BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Herschel Engineering Ltd v Breen Property Ltd [2000] EWHC Technology 178 (14 April 2000) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2000/178.html Cite as: [2000] EWHC Technology 178, 70 Con LR 1, [2000] BLR 272 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY and CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
HERSCHEL ENGINEERING LTD | Claimants | |
- v - | ||
BREEN PROPERTY LTD. | Defendants |
____________________
Adrian Davies (instructed by Messrs Fenwick and Co for the Defendants)
____________________
Crown Copyright ©
Mr Justice Dyson:
"The defendant has delivered a fully particularised Defence and Part 20 Claim in the County Court action. It is now being vexed, harassed and put to unnecessary expense by the pendency of two actions in respect of the same subject matter, and seeks the protection of the Court against such double vexation".
The relevant provisions of the Act
"The contract shall provide that the decision of the adjudicator is binding until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement. The parties may agree to accept the decision of the adjudicator as finally determining the dispute."
Subsection (5) provides that "if the contract does not comply with the requirements of subsections (1) to (4), the adjudication provisions of the Scheme for Construction Contracts apply".
The contract between these two parties did not comply with section 108(1) to (4). Accordingly, the provisions of the Scheme applied. So far as relevant, the Scheme provides:
"1(1) Any party to a construction contract (the "referring party") may give written notice (the "notice of adjudication") of his intention to refer any dispute arising under the contract, to adjudication……
23(2) The decision of the adjudicator shall be binding on the parties, and they shall comply with it until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration) or by agreement between the parties."
The submissions
proceeding with the adjudication. It was not the fault of the defendant that it was unable to obtain an injunction. In these circumstances, the court should not now be willing to give the claimant judgment and enable it to enforce the decision of the adjudicator.
"…..where the two actions are by the same man in Courts governed by the same procedure, and where the judgments are followed by the same remedies, it is prima facie vexatious to bring two actions where one will do".
"Where there is more than one suit being carried on in the Queen's Courts, it is obvious that the case is wholly different. The remedy and the procedure are the same, and a double action on the part of the Plaintiff would lead to manifest injustice."
jurisdiction to insist on deciding the rights of the parties and to compel them to accept its decision. If the matter were otherwise, there would be a race between the court and the other tribunal as to which should be the first to give its decision. This would be "ousting the jurisdiction of the court in a most ignominious way". Farwell LJ (at page 274) made the same point.
"It was not seriously suggested in this court that the judge was wrong in holding that the issue of a writ by the plaintiff, coupled with an application for directions to Master Gowers on November 25, constituted a repudiation of the arbitration agreement itself".
to refer a dispute to adjudication as a contractual right which is capable of being waived or repudiated. This is because the right to refer a dispute to adjudication is imposed on the parties by the 1996 Act.
Decision
"The intention of Parliament in enacting the Act was plain. It was to introduce a speedy mechanism for settling disputes in construction contracts on a provisional interim basis, and requiring the decisions of adjudicators to be enforced pending the final determination of disputes by arbitration, litigation or agreement."
arbitrator or the court or by the agreement of the parties. For the reasons that I have given earlier, I do not accept that the Act requires a reference to adjudication to be made before litigation or arbitration proceedings are commenced, or that such proceedings cannot be started until after an adjudication has been completed. If that is right, it is impossible to hold that, by starting court proceedings, a claimant has waived his right to refer a dispute to adjudication.
Should there be a stay?
Conclusion