 2016-2107 Vendée Globe shows that in only a few instances did the foil loads exceed the maximum reading of 16 tons. That was over the full length of the race during which all conditions were experienced from light to storm force winds and wave heights over 6m. Boat speeds in excess of 30 knots were experienced on numerous occasions."
The Claimant's alleged losses
(a) The balance of the price originally agreed in the supply agreement, as set out at appendix 2 to that agreement, which the Claimant contends is £252,542; alternatively
(b) The balance of the payment price plus bonus as agreed in the discussions summarised at paragraph 31 above, which the Claimant contends is £92,480 together with the bonus of £30,000 to reflect Mr Thomson's second place in the 2016/2017 Vendée Globe; and in any event
(c) Storage charges in the sum of £35,600 relating to the hydrofoils which the Claimant contends are a contractual obligation pursuant to the terms of their invoices (see paragraph 33 of Mr Robinson's statement at 476/459).
(a) The Claimant is not entitled to payment for the hydrofoils because they were not in compliance with the contractual standard and as a result were worthless; alternatively
(b) If the Claimant is entitled to payment of the purchase price, the varied price referred to at paragraph 31 above was not the subject of any condition precedent and therefore the Claimant is entitled to the balance of that sum;
(c) The bonus depended upon the Defendant using the V2 hydrofoils in the Vendée Globe. Since they were not used, the Claimant has no entitlement to a bonus;
(d) Whilst the Defendant pleaded no case in respect of the storage charges, at trial, it argued that the Claimant was unable to show that any contractual terms was incorporated to the effect that storage charges were payable if the goods were not collected. It is incorrect for Mr Robinson to state that the invoices refer to storage charges. In fact, the invoices in the disclosure do not contain a term as to the payment of storage charges though the delivery notes do – compare for example the delivery note at 1515/1454 and the corresponding invoice at 1516/1455. There is no evidence (or indeed pleaded case) that the delivery notes created contractual terms, nor is it obvious how they would do. Further, the Claimant has not shown any trade practice or established course of dealing.
The Defendant's alleged losses
(a) Diminution in value of the foils as a result of their substandard quality. The Defendant contends that they could not be used for the Vendée Globe, their primary purpose, and therefore are worthless. Accordingly it seeks to recover the element of the purchase price that was paid, £243,520 plus VAT.
(b) As a result of the Claimant's breach of contract, the Defendant contends that it suffered the various losses set put at paragraph 66 of the Amended Defence and Counterclaim (45/45), either as wasted expenditure on the manufacture of the V2s and modification of the Boat to accept them, or as consequential losses. Those items are:
Engineering and studies for V2 hydrofoils and bearing designs | £37,142 |
Costs of changing the bearing system on the Boat to accept the V2 hydrofoils | £38,430 |
Modification to the Boat to accept the V2 hydrofoils | £15,937 |
Modification to the Boat to accept the V1 hydrofoils again | £7,400 |
Investigation and analysis by APD | £5,600 |
Investigations and analysis by Gurit | £5,020 |
Wasted costs of Mr Ryan Taylor | £65,580 |
Wasted costs of cancelling professional sailors due to broken hydrofoils | £20,020 |
Other costs | £6,642 |
The Expert Evidence
(a) The construction of the shear boxes did not comply with the design specification in that the plies laid around the Rohacell foam core in that it appeared that ratio of plies in the 0° orientation to those in the 45° orientation was 1:1 rather than 1:3.
(b) The layup of the laminate wrapped around the Rohacell foam core was not as good as it could have been.
(c) In the final machining of the V2 port hydrofoil, a handheld grinder cut through the external laminate at the edge of the recess into the leading edge into which the camel toe feature was bonded.
(d) The board appears not to have been exactly in accordance with the drawing in that the measurement from tip to toe appeared to be offset by 17.5mm (though in cross examination Mr Smith accepted that this could simply have been a measurement error);
(e) The camel toe was not fitted straight and was not in alignment;
(f) The camel toe was not finished to an acceptable standard.
(a) Testing of the compressive strength of the compression side unidirectional plank following the failure showed on average a compressive strength of 814 Mega-Pascals (MPa). A low result of 522 MPa was considered a possible outlier and, discarding that, the average strength was 872 MPa. However, they would have expected a compressive strength in the region of 1197 MPa (see the agreed answer to question 2.1).
(b) Testing of interlaminar sheer strength on samples extracted from the damaged foil which was carried out by the manufacturers showed results which were either "low" (according to Mr Smith) or "lower than the theoretical values obtained from pristine components" (according to Mr Reis).
(a) Poor material quality from the suppliers of the laminate, resulting from poor distribution of resin matrix or contamination of the fibres resulting in poor resin adhesion;
(b) Failure to use a material with nano particulates;
(c) Poor consolidation during the debulking process;
(d) Wrinkles in the laminate;
(e) Issues with the curing process;
(f) Poor fibre alignment relative to the board axis during the lamination process.
