England and Wales High Court (Queen's Bench Division) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Queen's Bench Division) Decisions >> Menston Action Group v City of Bradford Metropolitan District Council [2016] EWHC 127 (QB) (29 January 2016) URL: http://www.bailii.org/ew/cases/EWHC/QB/2016/127.html Cite as: [2016] EWHC 127 (QB), [2016] PTSR 466, [2016] WLR(D) 54 |
[New search] [Printable RTF version] [Buy ICLR report: [2016] PTSR 466] [View ICLR summary: [2016] WLR(D) 54] [Help]
QUEEN'S BENCH DIVISION
LEEDS REGISTRY
1 Oxford Row, Leeds, LS1 3BG |
||
B e f o r e :
____________________
MENSTON ACTION GROUP (acting by Professor John David Rhodes) |
Claimant |
|
- and - |
||
CITY OF BRADFORD METROPOLITAN DISTRICT COUNCIL |
Defendant |
|
- and - |
||
CHARTFORD DEVELOPMENTS LIMITED |
Interested Party |
____________________
Ian Ponter (instructed by City of Bradford MDC) for the Defendant (CO/2184/2015)
Vincent Fraser QC (instructed by City of Bradford MDC) for the Defendant (CO/5750/2015)
David Forsdick (instructed by Walker Morris LLP) for the Interested Party
Hearing dates: JR1 27th November 2015, JR2 8th January 2016
____________________
Crown Copyright ©
Mr Justice Dove :
Facts
"Fluvial
The site is within Flood Zone 1. This zone comprises land assessed as having less than a 1 in 1000 (<0.1%) annual probability of tidal or river flooding in any one year.
It should be noted the watercourse on and adjacent to the site may be a source of localised fluvial flooding that has not been captured on the EA flood zone map. As a section of the water course on the site is piped and the pipe capacity may cause a restriction to flow in times of heavy rainfall and result in localised flooding to the immediate upstream open section of the watercourse.
In time of extremely heavy rainfall, local residents have reported that flooding has been apparent on the site up to a depth of approximately 0.4m.
A catchment area analysis has been undertaken of the watercourse that crosses the site and the 1:100 year flood level has been modelled as 147.70. The flood modelling analysis undertaken is attached in Appendix F.
Three dimensional modelling has shown the flood volume on the site is 216.3m³. The extent of the modelled flooding on the site is indicated on Fig 3 attached in Appendix G.
Runoff
From the inspection of site levels and ground levels to the surrounding properties to the northeast of the site, it appears that the north eastern sector of the site is in a 'bowl'. Therefore any overland waters either from surface runoff or from overtopping of open section of the watercourse will run into this area and accumulate. It is also apparent that once water has accumulated in this area of the site it cannot drain into the piped watercourse under this area of the site.
It is evident from several site visits made by CoDA Structures water does pond on the surface over the line of the piped watercourse to a depth of approximately 75mm. The surface flooding observed by CoDA Structure appears to be an accumulation of surface water runoff from the field which cannot drain into the piped watercourse as the open watercourse itself has not been in flood."
"Effect of Development on the Wider Catchment:
The proposed development will result in impermeable area on the site and therefore unattenuated surface water flows from the development, if not addressed, would increase the flood risk to the site and local catchment."
"Flood Risk Mitigation:
As part of the development of the site it is proposed to divert the piped section of the watercourse. In order to maintain the hydraulic characteristics of the piped section of the watercourse and not increase flows, the watercourse diversion will be undertaken in 300mm diameter pipes. The watercourse diversion will require formal consent from BMDC – Drainage. The proposed diversion route of the watercourse is shown on he Schematic Level and Drainage Scheme (Fig.5) attached in Appendix L.
