BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just Β£1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Royal Brompton Hospital National Health Service Trust v Hammond & Ors [2002] EWHC 2037 (TCC) (11 October 2002) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2002/2037.html Cite as: [2002] EWHC 2037 (TCC), 88 Con LR 1 |
[New search] [Printable RTF version] [Help]
QUEENS BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
133-137, Fetter Lane, London, EC4A 1HD | ||
B e f o r e :
____________________
THE ROYAL BROMPTON HOSPITAL NATIONAL HEALTH SERVICE TRUST | Claimant | |
and | ||
(1) FREDERICK ALEXANDER HAMMOND (2) JOHN RICHARD LERCHE (3) ANTHONY ROBERT HARRIS (4) ALAN MASSEY (5) ALFRED GEORGE HEPDEN (6) SYLVIAN REINHOLD (7) BRIAN ERNEST TEALE (8) WATKINS GRAY INTERNATIONAL (UK) (9) AUSTEN ASSOCIATES (a firm) (10) NORTHCROFT, NEIGHBOUR AND NICHOLSON (11) CLARKE NICHOLLS & MARCELL (a firm) (12) ARLINGTON PROJECT MANAGEMENT LIMITED (13) PROJECT MANAGEMENT INTERNATIONAL LIMITED (14) IVOR GORDON BERRESFORD (15) KEITH PEGDEN SMITH (16) AUSTEN ASSOCIATES LIMITED | Defendants |
____________________
Adrian Williamson and Abdul Jinadu appeared for the 1st to 7th and 13th Defendants, PMI, instructed by Davies Arnold Cooper.
Marcus Taverner QC and Richard Edwards appeared for the 8th, 14th and 15th Defendants, WGI, instructed by Fishburn Morgan Cole.
Andrew Bartlett QC and Jane Davies appeared for the 9th and 16th Defendants, AA, instructed by Berrymans Lace Mawer.
____________________
Crown Copyright ©
His Honour Judge Humphrey LLoyd QC
Relevant Event | Period | New Date for Completion |
Delayed handover of Chelsea Hospital forWomen (CHW) | 10 weeks | 1 October 1989 |
Delayed handover of CHW | 1 week | 8 October 1989 |
Vaults and reinforcement | 4 weeks | 12 October 1989 |
(concurrent) | ||
Instructions to lay Hydrotite | 5 weeks | 12 November 1989 |
Late M&E information | 2 weeks | 26 November 1989 |
Instructions to lay Hydrotite (plus 2 weeks for Christmas) | 7 weeks | 14 January 1990 |
LEB substation (later revoked) | 2 weeks | 28 January 1990 |
Late M&E information and safety cabinets | 2 weeks and 1 week | 18 February 1990 |
Safety cabinets and reinforcements | 2 weeks and 2 days | 6 March 1990 |
Late M&E information and commissioning | 5 weeks and 8 weeks | 22 May 1990. |
Expert Evidence
"The duty and standard of care to be expected from (the architect) was accepted as being that which applied to any profession or calling which required special skill, knowledge or experience. The test is that formulated in a medical negligence case Bolam v Friern Hospital Management Committee [1957] 1 WLR 582. Where there is a conflict as to whether he has discharged that duty the courts approach the matter upon the basis of considering whether there was evidence that at the time a responsible body of architects would have taken the view that the way in which the subject of enquiry had carried out his duties was an appropriate way of carrying out the duty, and would not hold him guilty of negligence merely because there was a body of competent professional opinion which held that he was at fault. The onus of proving negligence, of course, rests firmly upon the person who alleges it"
However Mr Taverner acknowledged both that not every claim of professional negligence had to be supported in that way and that none of the RBH claims which I have to decide had at its heart an issue involving competing schools of professional practice, such as the court had in mind in Bolam. Mr Williamson also accepted that RBH's case against PMI in respect of the hydrotite claim (i.e. that PMI failed to advise RBH of the (unspecified) risks of additional non-direct costs and delay consequent on the decision to authorise the laying of hydrotite, to which I shall come later) did not require the Bolam test, and that the evidence from the experts on project management in respect of the blue land claim and much of the M&E was not truly evidence of practice but of personal re-action. However both submitted that it did not follow that expert evidence was not needed where the Bolam test did not apply. Mr Taverner prefaced his submissions with a useful resume of the types of mistakes that lead to claims of professional negligence: giving factual advice that is incorrect or incomplete; omitting to inform the client of a fact, either because the professional person is unaware of it, or because he or she fails to appreciate the need to communicate it; giving "non-factual" advice (such as a recommendation or prediction) that is wrong or acting in a way that is wrong because it is based on an incorrect or incomplete understanding of the facts; giving non-factual advice that is wrong because, though based on a correct and complete understanding of the facts, the wrong conclusions have been drawn from those facts; omitting to give non-factual advice or not acting, because the need for such advice or action was not foreseen; taking action that is inappropriate in the relevant circumstances (here what is appropriate may depend on contractual provisions, laws or codes of practice, risks, and the client's instructions and objectives). Mr Taverner also submitted that however careless a professional person may be in considering the facts, forming an opinion or determining what action to take, there is no liability if the advice or action complained of was the appropriate action or the correct advice. He cited Matto v Rodney Broom Associates [1994] 2 EGLR 163 at 168: "A professional man is entitled to be lucky", and also Watts v Savill (unreported, 16 June 1998, Court of Appeal). However this submission is about causation: there is no liability because the negligence has not or would not have caused any loss or damage.
