BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £5, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Thames Water Utilities Ltd v Digginwell Plant & Construction Ltd [2002] EWHC 1171 (TCC) (24 June 2002) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2002/1171.html Cite as: [2002] EWHC 1171 (TCC) |
[New search] [Printable RTF version] [Help]
QUEENS BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133-137, Fetter Lane, London, EC4A 1HD | ||
B e f o r e :
____________________
THAMES WATER UTILITIES LIMITED | Claimant | |
- and - | ||
DIGGINWELL PLANT AND CONSTRUCTION LIMITED | Defendant |
____________________
Colin McCaul (instructed by Hextall Erskine for the Defendant)
____________________
Crown Copyright ©
H.H. Judge Richard Seymour Q. C. :
Introduction
“Where an escape of water, however caused, from a pipe vested in a water undertaker causes loss or damage, the undertaker shall be liable, except as otherwise provided in this section, for the loss or damage.”
No relevant exception in favour of Thames in relation to damage caused by flooding as a result of the incident on 8 February 1997 was contained in Water Industry Act 1991 s. 209 and it is alleged in the Particulars of Claim that Thames was liable to pay, and did pay, sums totalling £767,121 to four claimants which asserted that they, respectively, had suffered damage. In this action Thames claims that it incurred costs amounting to a further £20,741.97 in respect of what were called in the Particulars of Claim “Litigation Payments”. As is apparent from the terms of Water Industry Act 1991 s. 209(1), the liability of Thames under that subsection to those suffering damage as a result of the escape of water from the Main after it burst on 8 February 1997 was strict and did not depend upon whether Thames had been at fault in any way in relation to the circumstances in which the escape of water occurred.
“Nothing in subsection (1) above affects any entitlement which a water undertaker may have to recover contribution under Civil Liability (Contribution) Act 1978; and for the purposes of that Act, any loss for which a water undertaker is liable under that subsection shall be treated as if it were damage.”
“1(1) Subject to the following provisions of this section, any person liable in respect of any damage suffered by another person may recover contribution from any other person liable in respect of the same damage (whether jointly with him or otherwise)…
(4) A person who has made or agreed to make any payment in bona fide settlement or compromise of any claim against him in respect of any damage (including a payment into court which has been accepted) shall be entitled to recover contribution in accordance with this section without regard to whether or not he himself is or ever was liable in respect of the damage, provided, however, that he would have been liable assuming that the factual basis of the claim against him could be established…
(6) References in this section to a person’s liability in respect of any damage are references to any such liability which has been or could be established in an action brought against him in England and Wales by or on behalf of the person who suffered the damage;..
2(1) Subject to subsection (3) below (not material), in any proceedings for contribution under section 1 above the amount of the contribution recoverable from any person shall be such as may be found by the court to be just and equitable having regard to the extent of that person’s responsibility for the damage in question…
6(1) A person is liable in respect of any damage for the purposes of this Act if the person who suffered it (or anyone representing his estate or dependants) is entitled to recover compensation from him in respect of that damage (whatever the legal basis of his liability whether tort, breach of contract, breach of trust or otherwise).”
The statements of case of the parties
“(a) Failed to make any request from the Claimant of the details in respect of the existence and/or position of the water main;
(b) Failed to use any or any adequate detection methods to locate the existence and position of the Claimant’s water main;
(c) Failed to excavate with sufficient care or diligence the area in question so as to ensure that no damage was done to the water main;
(d) Failed to first notify the Claimant of its intention to carry out works in the vicinity of the water main;
(e) Failed to first excavate by hand;
(f) Failed to leave sufficient working space around the water main;
(g) Failed to take any or any sufficient precautions to ensure that the water main was not damaged during the course of the said works;
(h) Failed to ascertain the position and depth of the water main before causing or permitting works to be carried out in the vicinity of the water main;
(i) Causing or permitting works to be carried out in the vicinity of the site when there was a foreseeable risk that the water main would be damaged thereby.”