The flood storage volume before 147.70m AOD on the site will be increased to 324.0m³. The proposed flood compensation areas indicated on Fig. 4 are attached in Appendix H. The provision of flood storage has also been verbally discussed with BMDC Drainage Department (Mr E Norfolk) and it was advised it would be acceptable to provide the flood storage below ground by using, for example, a crate system…
The site surface water drainage system will be designed to restrict discharge to the piped water course on the site to greenfield run off with stormwater storage provided on the development for storms up to a 1:00 year event plus an allowance for climate change. BMDC Drainage Department (Mr A Davison) verbally advised that surface water discharge to the watercourse on the site should be restricted to greenfield runoff (1.6 lit/sec/ha) but for 'practical' reasons with regard to flow control units a discharge rate of 5.0l/s would be acceptable. It should be noted that the green field run off for the catchment was calculated as 8.2 lit/sec/ha in the Eastwood & Partners Report which equates to 8.2 l/sec for the site.
With reference to the Eastwood and Partners FRA Report, the following parameters were used for the volumetric discharge for the 1:100 year storm:-
- 1:100 year discharge rate 24.2 l/sec
- Total rainfall for the 1:100 year event = 57.4mm
Using these values the volumetric discharge for the site using the traditional percentage calculation is 0.3 x 0.0574 x 10 000 = 172.2m³.
The proposed discharge rate from the developed area of the site is 5.0l/sec (see Section 4.0). Therefore the volume discharged in 6 hours would be 5.0 x 60 x 60 x 6 = 108,000 litres (108.0m³).
The volume discharged from the undeveloped area of the site would be 0.3 x 0.0574 x (10 000 – 4390) = 96.6m³.
The gives a total discharge of 204.6m³ an increase of 32.4m³.
However, the flood compensation proposed on the site would give an additional 106.7m³ of storage which is more than sufficient to store the additional discharge from the site as the flow off the site is always restricted by the 300mm diameter piped section of watercourse.
The proposed management of surface water runoff from the developed site together with the flood storage volume provided below the existing 1:100 flood level of 147.70m AOD will not increase the risk of flooding both on and down stream of the site.
If the discharge rate from the developed area exceeded 5.01/sec for any reason it should be noted that an additional flood storage volume of 106.7m³ has been provided on the site below the 1:100 flood level of 147.70m AOD."
"For storm a of a given duration and return period the volume of water falling onto a catchment will be the same in the pre and post development state. The difference is how this water is managed and in the run off response time. The response time in the developed state is much quicker as flows are drained towards a defined point in a drainage network whilst in the undeveloped state rainfall will shed at a lower rate and will be subject to natural losses such as evaporation and infiltration.
It should be noted any rainfall on the pre-developed site would shed by overflow routes either towards the water course and the rear gardens of the properties on Red House Gardens.
In the developed state rainfall on the development will be captured in the gravity drainage system for flows up to the 1 in 100 year plus climate change event. These flows would be discharged at a managed rate of 5.0l/sec to the piped watercourse. Stormwater storage will be provided on the development in the form of oversized pipes for a 1:100 year storm return period and a 30% increase in rainfall intensity for climate change.
The following estimation of stormwater storage requirements for the development has been based on the following parameters:
Hardcover area 2190m²
Discharge rate 5.01/sec
Stormwater storage 199.2m³
It should be noted that in the final design approximately 765m² of drive area will be drained into the soils adjacent the Poplar trees.
A gravity system can be adopted on the development.
The stormwater storage calculations for the proposed system are attached in Appendix L."
"Surface Water
Ground conditions on the site are such that the use of conventional soakaways on the development is not considered to be a viable solution for the disposal of surface water from the development.
It is proposed that a separate surface water drainage system be provided on the development discharging to the watercourse on the site.
Based on a proposed total drained hardcover area of 2190m² and a discharge rate of 5.0l/sec a storage volume of 199.2m³ should be provided on the site, based on a 1:100 year storm return period with a 30% increase on rainfall intensity to cater for climate change.
It should be noted that in the final design approximately 765m² of drive area will be drained into the soils adjacent the hybrid Poplar trees."