"The question is, however, in what circumstances should one apply the test? There are qualifications to it as follows.
1. One such qualification is provided by Bolitho v City of Hackney Health Authority [1998] AC 232 namely:
"But if, in a rare case, it can be demonstrated that the professional opinion is not capable of withstanding logical analysis, the judge is entitled to hold that the body of opinion is not reasonable or responsible."
"(The judge) was entitled to take the view that the evidence of (the architect's experts) did not constitute evidence of a reasonable body of architects accepting as a proper practice that no warning of inflation need be given when providing an estimate of the cost of proposed works. It seems to me that the learned judge had ample evidence before him which entitled him to find that there was a failure on the part of Mr. Nye to draw the attention of the client to the fact that inflation was a factor which should be taken into account when considering the ultimate cost and that that failure constituted a breach of the Hedley Byrne type duty to the defendant.
3. The third qualification is expressed by Lloyd L.J. in Gold -v- Haringey Health Authority [1988] 1 Q.B. 481 at 490:
"If the giving of contraceptive advice required no special skill, then I could see an argument that the Bolam test should not apply."
"Now Mr Harvey urges that this is a class of case in which the court can find a breach of professional duty without having before it the standard type of evidence as to what constitutes lack of care on the part of a professional man in the relevant circumstances. There may well be cases in which it would be not necessary to adduce such evidence as for instance, if an architect omitted to provide a front door to the premises. But it would be grossly unfair to architects if, on a point of the type now under consideration, which relates to a special type of dwelling, the courts could without the normal evidence condemn a professional man."
In my view the ultimate decision of the Court of Appeal in Nye Saunders is also consistent with this third point, as Sedley LJ pointed out in his judgment in Williams see page 834-5: "Nye Saunders, despite the concession that it was governed by the Bolam test, was manifestly an exercise in standard-setting by the court itself and should be so regarded".
"As I read the evidence the experts were doing no more than putting themselves forward as reasonably competent architects and then saying what they would have done in the circumstances in which Mr Warrington found himself. In my judgment this case could well have been decided and disposed of by adoption of Oliver J's views in Midland Bank Trust Co. Ltd -v- Hett, Stubbs & Kemp (a firm) [1979] Ch. 384, 402:
"Clearly, if there is some practice in a profession, some accepted standard of conduct which is laid down by a professional institute or sanctioned by common usage, evidence of that can and ought to be received. But evidence which really amounts to no more than an expression of opinion by a particular practitioner of what he thinks that he would have done had he been placed, hypothetically and without the benefit of hindsight, in the position of the defendant, is of little assistance to the court ".
Moreover on the facts of Williams the Court of Appeal held that the Bolam test was not applicable since the conclusion in question required "the exercise of judgment .in deciding whether further investigation of the relevant risk was required or not [and] did not of itself require any special architectural skills" (per Ward LJ at page 831). In my view the ultimate decision of the Court of Appeal in Nye Saunders is also consistent with the second point, as Sedley LJ pointed out in his judgment in Williams (see page 834-5).
"Moreover, to make good a charge of professional incompetence, for that is what it involves, will often involve a fellow professional in the same area of practice indulging in an attempt to second-guess the judgment of the defendant sometimes many years after the defendant was called on to express his professional opinion and in circumstances where neither party is able with confidence to replicate the precise circumstances in which the opinion under attack came to be expressed and where the defendant for this reason may well find himself seriously disadvantaged. It is for reasons such as these that an allegation of should not be lightly made and that the law requires that such an allegation should be distinctly proved."