“8. It is denied that the Defendant or any of its servants or agents was negligent in any of the respects alleged or at all and that the fracture of the main was caused by negligence on its part.
9. The fracture of the main was caused wholly or in part by the negligence and/or breach of statutory duty of the Claimant.
Particulars
(a) Failing to maintain and provide accurate information as to the location of the main;
(b) Failing to disclose or warn that the main was located only about an inch beneath the concrete bed;
(c) Failing to heed the previous incident in a neighbouring street (Harewood Avenue) on 21st September 1996 when another contractor (McNicholas) damaged a water main under that street in similar circumstances and ensure that full and accurate information was provided to the Defendant as to the course and depth of the 36 inch main under Lisson Grove and/or to take any adequate steps to ensure that this was fully known to the Defendant;
(d) In breach of its statutory duty under section 17 of the Metropolis Water Act 1852 and/or negligently failing to mark the true Course and Situation of the 36 inch main, or cause it to be marked, on its plan of the area and/or to furnish accurate particulars thereof to the Defendant and/or in breach of its statutory duty under section 198 of the Water Industry Act 1991 and/or negligently failing to keep a true and accurate record of the location of the main and/or make such a record available to the Defendant and/or negligently failing to record the location of the 36” water main belonging to the Claimants as soon as reasonably practicable after locating it in the street and/or placing it in the street and/or being informed of its location;
(f) Failing to heed from the depth of the main and/or from that earlier incident and/or its experience generally that the breaking up of the concrete in Lisson Grove would entail a risk of thereby fracturing the 36 inch main and to take any or any adequate steps to bring this to the attention of the Defendant and/or to ensure that it was fully aware of that risk.
10. Further or alternatively, the bursting of the main was caused wholly or in part by the negligence of the Claimant.
Particulars
(i) Failing to take any or any effective measures to shut off the water supply and/or to do so with reasonable promptness;
(ii) Failing to heed from the previous incident in Harewood Avenue and/or from the case of itself v Videotron and McNicholas and the decision therein and/or from its experience generally that the water supply needed to and should be shut down by it with reasonable promptness.”
“2. C submits that the 1852 Act was impliedly repealed by The Water Act 1989 (the amending Act passed on the privatisation of the water industry, and which was the predecessor of the consolidating Water Industry Act 1991).
3. If a later Act makes contrary provision to an earlier, Parliament is taken to intend the earlier to be repealed – see Bennion: Statutory Interpretation (3rd edition) Section 87, page 225, and Supplement, at page S20. See also Re Mineral Resources Ltd, Environment Agency v. Stout [1999] 1 All ER 746.
4. Sections 20 and 165 of the 1989 Act are the equivalent provisions of sections 18 and 198 of the 1991 Act.
5. The combined effect of sections 20(10) and 165(7) of the 1989 Act is that the only remedy available for a breach of section 165 is an enforcement order under section 20.
6. The provisions of section 17 of the 1852 Act are inconsistent with sections 20(10) and 165(7) of the 1989 Act if and insofar as the former Act enables a person to bring a private law action for breach of the statutory duty imposed by section 17.
7. Accordingly, to the extent that there is an inconsistency between section 17 of the 1852 Act, and sections 20 and 165 of the 1989 Act, Parliament must be taken to have intended to repeal the 1852 Act.”
In his oral submissions Mr. Daiches modified his client’s position to the extent that he only contended for an implied repeal of Metropolis Water Act 1852 s. 17, not the whole Act, and only in relation to Thames, not in relation to the World at large.
“4. As to the breaches of statutory duty alleged at paragraph 9 of the Re-Amended Defence, the Claimant will contend that it did not owe any private law duty to the Defendant in relation to the section 17 of the Metropolis Water Act 1852 and/or section 198 of the Water Industry Act 1991. In the case of the former statute, the policy of Parliament was that the only remedy for enforcement should be the penalty imposed by section 16. In the case of the latter statute, the policy of Parliament was that the only remedy for enforcement should be an enforcement order made pursuant to section 18.