"Land Drainage
Following the extensive discussion on issues of land drainage, the Councils Drainage section has reviewed the objectors' submissions and the applicant's response, on this matter. The commentary below forms the appraisal of land drainage matters.
Consideration has been given to all the submitted reports from the applicant and objectors in relation to the drainage characteristics and proposals for the Bingley Road site in Menston. The evaluation has been made on the basis that the matter before Committee is a proposal to develop the site so as not to increase existing flood risk, not a scheme to remove it. It is therefore against the former legislation [WHAT LEGISLATION?] that the applications have been assessed.
Surface water discharge from the site.
As development will normally increase the runoff rate of the site, therefore the final surface water flow rate will have to be restricted if no increased run off is to occur. The principle used to set a low rate is to ensure it is not an increase from the existing sites runoff rate for the rainfall events of 1:1 year and 1:100 year. In the case of the two application sites, as they are currently undeveloped, the limiting discharge rate will be set no greater than the existing Greenfield runoff rate. The method for calculating the existing Greenfield runoff rate according the British Standard 8582:2013, Code of practice for surface water management for development sites, and for sites less than 50 ha the IH124 method should be used. This method has been used on both application sites.
The Chartford Homes site is approximately 1.0 hectare in size. The existing Greenfield runoff rates for the site have been correctly calculated using the IH124 method as 1:1 year = 8.2litres/second and 1:100 year = 24.2 litres/second. The proposed discharge rate will be set to 5litres/second and is therefore a considerable reduction for both the 1:1 year and 1:100 year existing flow rates.
The proposed discharge rate of surface water from both development sites therefore will not increase flooding but reduce it and is therefore acceptable.
Surface water storage serving the new development sites.
With a restriction imposed on the surface water runoff it is required that the development provides water storage facilities to hold excess water during heavy rainfall events. The exact amount of storage required is determined during the detailed design of a drainage system as the falls and sizes of pipelines has an affect on how quick water is distributed around a system. At planning stage the drainage department needs to be satisfied that the estimated storage amount can be achieved within the development's layout.
The Chartford Home site estimates a storage requirement in the region of 199m³. The drainage department has used their own storage calculations to verify this estimate. The submitted drainage strategy drawing 6984/fig5 Revision A prepared by CODA Structures, proves the estimated storage can be fitted within the site layout.
The risk of flooding is reduced by the designed storage tank and is therefore acceptable…
Groundwater flooding
…
Ponding has been experienced on the Chartford Home site during prolonged rainfall events. The emergence of flood waters has been assessed using a hydraulic flood model of the unnamed watercourse that passes through the site. Flood levels and volumes have subsequently been calculated for the existing site. Witness statements also provide photographic evidence of flood waters and levels on the site. The source of the flood water has been suggested to be from both ground water and surface water runoff. The Chartford Homes site therefore proposes to provide flood storage within the site boundary. The flood storage provided equates to 50% more than what the site currently provides to the catchment. The storage provided is adequate to cater for the flooding modelled by the hydraulic flood model and also the flooding witnessed by residents detailed within the objectors report. The finished floor levels of the development will be set 600mm above the calculated 1:100 year flood levels and are therefore above the existing ground levels and witnessed flood levels…
Surface Water Flooding
A development should not increase the quantity and velocity of surface water run-off through the site, in accordance with planning policy.
The submitted proposal complies with the relevant legislation for managing surface water of the application site. The documents submitted on behalf of objectors are not relevant in terms of development proposal, the rainfall events referred to fall outside the range that can be considered for a development proposal. Consideration of such events would be appropriate if this were a flood alleviation scheme, even then though the volumes based on a methodology derived from observed from photographs for a single event is not robust or would stand expert scrutiny.
Existing flows through the Chartford Home site has been modelling using industry recognised methods and the flood levels derived are close to the observed levels witnessed during the flooding events in September. The modelling undertaken also concurs with Environment Agencies surface water flood maps. As discussed above the Charford Homes site proposes to add an additional 50% of contribution storage volume to the site and therefore flood risk from overland surface flows will be reduced.