However in such circumstances the position of such a party is the same as any other defendant. A claim for professional negligence is a claim for breach of contract or of some contractual duty of care and the fact that a defendant's reputation is at stake does not require the professional person to be treated differently from somebody comparable, such as a specialist manufacturer or supplier.
"It by no means follows that a professional valuation or opinion was negligently given because it turns out to have been wholly wrong. Whether or not there has been negligence is, of course, a pure question of fact depending upon the particular circumstances of each case."
In Saif Ali v Sydney Mitchell & Co [1980] AC 198 Lord Diplock said at page 220:
"No matter what profession it may be, the common law does not impose on those who practice it any liability for damage resulting from what in the result turn out to have been errors of judgment, unless the error was such as no reasonably well-informed and competent member of that profession could have made."
In addition, when discussing the position of PMI, WGI or AA (1) although for convenience I may refer to PMI, WGI, or AA, where it is necessary to identify a person, the reference is to the relevant partner or individual responsible; (2) it is that person's competence which is being considered, although as partner or employee of a reputable entity; (3) the standard applied is that set out in Saif Ali, whether an individual or a firm is being considered.
The Blue Land
"Following our discussion this morning, I enclose a site plan showing how much of the Kingsmead site we think it would be desirable to offer the Phase 1 contractor. You will see that it is somewhat larger than 'the blue area' which has been generally talked about before."
The site plan enclosed no longer exists. Mr King could not remember what the enclosure showed but admitted that it might have shown the Original Proposed Reserved Land.
"BILL NO 1
GENERAL CONDITIONS AND PRELIMINARIES
Page 1/1
A. GENERALLY SCOPE: these conditions are supplementary to those stated in the invitation to tender and on the Form of Tender. |
ACCEPTANCE OF TENDERS: the Contractor shall allow for a period of 6 weeks between the date of tender and acceptance during which the tender documents may be checked and approval sought from the Employer. |
POSSESSION OF SITE: It is anticipated that the date for site possession will be within 8 weeks of the date of tender submission. |
B. PRICING OF BILLS |
ALTERATIONS AND QUALIFICATIONS to Bills of Quantities shall not be made without the written authorisation of the Quantity Surveyor. Lined through amendments will be disregarded or the entire tender containing them will be rejected depending upon the nature and extent of the amendments. |
UNPRICED ITEMS: costs relating to items which are not priced will be deemed to have been included elsewhere in the Bills of Quantities. |
LUMP SUM ADJUSTMENTS: should the Contractor add or deduct a lump sum in any part of the Bill it will be assumed that such adjustment represents a percentage of the value of the Contractor's Own Work (i.e. the Contract Sum exclusive of P.C. and Provisional Dayworks) unless otherwise indicated. |
ERRORS: errors in the priced Bills will be dealt with in accordance with the Code of Procedure for Single Stage Selective Tendering 1977. Alternative 1. |
C. SUBMISSION OF TENDER |
At the time of submitting the Tender, one fully priced and totalled copy of the Bills of Quantities, duly certified as being the copy upon which the tender is based, shall be submitted under sealed cover to the Quantity Surveyor using the label provided. |
The Contractor is to prepare and submit with his tender a fully detailed time schedule and method statement in accordance with which he proposed to execute the works. D. [In handwriting] The Contractor is to submit with his tender a fully detailed time schedule and method statement in accordance with which he proposes to execute the works. Page 1/2: |
A. Acceptance of Tender |
As soon as the Tender is accepted the Quantity Surveyor will prepare two copies of the Contract Bills. |
JOINT VENTURE |
Tendering shall be on a joint venture basis with each tenderer comprising a partnership of a general building contractor and a building services contractor formed specifically for the project and with the primary objectives of a joint and several liability of the partners for the execution of the Contract and the avoidance of a sub-contractual arrangement in respect of the generality of the services elements. To the extent that sub-contractual arrangements are required in respect of certain restricted specialist installations or work, whether nominated or domestic, such sub-contracts shall be between the sub-contractors and the joint venture partnership rather than between the Sub-contractors and one of the joint venture partners. This latter requirement is a particular application of the general intention that the term 'Contractor' throughout the Contract Documents shall be deemed to apply to the successful Joint Venture Tendering Partnership. |
THE PARTIES |
The names and addresses of the parties to be named in the Contract are as follows: |
Employer: The National Heart & Chest Hospitals Project Manager Project Management International The Lodge Harmondsworth West Drayton Middlesex UB7 OLA |