5. In the premises, the Claimant will contend that Parliament intended to exclude any private law duty of care which might arise by reason of any omission by the Claimant (which is not admitted) to perform the relevant statutory duties.”
The issues to be tried
Metropolis Water Act 1852 s. 17
“Every company shall, within one year after the passing of this Act, cause a map to be made of the district within which any mains or pipes shall have been laid down or formed by them on a scale not less than six inches to a mile, and shall cause to be marked thereon the course and situation of all existing mains and pipes and shall, within six months from the making of any alterations or additions, cause the said maps to be from time to time corrected, and such additions made thereto as may show the line and situation of all such mains and pipes as may be laid down or formed by them from time to time…; and such map, or a copy thereof, with the date expressed thereon of the last time when the same shall have been so corrected as aforesaid, shall be kept in the principal office of each company, and shall be open to the inspection of all persons interested in the same within the said district, who shall be at liberty to take copies of or extracts from the same.”
“Subject to subsections (4) and (5) below, it shall be the duty of the Authority and of every water undertaker to keep records of the location of –
(a) every resource main, water main or discharge pipe which is for the time being vested in the Authority or, as the case may be, that undertaker; and
(b) any other underground works, other than a service pipe, which are for the time being vested in the Authority or, as the case may be, that undertaker.”
“The duties of a water undertaker under this section shall be enforceable under section 20 above by the Secretary of State.”
“Where any act or omission constitutes a contravention of a condition of an appointment under this Chapter or of a statutory requirement enforceable under this section, the only remedies for that contravention, apart from those available by virtue of this section, shall be those for which express provision is made by or under any enactment and those that are available in respect of that act or omission otherwise than by virtue of its constituting such contravention. ”
The mains in Lisson Grove
Maps of the mains in Lisson Grove
“The position of apparatus shown on this plan is believed to be correct but Thames Water Utilities Limited accepts no responsibility in the event of any inaccuracies. The actual position of such apparatus and of service pipes which are not shown on the plan must be established on site.”
He also said that a similar disclaimer appeared on copies of plans provided in electronic form by Thames. Why no form of disclaimer appears on the copies of the plans of water mains produced by Digginwell on disclosure is unclear. I am not sure that the issue whether the maps provided to Digginwell did contain, or should have contained, some disclaimer is particularly important. The scale of the maps is such that the lines of the mains marked cannot be precisely accurate. Moreover, it was, I think, accepted on behalf of Digginwell, at least by Mr. Tony Mullarkey in his cross-examination, that it was understood that the lines of services shown on maps such as those maintained by Thames were approximate.
The McNicholas incident
8 February 1997
“On arriving on site at Lisson Grove 7.30am, I checked stats drawings to ascertain what utilities were present. I found on the stat drawings 1 24” gas main and 1 180mm gas main (polyethylene). I also found 3 water mains 4”, 9” and 36” trunk and numerous LV and HV cables.
I proceeded to scan the road on radio and power mode, and mark utilities found. I was unable to find all utilities as indicated on drawings. I proceeded with my transmitter (genny) on induction mode to find the line of any other utility. I placed my transmitter on water and gas valves in the immediate facility and proceeded to trace the lines of the mains. I located 3 separate mains. The first reading was approximately 1M from the kerb southbound, the third reading was on the white line. These two readings were found by inducing a signal on water valves. A second signal was found between the first and third signal. I proceeded to mark the signals.
Signal 1 water Blue
Signal 2 gas yellow
Signal 3 water Blue.”