In conclusion therefore the measure proposed for the site are reasonable and meet the appropriate regulatory requirements."
"Some 20 years ago the Environment Agency specifically supervised the construction of the overflow system at the site to ensure that the site acted as a Detention Basin after allowing the adjacent lake on Red House Gardens to be filled in. It has acted as designed for many years with a large lake forming over the site and adjacent gardens…"
"We have looked into the matters raised by Mr Schofield [the claimant's solicitor] and can confirm that at the time our consultation response was provided, we had no information that suggested that the site was subject to any specific drainage problems. Furthermore we hold no record that the Environment Agency was involved in works at this site, although it should be noted that the EA was not formed until 1996 – this may therefore be a reference to a predecessor organization. We would anticipate that the local authority would hold records of any requirements arising from the development of the Red House Gardens site on the relevant planning application file…
… noting that Bradford drainage department (as Lead Local Flood Authority) has considered and commented on the further information and reports that have been submitted, we can confirm that we have no further evidence regarding flood risk at this location that would add to the consideration of flood risk in the determination of this planning application."
"Environment Agency updated response recommendation
We have considered the detailed assessment of the drainage characteristics of the application site and the potential flood risks to and resulting from the development which has been submitted in support of this application. We acknowledge that the assessment includes consideration of information and reports provided by local residents.
We are satisfied that the flood risk assessment adequately addresses both flood risk and surface water management. We can confirm that we concur with the conclusions which the LLFA officers have already made in respect of the flood risk assessment. We point out that as a matter of principle the LFFA officers are best placed to advise you on the flood risk and surface management issues arising in connection with the application as such matters are within Bradford Council's remit as the LLFA.
We consider that Bradford Council should ensure that the mitigation measures detailed in the flood risk assessment are implemented and secured for the lifetime of the development. We recommend that these measures are secured through the inclusion of a planning condition on any planning permission. If the implementation of the mitigation measures are not secured, our position would be one of objection on the flood risk grounds."
"2. No development shall take place until full details and calculations of the proposed means of disposal of foul and surface water drainage, have been submitted to and approved by the Local Planning Authority.
Reason: To ensure the application site is properly drained.
3. No development shall take place until details of how the development will cater for flood waters generated within the existing watercourse and wider catchment is submitted and approved by the LPA.
Reason: In the interests of flood protection.
4. The total combined surface water flows from the development draining to the existing watercourse on the submitted drawing 6984/Fig 3. shall be restricted to a peak flow of 5 litres per second. Furthermore, the developer should submit proposals to mitigate damage to the development, or residence downstream of it, should exceedence of the system occur.
Reason: In the interests of flood protection
5. The development permitted by this planning permission shall be carried out in accordance with the approved Flood Risk Assessment (FRA) dated 28th March 2014 revision C and associated drawing Schematic for External Works (no 6984 Fig5 RevA) with the following mitigation measures detailed within the FRA:
1. Limiting the surface water run-off generated by the up to and including 1 in 100 year critical storm so that it will not exceed the run-off from the undeveloped site or increase the risk of flooding off-site. Run off rates should be finalised with the lead local flood authority;
2. Finished floor levels of new dwellings are set no lower than 148.3 metres AOD; and
3. Provision of Flood Storage Areas and swales.
The mitigation measures shall be fully implemented prior to occupation of any dwelling comprised in the development hereby approved and shall be maintained for the life time of the development.
Reason: To prevent flooding by ensuring the satisfactory storage/disposal of surface water from the site; and to reduce the risk of flooding to the proposed development and future occupants; and to provide maintenance access to the culvert and prevent compromise of the culvert structure.
6. No development shall take place until details for proposals for dealing with any existing watercourses, culverts, land drains etc encountered during the works are submitted to and approved in writing by the LPA. The development to be carried out in accordance with the approved details.
Reason: In the interest of the protection of the watercourse.
…
17. No development shall take place until full details and calculations of the proposed means of disposal of foul and surface water drainage, have been submitted to and approved by the LPA. The development to be carried out in accordance with the approved details.