Architect: Watkins Gray International (UK) Alexander House 1a Spur Road Orpington Kent BR6 OQR have been appointed by the Board of Governors of the National Heart and Chest Hospitals as Project Managers for the development. Accordingly Project Management International are empowered to exercise the authority of the Employer under the provisions of the Contract. |
Quantity Surveyor: Northcroft Neighbour & Nicholson Leda House Station Road Cambridge CB1 2RF The names and addresses of the other consultants and their areas of responsibility are as follows:- Services Engineer: Austen Associates 45 Coombe Road Croydon Surrey CRO 1BQ Responsible for the design and supervision of drainage, plumbing and engineering and electrical installations. Structural Engineer: Clarke Nicholls and Marcell Galena House 8 30 Galena Road London W6 OLT Responsible for the design and supervision of the structural elements of the buildings. |
DESCRIPTION OF THE SITE |
The site is located at Sydney Street, Chelsea, SW3 and is bounded by Cale Street, Sydney Street, Britten Street and the Chelsea Hospital for Women to the North East, South and West respectively. |
Access to the site shall be determined by the Contractors in consultation with the relevant Authorities. |
WORKING AREA: the Contractor will be confined to the boundaries of the site as marked on Site Plan No. |
ADJACENT BUILDINGS: Buildings immediately adjacent to the site are the Chelsea Hospital for Women and No 30 Britten Street. |
ARRANGEMENTS FOR VISITING THE SITE: before tendering the Contractor shall examine the drawings and conditions of Contract and visit the site to satisfy himself as to all the local conditions affecting the execution of the Contract including accessibility of the site, local restrictions, the full extent and character of the proposed works, the nature of the ground, the supply of and conditions affecting labour and materials and the execution of the contract generally as no claim in the grounds of want of knowledge in such respect will be entertained. Facilities for the inspection of the site are to be arranged with J Wragg PMI Telephone No 01-759-0960. |
DESCRIPTION OF THE WORKS |
THE PROJECT comprises a six storey building with three internal courtyards and has a gross floor area of 21,770 m2 providing adult and children's' general acute, intensive car and heavy dependency beds; operating theatres; pathology laboratories; central kitchens and various ancillary and service departments including main boilers and flues. There are also external works of roads, paths and other paved areas; 'landscaping' including the internal courtyards and external services mains, drainage and the like." |
"You mentioned yesterday about the timing of our occupation of the 'blue' land on the Kingsmead site just off Britten Street. This will be required by the middle of September and I think it might be useful if Douglas Bayle, John Wragg (PMI) and myself met to agree the way in which we can provide access to the 'pink' land which I think Bayle does require."
Some of the background to that note can be found in Mr King's evidence where he said that at the beginning of 1986 a decision had been made to move the medical gases compound from its originally planned location to the south of Britten Street to an area on the western boundary of the site adjacent to the Hospital. As a result the offices used by CFM did not need to be demolished and the area eventually made available to TW was freed, subject to the access to which the note refers.
"NHCC PHASE 1 SITE LOCATION PLAN 03 2621 EWO 1
Please find enclosed a marked up copy of the above plan showing-
(a) Hoarding to MR Unit
(b) The additional area allocated for site offices/parking on the south side of Britten Street.
Both these items are to be referred to in the Preliminaries with a reference to this drawing, as agreed."
"DESCRIPTION OF SITE
The SITE is located at Sydney Street, Chelsea, SW 3 and is bounded by Cale Street, Sydney Street, Britten Street and the Chelsea Hospital for Women to the North, East, South and West respectively.
ACCESS TO THE SITE will be from Cale Street.
WORKING AREA: The Contractor will be confined to the boundaries of the site as marked on Site Plan No. 03 2621/PW 185"
In his witness statement Mr Wragg said that he met TW's estimating team on 23 September 1986, and that he distinctly recalled showing them the area that was actually made available, since he had no reason to suspect that the area was wrongly indicated on Drawing PW 185. He said:
"The extent of land to be made available to TW was clear, as the Plot was a self contained unit, clearly defined by boundary fencing separating it from the garden centre and adjacent property.
During the visit I emphasised to TW's representatives that the Plot was for offices and car parking only."
He also said:
"This restriction of use, I understood from Mr King, resulted from CFM's desire to ensure that the land was not used for any purpose which interfered with its business. Thus, it would not have been acceptable for this area of land to be used for storing materials which would have resulted in noise or excessive traffic on the site. Likewise it would not have been acceptable for the canteen to have been located in this area, because of the potential disturbance caused by site workers (up to 300 people at the peak) using this canteen throughout the day. . I also informed them of CFM's access requirements."