“I have also noted some of the comments made by the Digginwell staff in locating the mains prior to the commencement of [sic] by using cat and genny operating equipment. These comments are made in the witness statements in the previous proceedings and also in the two contemporaneous statements provided on discovery. It is possible to have located the position of the 4” and 9” mains prior to the start of works. However, it would not have been possible for the 36” main to be located by this method. The cat and genny is a piece of equipment which allows the presence and direction of metal mains to be located. It works by placing one piece of equipment over part of the main above the surface, i.e. a valve or standpipe. This generates an electro-magnetic field in the main, which is located by the second piece of equipment. This would have been possible for the 4” and 9” main due to the relative proximity of the valves/standpipes etc to the incident. However, the only places where the equipment could have been placed on the 36” mains were approximately 1-1½ miles on either side of the incident. It is highly unlikely that the Defendant’s operatives would have walked this far and, in any event, the signal would not have been carried that far back to the site of the incident to allow the 36” main to be located. It would appear that they located the 4” and 9” mains and a main operated by the gas transporter, Transco. However, I would think it unlikely that they attempted to locate the actual position of the 36” main. ”
“3. During the previous couple of weeks ducting had been laid down the middle of Lisson Grove and Harewood Row. It was therefore the intention to connect the two lines of ducting at the junction of Lisson Grove/Shroton Street [a street almost directly opposite Hayes Place] and involved laying it across the junction. It was a busy junction and the work had to be carried out at the weekend in order to minimise disruption to traffic.
4. I arrived on site around 8.30 a. m. having picked up a compressor beforehand. There were four people in the gang since two of the gang needed to work the STOP/GO boards in order to control the traffic. The site had been marked up prior to our arrival by Kevin McGlinchey, who was Digginwell’s professional tracer. We also had a CAT machine with us that we used to locate cables whilst digging the trench into which the cables were laid. We also had a drawing showing the location of the Thames Water mains with us. As far as I recall the Thames Water drawing showed that there was a large 36” main in the pavement and a small 9” main in the road. Kevin McGlinchey had identified the mains services in the road and in the pavement. The 9” main was shown on the drawing in the middle of the road and we assumed that to be correct. The main that had been identified by Kevin McGlinchey in the pavement we thought was the 36” main, ie the larger one.
5. At about 9 a.m. on the 8th February 1997 we started work by excavating a trench for the ducting and identifying the services in the road near the pedestrian crossing. We were slowly working our way across the road with jackhammers and the CAT in order to locate the services. However, as we got further out into the road, the road surface got thicker and it was not possible to use jackhammers. At about 12 noon we started excavating the middle of the road with the intention of working around the 9” main that had been marked up. We were working carefully to try and avoid that main and locate its position. The surface of the road is made up of a surface layer of tarmac, approximately 4 to 6 inches thick followed by a concrete layer of approximately 12 or 13 inches. The jackhammers are not capable of breaking through this concrete layer. Therefore, we were using the JCB and had starting [sic] excavating approximately 2 feet to the side of the marked up main, which, as I have said, we assumed to be a 9”main. Unfortunately, that was incorrect and the main was in fact a much larger 35 [sic] inch main. Furthermore, the top of the main was actually embedded into the concrete layer of the road surface by 2 or 3 inches. As a result, as the JCB pecker began to work its way through the concrete layer, its vibration caused a compression fracture of the main. If the main had been a 9 inch main, as identified on the drawing, we would have been well clear of it and the JCB’s vibration would not have caused any damage to it.
6. At, approximately, 12.10 pm before we had broken through the concrete layer of the road surface water started to appear in the trench and we immediately stopped work. We contacted Vincent Sugrue, Digginwell’s London Agent, to inform him of the situation. The JCB driver had a mobile ‘phone which we used to do that. Vincent Sugrue arrived on site at, approximately, 12.50 p.m. and took charge. I understand that Vincent Sugrue reported the incident, via Digginwell’s office, immediately to Thames Water. However, as I recall, Thames Water personnel did not arrive on the site for a couple of hours. Kevin McGlinchey arrived on site shortly after Vincent Sugrue at about 1.30 p.m.