Reason: In the interests of the drainage of the site."
"The detailed drainage design for the development has been prepared in accordance with the approved Flooding and Drainage assessment report [revC] for the site.
With reference to the Flooding and Drainage Assessment.
In order to reduce the volume of discharge from the development drainage system in a 6 hour period by the 32.4m³ 'exceedence' (ie to maintain the calculated volumetric discharge from the site to 172.2m³) the discharge rate form (sic) the storm water system has been reduced from 5.0l/s to 3.5l/s [ie (5.0 x 60 x 60 x 6 = 108.0m³) – (3.5 x 60 x 60 x 6 = 75.6m³) = 108.0 – 75.6 = 32.4m³].
The final detailed design of the surface water drainage system, including the stormwater storage has been undertaken using Windes drainage software. A storm return period of 1:100 has been used for storms between 15 and 10800 minutes for both summer and winter events. A 30% allowance for climate change has been included within the calculations.
Calculations for all storms have been submitted for approval.
The proposed drainage system is indicated on drawing 6984/010revC."
"Should any unrecorded watercourses, culverts or land drains etc. be exposed during the works the Local Panning Authority will be notified in writing immediately and operations on the affected part of the site ceased until a temporary diversion to the water course is put in place.
It would be the intention to retain the watercourse, culverts or land drains in place but if the watercourses, culverts or land drains are below a proposed property it would be the intention to divert the watercourse, culverts or land drain around the property in question. All watercourse, culverts or land drains would be piped directly to the water course that crosses the site to avoid potential accumulations of water in garden areas.
An amended drainage drawing would be submitted to the Local Planning Authority to obtain the necessary consents prior to works being undertaken on the site."
"The principles and arrangement of the foul and surface water drainage scheme are acceptable. The submitted calculations show the proposed surface water system does not flood and is therefore adequately designed to cater for all storm events…
Conditions 2 and 17 are therefore recommended to be discharged…
Within the Flooding and Drainage assessment dated 28 March 2014a hydraulic model of the existing watercourse that passes through the site was included. Within these modelled results it was shown that the existing site, pre development, during an 1:100year rainfall event, flooded to a level of 147.70 equating to a volume of 216.3m³. The report also included a scenario for the proposed site levels presented on drawing 6984/Fig4 Flood Compensation Areas, which would provide a total volume of storage equating to 324m³ in dealing with the existing flood volumes. Drawings 6984/100 Rev A, 6984/101 – and 6984/102 – confirm that the suggested levels in the report are to be incorporated into the proposals thus ensuring the proposed site includes approximately 50% more storage in catering for flood waters generated by the watercourse. Furthermore, The sites existing 1:100 year greenfield discharge rate is calculated as 24.2 litres/second/hectare. This would give a discharge volume of 24.2 x 60 x 60 x 6 x 1.0 = 522.7m³ from the undeveloped site in a 1:100 year 6 hour event. For the developed areas of the site (3720m²) the greenfield runoff equates to an existing volumetric discharge for the 1:100 year 6 hour storm event of 24.2 x 60 x60 x 6 x 0.372 = 194.5m³ However, the proposed discharge rate from the developed areas of the site will be restricted to 3.5litres/second which equates to a volumetric discharge from the 1:100 year 6 hour event of 3.5 x 60 x 60 x 6 = 75.6m³. Therefore the proposed volume of discharge is less than the pre development situation thus showing the development runoff will not take up space in the 50% increase in storage provision for the watercourse.
