BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Queen's Bench Division) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Queen's Bench Division) Decisions >> Laker Vent Engineering Ltd v Templeton Insurance Company Ltd [2008] EWHC B6 (QB) (02 May 2008) URL: http://www.bailii.org/ew/cases/EWHC/QB/2008/B6.html Cite as: [2008] EWHC B6 (QB) |
[New search] [Help]
QUEEN'S BENCH DIVISION
LIVERPOOL DISTRICT REGISTRY
MERCANTILE COURT
B e f o r e :
____________________
LAKER VENT ENGINEERING LIMITED |
Claimant |
|
And |
||
TEMPLETON INSURANCE COMPANY LIMITED |
Defendant |
____________________
____________________
Crown Copyright ©
Introduction
The Policy
"The sum of any legal costs and disbursements (including Counsel's fees and the costs and expenses of expert witnesses) reasonably, properly and directly incurred by the Insured in connection with the pursuit or defence of a Construction Claim in Court or arbitration proceedings up to and including the conduct of an Appeal against a Court judgment or the award of an arbitrator."
"A bona fide construction claim arising under a Contract provided always that the Insured shall have first made an application for payment or asserted a defence under and in accordance with the terms of the relevant Contract and the said application or assertion shall have been rejected in writing on at least two occasions either in whole or in part by the Other Party or its agent."
"It is a condition precedent to the Insurers' liability hereunder that We are notified in writing, immediately the Insured is aware of any cause, event or circumstance which has given or is likely to give rise to a Construction Claim. It is important to note that on any renewal declaration to the Insurers, the Insured must advise the Insurer of any potential claims, not already advised by the Insured and received by the Insurers. If the Insured fails to notify Us of such cause, event or circumstance during the Period of Insurance, any claim arising from that cause, event or circumstance shall not be admitted unless the Insurers in their sole discretion decide otherwise."
"Where such notification has been given, the Insurers agree to treat any subsequent Construction Claim in respect of the cause, event or circumstance notified as though the Construction Claim had been made, brought or commenced during the Period of Insurance. Upon receipt of notification by the Insured under Clause 6.1, We will forward the Insured a Claim Form which must be completed and returned if the Insured wishes to proceed with a Policy Claim."
Renewal
LVE's Dealings with GWUG
"We were all hoping that the spirit of our meeting in Berlin would prevail to get a co-operative front to finish this project and obtain a consensus for possible claims from RWE by creating a performance that would enable RWE to be generous.
I urge you to sign off on the proposed original addendum. Otherwise you jeopardise the advanced payment regulation with RWE."
"LVE has to improve significantly its performances till the 9th January 2005, otherwise RWE's site management is threatening to substitute Laker.
We often spoke about these problems with you and Richard Ventre. I also asked Dave to deploy one or two teams just for completion. LVE didn't pay attention to this note.
I ask you to initiate measures immediately."
"The comments contained in your e-mail are not helpful. We are still in the middle of Construction. Due to delays largely outside of our control the project is significantly delayed. We are now installing, snagging, testing and handing over in parallel due to the compression of the time schedule. We are endeavouring to complete works as quickly as possible but it does not help when we feel that we are being continually criticized for a situation which is not our fault."
He then went on to refer to a number of different actions which LVE had taken in order to assist in the progress of the project and concluded with the following comments:
"It is now vitally important that we receive a response to our e-mail dated 16th December 2004. We have organised additional resources at your request based on good will. We are not prepared to incur this additional cost unless we receive confirmation that it will be fully reimbursed. It is also worth noting that without this supervision structure in place we will not be able to maintain current or additional site manpower as it will significantly affect productivity, safety and quality aspects of our work."
"I believe LVE have shown a high level of good will. Our Chief Executive has become directly involved in the project. We have increased manpower in line with your own requirements. We have also employed a far greater level of site management in order to control the increase in manpower. This has been implemented without conclusion of the respective commercial negotiations and very much at our risk. This is a situation which simply cannot continue.
We originally requested additional costs for acceleration of contract extension via our e-mail dated 16th December 2004 as requested. A month has now passed without formal response. If LVE were to react so slowly to requests from RPS/GWU/RWE the project would suffer even further delay.
We respectfully request that until commercial negotiations reach their conclusion our latest application for payment (No 5) is approved in full and payment is processed by the end of the month."
The Construction Question
"It is a condition precedent to the Insurers' liability hereunder that We are notified in writing, immediately the Insured is aware of any cause, event or circumstance which has given or is likely to give rise to a Construction Claim. It is important to note that on any renewal declaration to the Insurers, the Insured must advise the Insurer of any potential claims, not already advised by the Insured and received by the Insurers. If the Insured fails to notify Us of such cause, event or circumstance during the Period of Insurance, any claim arising from that cause, event or circumstance shall not be admitted unless the Insurers in their sole discretion decide otherwise."
The Disclosure Issue
18 Disclosure by assured
(1) Subject to the provisions of this section, the assured must disclose to the insurer, before the contract is concluded, every material circumstance which is known to the assured, and the assured is deemed to know every circumstance which, in the ordinary course of business, ought to be known by him. If the assured fails to make such disclosure, the insurer may avoid the contract.
(2) Every circumstance is material which would influence the judgment of a prudent insurer in fixing the premium, or determining whether he will take the risk.
(3) In the absence of inquiry the following circumstances need not be disclosed, namely: -
(a) any circumstance which diminishes the risk;
(b) any circumstance which is known or presumed to be known to the insurer. The insurer is presumed to know matters of common notoriety or knowledge, and matters which an insurer in the ordinary course of his business, as such, ought to know;
(c) any circumstance as to which information is waived by the insurer;
(d) any circumstance which it is superfluous to disclose by reason of any express or implied warranty.