7. Initially the water leaking from the main was not too bad. Whilst it was enough to bubble onto the road surface it was flowing away down a drain. In order to try and prevent the damage to the main getting worse, we placed the pecker of the JCB on the point where the main had fractured. However, as the afternoon progressed the pressure of water in the mains gradually made the leak worse until at approximately 3.30 or 4 pm the water had got to the stage where it was flowing across the road. Thames Water personnel had by this time been on site for a couple of hours but as I recall were having difficulty locating the valve to turn off the water main.”
“At approximately 12.10pm on Saturday 8th February 1997 I received a telephone [call] from the Ganger Man Tony Mullarkey who was working at Lisson Grove to say that he had hit some kind of water main.
I immediately made a telephone call to the Office and asked them to telephone the Water Board and give them the address of the hit and then made my way to the site, I was only 5-10 minutes away.
I arrived on site approximately 12.20pm and saw there was some water coming up onto the road, though not very much at this stage. I also noticed that the JCB still had its pecker stuck where the water main was hit.
At 1.05pm the first Water Board van turned up. He was examining drawings for some time and some other vans turned up and they all seemed to be walking up and down looking for a valve. At this stage there still was not a large amount of water coming up.
At approximately 3.45pm the water main exploded. It was obviously [sic] then that it was a large water main.”
“At approxmately 12.10pm I received a telephone call from Vincent Sugrue, a Digginwell Agent. He informed me that the gang working on Lisson Grove junction with Hayes Place had struck a water main. I asked him had the water board been informed he said yes. I also asked him do we know what size it was. He replied No, but we think it is the 9” according to the drawings.
He instructed me to return to site which is common practice. On returning to site I observed a JCB with a hydraulic hammer in the ground with water coming up around the hammer. I asked the JCB driver how deep he was. He replied “I’ve got a 12” point and I observed the face of the hammer was still visible above the ground. I advised him to leave his point where it was until the Water Board told him to remove it. Which he did.
When the Water Board representative arrived on site he was unable to identify what size water main it was and then proceeded to check his drawings and turn off valves. On doing this Thames Water Supervisor located a valve under the stabiliser jack of the JCB. He asked the JCB driver to move his jack off the valve without moving his point. On doing this the water increased twofold. The Water Board official informed Vincent Sugrue and myself that he had located another valve underneath a Volvo Estate car and asked us for our assistance to manually move the car. Unable to move the car physically we proceeded to knock on local residential properties to ascertain the owner of the vehicle with no avail and informed the Water Board. The Water Board informed us that they would contact the police to get the vehicle moved.
At approximately 3.45pm the water main exploded.”
“At approximately 12.35 – 12.40 p.m. I arrived at the site. I discovered a pecker operated by the Defendant with its digging point in the road. Water was emerging from around the digging point and rising out of the ground to a depth of about 1 foot. At this stage I was not able to establish what had been hit by the pecker but considered it to be a main of some size given the amount of water that was flowing. However, the flow at this stage did not appear to suggest that the 36” main had been hit. The Digginwell staff were still on site at this stage. When attending at a site there is a procedure, which all NST’s follow when shutting down mains. The procedure is to shut down the smallest main first, up to the largest main. In this case the smallest was the 4” followed by the 9” and then the 36”. The procedure is set out because it can never be said with any certainty what main has been damaged. In some cases a 9” main can produce as much flow as a 36” main. Also, given that the site of the damage is usually deep in water it is often very difficult to ascertain what has actually been damaged. Additionally, the shut down of a 36” main requires a great deal more organisation, additional employees and authorisations before it can be shut down.”