Condition 3 is therefore recommended to be discharged…
Part 1 of condition 5 relates to the limiting discharge rate of surface water runoff from the development. The existing greenfield runoff rate for the site has been correctly calculated using the IH124 method as, 1:1 year = 8.2litres/second/hectare and 1:100 year = 24.2 litres/second/hectare. As per the assessment in discharging condition 3, The sites existing 1:100 year greenfield discharge rate is calculated as 24.2 litres/second/hectare. This would give a discharge volume of volume of 24.2 x 60 x 60 x 6 x 1.0 = 522.7m³ from the undeveloped site in a 1:100 year 6 hour event. For the developed areas of the site (3720m²) the greenfield runoff equates to an existing volumetric discharge for the 1:100 year 6 hour storm event of 24.2 x 60 x 60 x 6 x 0.372 = 194.5m³ However, the proposed discharge rate from the developed areas of the site will be restricted to 3.5 litres/second which equates to a volumetric discharge from the 1:100 year 6 hour event of 3.5 x 60 x 60 x 6 = 75.6m³. Therefore the proposed volume of discharge is less than the pre development situation thus showing the agreed discharge rate is acceptable in discharging part 1 of condition 5…
Drawings 6984/100 Rev A, 6984/101 – and 6984/102 – confirm that the finished external levels shown on the drawing 6984/Fig4 Flood Compensation Areas thus indicating the site provides the necessary provision of flood storage areas and swales recommended within the Flooding and Drainage Assessment dated 28th March 2014 and as a result Part 3 of condition 5 is satisfied.
Condition 5 is therefore recommended to be discharged…
The information contained within the above documentation describes the applicant's intentions in dealing with any unknown watercourse, land drains or culverts in a manner that would ensure that flood risk during the development lifetime would not be increased. The strategy in the statement is considered acceptable to recommend the discharge of condition number 6."
Policy and guidance
"100. Inappropriate development in areas at risk of flooding should be avoided by directing development away from areas at highest risk, but where development is necessary, making it safe without increasing flood risk elsewhere. Local Plans should be supported by Strategic Flood Risk Assessment and develop policies to manage flood risk from all sources, taking account of advice from the Environment Agency and other relevant flood risk management bodies, such as lead local flood authorities and internal drainage boards. Local Plans should apply a sequential, risk-based approach to the location of development to avoid where possible flood risk to people and property and manage any residual risk, taking account of the impacts of climate change, by:
• applying the Sequential Test;
• if necessary, applying the Exception Test;
• safeguarding land from development that is required for current and future flood management;
• using opportunities offered by new development to reduce the causes and impacts of flooding; and
• where climate change is expected to increase flood risk so that some existing development may not be sustainable in the long-term, seeking opportunities to facilitate the relocation of development, including housing, to more sustainable locations.
101. The aim of the Sequential Test is to steer new development to areas with the lowest probability of flooding. Development should not be allocated or permitted if there are reasonably available sites appropriate for the proposed development in areas with a lower probability of flooding. The Strategic Flood Risk Assessment will provide the basis for applying this test. A sequential approach should be used in areas known to be at risk from any form of flooding…
103. When determining planning applications, local planning authorities should ensure flood risk is not increased elsewhere and only consider development appropriate in areas at risk of flooding where, informed by a site-specific flood risk assessment following the Sequential Test, and if required the Exception Test, it can be demonstrated that:
• within the site, the most vulnerable development is located in areas of lowest flood risk unless there are overriding reasons to prefer a different location; and
• development is appropriately flood resilient and resistant, including safe access and escape routes where required, and that any residual risk can be safely managed, including by emergency planning; and it gives priority to the use of sustainable drainage systems."
"What are the opportunities for reducing flood risk overall?
Local authorities and developers should seek opportunities to reduce the overall level of flood risk in the area and beyond. This can be achieved, for instance, through the layout and form of development, including green infrastructure and the appropriate application of sustainable drainage systems through safeguarding land for flood risk management, or where appropriate, through designing off-site works required to protect and support development in ways that benefit the area more generally."
Grounds and procedure
The Law
"38(6) If regard is to be had to the development plan for the purpose of any determination to be made under the planning Acts the determination must be made in accordance with the plan unless material considerations indicate otherwise."
