BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £5, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Holt Insulation Ltd v Colt International Ltd [2001] EWHC 451 (TCC) (12 January 2001) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2001/451.html Cite as: [2001] EWHC 451 (TCC) |
[New search] [Help]
LIVERPOOL DISTRICT REGISTRY
TECHNOLOGY AND CONSTRUCTION COURT
B e f o r e :
____________________
HOLT INSULATION LIMITED |
Claimant |
|
and |
||
COLT INTERNATIONAL LIMITED |
Respondent |
____________________
Counsel for the Defendant:- Miss Delia Dumaresq.
____________________
Crown Copyright ©
"is substantially the same as the one which has been previously referred to adjudication and in respect of which a decision has previously been taken in that adjudication, within the meaning of paragraph 9 (2) of this Scheme for Construction Contracts (England and Wales) Regulations 1998."
Paragraph 9(2) provides:
"9(2)A an adjudicator must resign where the dispute is the same or substantially the same as one which has previously been referred to adjudication, and a decision has been taken in that adjudication."
"the Applicant therefore claims immediate payment the balance of the sum due under Application number 10 and earlier Applications of £139,227.13 less the part payment received on 23rd May 2000 (by the Applicant) of £28,639.57 ie £110,587.56 plus interest pursuant to contract (Clause 40.2 of the General Conditions of Contract referred to in paragraph 2 hereof - page 60)".
"1. There is, I conclude, only one substantive issue that I'm required to determine in this Adjudication. That issue is, by the terms of the referral notice, whether Colt is entitled to be paid the sum claim to arise out of the Application 10 for interim payment in the sum of £110,586.56.
2. Although Colt have by their subsequent submissions upon Holt's Response to the Referral, invited me to make numerous assessments of value in the alternative, concerning the degree of completion, and the alleged arbitrary deductions and set off applied by Holt against Application 10, I was not invited to do so by the Referral Notice.
3. I find myself in agreement with Holt's contention that my jurisdiction in this matter extends only to the consideration and determination of the above issue, and I do not consider I have power to venture into deciding matters of alternative valuation and completion, suggested by Colt, in their comments upon Holt's Response to the Referral Notice."
"The Applicant therefore claims immediate payment of the balance of the sum or sums due Application number 10 and earlier Applications calculated by the Applicants to total £97,309.77 or alternatively, such other sum or sums as the Adjudicator shall decide to be fair and reasonable in the circumstances of the claim(s) set out in clause 6 above, plus interest pursuant to the contract... on the delayed payment of £28,69.51 not made until 23rd May 2000, the sum of £24,836.07 wrongly withheld and on such other sum or sums as the Adjudicator shall decide to be fair and reasonable in respect of each element of this claim together with the costs of this adjudication as well as any other costs that the adjudicator may decide is fair and reasonable to award to the Applicant."
"In this present case I have made an inquiry as to the nature of any overlap but the fact that I have made such inquiry must not be taken as an indication that I consider that the adjudicator erred or indeed there are substantial grounds for considering that the adjudicator had erred."