Negligence on the part of Digginwell
“11. Our safe system of work has three basic elements:
(a) Plans
Whenever possible, plans or other suitable information about all buried services in the area should be obtained before excavation work starts, and the utilities should do everything reasonably practicable to ensure that such information is made available to enquirers. When this is not possible, as may be the case when emergency or other unforeseen work has to be undertaken, the excavation should be carried out as though there are buried services in the vicinity. Account should be taken of any indications that buried services exist, such as the presence of lamp posts, illuminated traffic signs, valve pit covers, etc. However, the absence of such indications does not necessarily mean that there are no buried services…
(b) Cable and pipe locating devices
Suitable cable and pipe locating devices should be used, in conjunction with any available plans, to determine as accurately as possible the position of metallic underground services in or near the proposed work area. These devices will not detect plastic pipes…
(c) Safe digging practices
Excavation work should be carried out carefully, and follow recognised safe digging practices…
12. These key elements – plans, locators and safe digging – complement each other, and all three should be used when working near buried services. Using only one may not be enough: for example, a cable may be shown on a plan as a straight line, with measurements taken from fixed objects at the time of installation, whereas in practice the cable may snake or may have been moved out of position. Reliance on the plan alone would give a false position, but this could be alleviated by the correct use of a cable locator. If several cables are close together a locator may show them as a single cable, whereas the plan would help give a more accurate picture…
Safe digging practice
25. Once a location device has been used, excavation may proceed, with trial holes dug using hand tools as necessary to confirm the position of any buried services. Special care should be taken when digging above or close the assumed line of such a service. Hand held power tools and mechanical excavators are the main causes of danger and they should not be used too close to underground services….
26. Incorrectly used hand tools are a common source of accidents but when carefully used they can normally provide a satisfactory way of exposing buried services, once the approximate positions have been determined using plans and locators. Every effort should be made to excavate alongside the service rather than directly above it. Final exposure of the service by horizontal digging is recommended as the force applied to hand tools can be controlled more effectively. In particular:
(a) spades and shovels should be used rather than other tools. They should not be thrown or spiked into the ground, but eased in with gentle foot pressure;
(b) picks, pins or forks may be used with care to free up lumps of stone etc and to break up hard layers of chalk or sandstone; and
(c) picks should not be used in soft clay or other soft soils near to buried services…”
“In my opinion, DPACL should have anticipated that the thick concrete slab served some purpose, the probability for which was as a protection to other apparatus laid at a more shallow depth than normal. To switch from excavation by hand to excavation by machine in these circumstances was cavalier in the extreme.”
“My understanding of the evidence of Mr. Mullarkey is that, having encountered hard concrete in the course of excavating the trench across Lisson Grove, he decided to try to approach the area covered by the hard concrete from the west side of it. When he caused the JCB pecker to seek to break up concrete some 4 feet from the point the excavation had reached he ought to have recognised that the pecker had not got past the area of hard concrete and should have taken it further to the west until beyond the area of hard concrete.”
Mr. Hurwood did not explain how Mr. Mullarkey should have recognised that he had not got past the area of hard concrete.
Negligence on the part of Thames
Causation of the loss of the Victims
“23. In the light of the September 1996 incident, Thames Water should have updated their plans to show the correct location of the 36” main and its depth below surface level or alternatively added a note at the site of the 1996 incident.
24. By November 1998 Thames Water had not updated their drawings to show the correct location of the 36” main or its depth below ground level…
32. The proper procedure to be adopted by a water company on being advised of damage to a water main is as follows:-
- NST (or an inspector) attends site
- NST makes an assessment of the mains that have been damaged, considers the implications including:
- the number of properties at risk of loss of supply,
- type of customers likely to be affected (eg the sick, elderly, disabled, hospitals, schools and other vulnerable sections of the population),
- the risk of flooding and third party damage, and
forms an assessment of the appropriate course of action.
- NST calls control centre to discuss his assessment and agrees a plan of action, including requesting assistance as necessary;
- NST implements agreed plan of action whilst continuing to monitor the position and reviewing and amending the plan in the light of any changes in the circumstances.”
I accept the evidence contained in those parts of the agreement between Professor Evans and Mr. de Silva which I have set out. That evidence seems to me to represent what is just plain common sense. It is in rather marked contrast to the rigid and inflexible approach adopted by Thames on the basis of its received procedure. That someone attending the scene of an occurrence of damage to a main should try to assess what has been damaged, and then seek to mitigate the consequences of that damage, strikes me as blindingly obvious.
Conclusion