"15. Each local planning authority delegates its planning functions to a planning committee, which acts on the basis of information provided by case officers in the form of a report. Such a report usually also includes a recommendation as to how the application should be dealt with. With regard to such reports:
i) In the absence of contrary evidence, it is a reasonable inference that members of the planning committee follow the reasoning of the report, particularly where a recommendation is adopted.
ii) When challenged, such reports are not to be subjected to the same exegesis that might be appropriate for the interpretation of a statute: what is required is a fair reading of the report as a whole. Consequently:
"[A]n application for judicial review based on criticisms of the planning officer's report will not normally begin to merit consideration unless the overall effect of the report significantly misleads the committee about material matters which thereafter are left uncorrected at the meeting of the planning committee before the relevant decision is taken" (Oxton Farms, Samuel Smiths Old Brewery (Tadcaster) v Selby District Council (18 April1997) 1997 WL 1106106, per Judge LJ as he then was).
iii) In construing reports, it has to be borne in mind that they are addressed to a "knowledgeable readership", including council members "who, by virtue of that membership, may be expected to have a substantial local and background knowledge" (R v Mendip District Council ex parte Fabre (2000) 80 P & CR 500, per Sullivan J as he then was). That background knowledge includes "a working knowledge of the statutory test" for determination of a planning application (Oxton Farms, per Pill LJ)."
"34. When the court is concerned with the interpretation of words in a condition in a public document such as a section 36 consent, it asks itself what a reasonable reader would understand the words to mean when reading the condition in the context of the other conditions and of the consent as a whole. This is an objective exercise in which the court will have regard to the natural and ordinary meaning of the relevant words, the overall purpose of the consent, any other conditions which cast light on the purpose of the relevant words, and common sense. Whether the court may also look at other documents that are connected with the application for the consent or are referred to in the consent will depend on the circumstances of the case, in particular the wording of the document that it is interpreting. Other documents may be relevant if they are incorporated into the consent by reference… or there is an ambiguity in the consent, which can be resolved, for example, by considering the application for consent.
35. Interpretation is not the same as the implication of terms. Interpretation of the words of a document is the precursor of implication. It forms the context in which the law may have to imply terms into a document, where the court concludes from its interpretation of the words used in the document that it must have been intended that the document would have a certain effect, although the words to give it that effect are absent. See the decision of the Privy Council in Attorney General of Belize v Belize Telecom Ltd [2009] 1 WLR 1988 per Lord Hoffmann at paras 16 to 24 as explained by this court in Marks & Spencer plc v BNP Paribas Securities Trust Company (Jersey) Ltd [2015] UKSC 71, per Lord Neuberger at paras 22 to 30. While the court will, understandably, exercise great restraint in implying terms into public documents which have criminal sanctions, I see no principled reason for excluding implication altogether.
36. In my view assertions, such as are found in Trustees of the Walton-on-Thames Charities v Walton and Weybridge Urban District Council (1970) 21 P & CR 411, Salmon LJ at p 418 and Widgery LJ at p 420, and in the Sevenoaks District Council case (above), Sullivan J at para 45, that there can never be an implied condition in a planning permission are too absolute."
"66. … As will have become apparent, however, and in agreement also with Lord Hodge, I do not think it is right to regard the process of interpreting a planning permission as differing materially from that appropriate to other legal documents. As has been seen, that was not how it was regarded by Lord Denning in Fawcett. Any such document of course must be interpreted in its particular legal and factual context. One aspect of that context is that a planning permission is a public document which may be relied on by parties unrelated to those originally involved. (Similar considerations may apply to other forms of legal document, for example leases which may need to be interpreted many years, or decades, after the original parties have disappeared or ceased to have any interest.) It must also be borne in mind that planning conditions may be used to support criminal proceedings. Those are good reasons for a relatively cautious approach, for example in the well-established rules limiting the categories of documents which may be used in interpreting a planning permission (helpfully summarised in the judgment of Keene J in the Shepway case at pp 19-20). But such considerations arise from the legal framework within which planning permissions are granted. They do not require the adoption of a completely different approach to their interpretation."
Conclusions