These criticisms in part reflect possibilities raised in a report from Applied Polymer Development into the failure of the hydrofoil, which appears at 659/641, although it should be noted that that report expresses no confident conclusion on the cause of failure other than noting poor interlaminar sheer strength referred to above.
(a) A small amount of dry fibre in the laminate;
(b) Voids in the laminate;
(c) Fibre distortion locally in areas of the foam cores;
(d) The presence of an unidentified foreign substance.
Discussion 1: – the Contractual Issues
(a) The Defendant contracted to purchase the V2s;
(b) The Claimant manufactured both V2s and delivered the port hydrofoil to the Defendant;
(c) The Defendant is liable to pay the purchase price for the V2s unless it shows that the goods were worthless due to manufacturing error by the Claimant, the burden of proving which relies on the Defendant.
Discussion 2: – the Expert Issues
(a) Mr Reis' modelling shows that the foil as designed is strong enough to resist 28 tonnes of force even at its weakest point.
(b) The failure of laminar bonding did not occur in the neutral axis, where shear forces would be at their maximum, but rather on the plane 13.5mm in from the outside of the unidirectional compression plank. This is some way from the neutral axis and therefore the failure would not have occurred here unless this was a weak point. Given that the forces are greatest at the neutral axis, if the failure at the 13.5mm plane was due to overloading, the load on the neutral axis at the time of failure would have been even greater. But since the unidirectional plank was designed to be uniform in construction, failure at a point other than that where the shear force is at its greatest leads overwhelming to the conclusion that the failure was due to a manufacturing or materials error at the point of failure rather than a more generalised design (or indeed construction) error.
(a) Whilst Mr Smith had not seemingly seen the Pierrepoint analysis when he prepared his report, it would be surprising that, if he considered it to be significant, he only mentioned this for the first time in cross examination. Of course this may be because the significance of the analysis only came to him when giving evidence. But if this were so, I would be concerned that he had not fully thought through what he was saying.
(b) Moments before giving the evidence, relating to the Pierrepoint Report, Mr Smith had dismissed this kind of NDT testing as of little help in investigating the cause of the event. At the point that he made that statement, it is difficult to believe that he had in mind that he was about to say that the NDT in fact supported his interpretation of events. This adds to my anxiety about how carefully considered this evidence was.
(c) In any event, I am not clear that the Pierrepoint analysis has the importance that Mr Smith attributes to it. It is correct that the table at 893/875 identifies what may be anomalies in "P1", "P2 and "P3" at a depth of 12mm from the outboard surface. But, on my reading of the report, that is a reference to the points shown on picture 4 (894/876) and scans 3 and 4 (895/877), not the scan at 889/871, to which Mr Smith made reference. Without the kind of fuller investigation of this issue which would have occurred if the point had been made in advance in writing, thereby allowing the Claimant's expert to consider and comment upon it, I am not satisfied that Mr Smith is correctly interpreting the Pierrepoint report.
(d) If the APD investigation shows what Mr Smith contended in cross examination, I do not see why he failed to make the point within his original report. Mr Smith noted that report with its reference to failure at the 12mm level, but did not attribute any significance to the photograph which he now says demonstrates that his case is correct. Again, it has not been possible properly to investigate whether the photograph is being correctly interpreted by Mr Smith because the point had not been made earlier.
(e) The matters on which Mr Smith commented were not put to Mr Reis. One might wonder whether this was because Mr Land, for the Defendant, was unaware of the points until Mr Smith gave evidence, but that of course would be speculation. In any event, the fact that they were not put to Mr Reis means that the court is left with little further material by which it might judge the reliability of the evidence given by Mr Smith. Mr Reis was asked in re-examination about the electron microscope image at 678/660 and said that he did not see that the court could draw the inference of any gross manufacturing defect from that. However, such evidence suffers from the problem that it was being given very much "on the hoof" and may not reflect a considered opinion on the point.
Discussion 3: – the Claimant's losses
Discussion 4: The Defendant's Losses
(a) The Defendant fails to show that the purchase of a further set of foils was a reasonable mitigation of its loss. There is simply no evidential basis for saying that this was money well spent and, for example, the court does not know how much the value of the Boat would have depressed had it been sold without hydrofoils.
(b) More fundamentally, if the Defendant were to recover both the cost of purchasing the V2s and the cost of replacement foils, it achieves double recovery through getting the ultimate foils for free.
Conclusion
Permission to Appeal
(a) That I failed to bear in mind that, in a "two cause" case such as this, where the court rejects one of the causes, it must accept the other.
(b) That, having found that the design failure was an improbable cause, I should have accepted the other cause, namely manufacturing defect, to be the probable cause
(c) That I erred in finding that the Defendant was obliged to find an identified manufacturing cause; it was enough for the Defendant to succeed to show that a design cause was improbable.
(d) That it is logically unsustainable for me, having found a design cause to be improbable to have found a manufacturing cause to be even more improbable.