(4) Whether any particular circumstance, which is not disclosed, be material or not is, in each case, a question of fact.
(5) The term "circumstance" includes any communication made to, or information received by, the assured.
Materiality
"(1) The Claimant had been in increasing dispute with Gass Wasser Umwelt Gommern GmbH from about October 2004;
(2) The Claimant was making claims against Gass Wasser Umwelt Gommern GmbH in relation to acceleration, site establishment, time extension cost and additional supervision;
(3) Gass Wasser Umwelt Gommern GmbH was complaining that the Claimant had failed to manage its works properly and/or to proceed with its works under the contract in a timely manner and/or to provide sufficient manpower to carry out its works;
(4) Gass Wasser Umwelt Gommern GmbH had informed the Claimant by an e-mail dated 4 January 2005 that it would be fired, unless it significantly improved its performance by 9 January 2005; and
(5) Gass Wasser Umwelt Gommern GmbH had been increasingly failing to meet the Claimant's applications for payment from about October 2004.
"The Claimant's dispute with GWUG was a material circumstance and a potential claim from at least the middle of December 2004. The Claimant's claim against GWUG had been rejected several times in writing and orally at a meeting; the Claimant and GWUG were blaming each other or persons for whom they were responsible for the delay to the project; the managements of the two companies had become involved; an attempt to settle the dispute had fallen apart; the main contractor had become involved, and its order that a commercial settlement be reached within a week had come to nothing. There was plainly an actual dispute between the Claimant and GWUG about its right to compensation for the delay to the works. Several more weeks passed; the dispute continued; and the Claimant was being threatened with the sack before the contract of insurance was renewed on 17 January 2005."
"The Claimant should have notified the Defendant before the renewal of the insurance that the progress of its works at Cottam Power Station had been severely delayed; that the delay was not its fault; that it was claiming that it would be entitled to compensation from GWUG for the inevitable extension of time for completion of the works in sums totalling several hundred thousand pounds; and that GWUG had rejected this claim that it would be entitled to compensation on several occasions."
"7.7 The level of disagreement between Laker Vent and B&D was escalating during the period from November 2004 onwards to the extent that, in my opinion, a prudent underwriter would regard the situation as material information that he would want knowledge of.
7.8 7.8 Once aware of the disagreement, an underwriter would be able to decide whether he should make further enquiries as to the likely probability of a claim developing.
7.9 7.9 The response to these enquiries would have allowed a prudent underwriter to assess whether renewal would be offered and, if so, on what terms."
"On my reading, the evidence shows clearly that there were a number of questions and challenges by MC in relation to some of the work carried out by Laker Vent under the Cottam contract and that, failing a response satisfactory to MC, it withheld certain payments due to Laker Vent. I have seen nothing in the evidence to suggest to me that these differences between the parties were unusual in their nature or origin, amounted to a dispute, were likely to give rise to a dispute or even had the potential to give rise to a dispute. They would appear to be an almost inevitable part of the overall process of carrying out works under a construction contract. Indeed, a construction contract will recognise the potential for such differences and provide mechanisms for dealing with them if, in the event, they are not resolved and become the subject of formal dispute. It is in order to address the uncertainties of such a dispute arising and requiring legal action potentially giving rise to otherwise irrecoverable legal expenses that a party is minded to effect and maintain an appropriate form and level of LEI, as was the case here with Laker Vent."
"I have stated at 6.2(c) above that I could find no evidence of any identifiable dispute or probable or even potential dispute underlying the relationship between Laker Vent and MC at or before 19th December 2004. It is therefore my opinion that there is nothing factual of this nature for Laker Vent to disclose to Templeton in relation to the proposed inception of CPS3".
"I have significant experience of underwriting insurance contracts providing indemnity in relation to the legal expenses and/or damages arising from the insured's pursuit or defence of 'dispute' situations of various types. I have also handled many legal expenses and liability claims which have been made in relation to such disputes. It is also my opinion consistent with my experience that, had Laker Vent disclosed to a reasonable and prudent underwriter of insurance of the type contemplated by CPS3 any of the facts relating to the Cottam Contract at or before 19th December 2004, such a disclosure would not have influenced his judgment in determining whether he would continue to insure the risk or in fixing the premium or other terms for doing so. I say this because such facts as could then have been disclosed would, in my view, have indicated nothing more than the progress of a generally amicable and constructive dialogue between Laker Vent and MC."
Inducement
"Amy,
Please invite renewal at £4,900-00 a 20% claims loading i.e. £5880-00 plus ipt. Premium inclusive of ipt = £6174-00. Regards, Greig."
Notification
"Can you send a Claim Form through to the Client please for a potential new claim please.
Lakers have a contract for pipework at Cottam power station in Nottingham. The main contractors are a German company and the contract period is for 10 weeks. Unfortunately there have been delays on the site, none of which are the fault of Lakers but the effect is they will be unable to meet the completion date of 15th February 2005. Lakers have asked the main contractor for an extension in time and prolongation/acceleration costs. The main contractor has said no and under the terms of the contract Lakers cannot stop working.
David Baldwin of Glovers Project Services Limited has been involved on this contract from its initial stages and we understand Lakers have fully documented paperwork."
"I would like to draw your attention to the fact that there cannot be a valid claim under the Policy until an application or assertion under the terms of a contract has been rejected in writing by the other party on at least two occasions; if this has occurred please let us have copies of the correspondence."
Other Matters
Conclusions
His Honour Judge Hegarty QC
30th April 2008