"Site accommodation: All the site offices, stores and messing facilities will be provided in the designated area of Britten Street, opposite the MR unit. The area south of the building will be used as an area to stockpile backfill material ..."
Just as the time it took for the penny to drop and for TW to realise its rights, that fact is nevertheless only a matter for comment unless it afforded RBH some substantive defence. In my judgment Mr Williamson's submission is in this instance a somewhat artificial reading of the contract and is not consistent with its ordinary and natural meaning which is that which justified TW's claim.
"Q. Now, taking all those matters into account, Mr Adams, would you agree with me that PMI's error, if such it was, is a borderline error, rather than one that falls into the area of professional negligence?
A. Well, it is clearly not competent to take an instruction from a client, give an erroneous instruction to an architect, fail to check the product of that erroneous instruction. I cannot see how that complies with the reasonable skill and care to be expected of a competent person, never mind a project manager, harsh as it may seem."
Q. But, of course, if they did get the drawing, and if they looked at it, they would not have realised there was any discrepancy to what they had sent WGI?
A. No, but it should have dawned on them at that point that the site that the architect had drawn up was substantially bigger than the site they had been shown the previous day, that was bounded by fencing and contained a low rise office building.
M & E Drawings
50. By reason of the terms of the WGI retainer set out in paragraphs 13.4.1, 13.4.3, 13.4.4, 13.4.6, 13.4.10, 13.4.11, 13.4.12 and 13.4.13 above WGI was under a duty to co-ordinate, direct programme and/or oversee the preparation of co-ordination drawings and provision of builders work information by Austen Associates.
51.
51.1 Further, by reason of the terms of the PMI retained set out in paragraph 9.6 (and in particular subparagraphs (e), (f), (g) and (m) thereof) above, PMI was under a duty to monitor, co-ordinate and/or oversee the preparation of co-ordination drawings and provision of builders work information by Austen Associates.
51.2 Further, by reason of the terms of the PMI retainer set out in paragraph 9.6 (and in particular subparagraphs (e), (f), (g) and (m) thereof) above, PMI was under a duty to monitor, co-ordinate and/or oversee the discharge by WGI of its duties set out in paragraph 50 above.
52.
52.1 In about the second week of February 1987 Austen Associates orally advised Brian Teale of PMI on behalf of the Board that Austen Associates had the bulk of design information ready for issue (following various amendments to the design to produce reductions in the contract price).
52.2 By a letter dated the 16th February 1987 and/or orally at about the same time, PMI advised the Board of the advice given by Austen Associates set out in the preceding subparagraph and that the information needed by Taylor Woodrow was available and that there was no reason why Taylor Woodrow should be able to claim any delay by reason of late release of information.
52.3 Austen Associates and PMI gave the advice set out in the proceeding subparagraphs knowing that, as was in fact the case, the Board would rely upon it in agreeing to a start date of the 2nd March 1987 for the main contract.
52.4 In fact, as set out below, Austen Associates was not in a position to provide Taylor Woodrow with co-ordinated mechanical and electrical drawings and/or the bulk of such drawing in about mid-February 1987 so that the bulk of design information was not ready for issue and/or the lack of preparation of such drawings was such that there was very reason why Taylor Woodrow would be able to claim delay by reason of late release of information.
53.
53.1 Hospitals, including the hospital, have a particularly large number of mechanical and electrical services.
53.2 In the hospital, the mechanical and electrical services were generally concentrated in the ceiling voids. In particular:
53.2.1 Domestic hot water flow, domestic hot water return, domestic cold water flow, medical gasses, steam, condensate, heating flow, heating return, mains water, pathology cold water service, laboratory drainage ventilation pipework, waste pipe work, natural gas pipework, cold room refrigeration pipework, pumped drainage pipework, rainwater pipework, soil pipework, drainage ventilation pipework, supply ventilation pipework, supply air-conditioning pipework, extract ductwork, fume and safety cabinet extract ductwork, electrical ladder racks, electrical trunkings and conduit runs.
53.2.2 Of the services listed in paragraph 53.2.1 above, the following had to be installed with a fall or gradient: domestic hot water flow, domestic hot water return, domestic cold water flow, steam, condensate, heating flow, heating return, mains water (if possible), pathology cold water service, waste pipework, pumped drainage pipework, rain water pipework, soil pipework and fume and safety cabinet extract ductwork.
53.2.3 Of the services listed in paragraph 53.2.1 above, the following had to be insulated: domestic hot water flow, domestic hot water return, domestic cold water flow, steam, condensate, heating flow, heating return, mains water, pathology cold water service, cold room refrigeration pipework, supply air-conditioning ductwork and some rainwater pipework.
53.3 In the premises, it was essential that great care was taken to co-ordinate the services in the hospital so as to avoid clashes.
54.
54.1 In 1987, Taylor Woodrow was programming the execution of its works by programme TWC/B364/B/P01/C, which provided for the start of the first fix of mechanical and electrical works to be carried out as shown in the second column in the table below. Austen Associates provided purported co-ordinated drawings on the dates shown in the third column in the table shown below:
Level | (1) Date first fix M&E due to start | (2) Date Austen Associates provided drawings | Interval between (1) and (2) |
5.10.87 | 14.8.87 | 8 weeks | |
16.11.87 | 7 & 18.9.87 | 8-10 weeks | |
4.1.88 | 20.10.87 and 6, 10 and 13.11.87 | 7-11 weeks | |
8.2.88 | 23.11.87 and 6.1.88 | 5-10 weeks | |
14.3.88 | 4 and 15.1.88 | 8-10 weeks | |
25.4.88 | 15.1.88 and 8.2.88 | 11-14 weeks |
54.2 The drawings provided by Austen Associates were indicative of Austen Associates' design intent, but did not show sufficient detail for installation purposes. In particular, they contained no sizes for pipework, ductwork or cables, no dimensional or ductwork locations were shown and they did not demonstrate that the service routes were practical or workable or that the services could be installed or maintained. The drawings did not show detailed sections at important areas, such as corridor intersections, electrical cupboards or service risers. They did not show final conduit routes to equipment or accessory positions. Moreover, there were numerous clashes, on and/or between those co-ordination drawings and they gave rise to numerous queries. As a result:
54.2.1 Taylor Woodrow and/or Taymech were delayed and disrupted in producing installation drawings and/or in carrying out the mechanical and electrical works both because of the need to engage additional drawing office resources and because of the tardy and piecemeal fashion in which usable installation drawings could be produced and then approved by Austen Associates;
54.2.2 Taylor Woodrow and/or Taymech were unable to produce installation drawings and order materials so as to comply with programme TWC/B364/B/P01/C;
54.2.3 It was not possible to carry out first fix mechanical and electrical works before the erection of internal blockwork walls (thus rendering it more difficult to carry out those works and requiring the production of builders work drawings by Taylor Woodrow and/or Taymech, which in turn required a diversion of and/or increase in resources); and
54.2.4 Taylor Woodrow lacked builders work information so as to enable it to produce builders work drawings so that appropriate holes could be left in slabs and/or internal blockwork walls."
The case against PMI and WGI is pleaded in paragraphs 62-64 of the RASC. In paragraph 17 of the RASC RBH set out the contractual provisions relied on. They are to be found in the annexe to this judgment.
"2. The Consulting Engineers have on their permanent staff suitably qualified employees capable of undertaking the specific levels of work expected during all stages of the Project.
a) All design and production drawings and specifications (as defined in DHSS Health Notices HN(67)7 and HN(78)6) are to be completed prior to tendering for the main contract.
b) Design work for mechanical and electrical services as well as for structural work should be carried out by relevant members of the Design Team and accordingly it is unlikely that any sub-contractors will be involved in any basis, or scheme design work; (should nominated sub-contractors be used the Employer intends that they would only perform a supply and installation service as opposed to design, supply and installation)."
HN(78)6 provided in the Supplementary Annexure:
1.1 The Consulting Engineer shall, if so requested by the Client, undertake responsibility for Co-ordination of Engineering Services designed by the Consulting Engineer and for the provision of Builders Work Information associated therewith.
(a) collaborate fully with other professional advisers appointed by the Client;
(b) collaborate with the appointed Architect, in the particular case of disposition of user outlets and environmental terminals, in accordance with procedures agreed by the Client provided that such procedures be neither more complex nor more comprehensive than those defined in Appendix B hereto;
(c) prepare Co-ordination Drawings and such other documentation as may be required in the opinion of the Consulting Engineer to fulfil his design responsibility;
(d) provide the Builders Work Information necessary in the opinion of the Consulting Engineer to enable detailed structural provision to be made by others for the engineering services designed by the Consulting Engineer."
Later it said also:
"7. Information to be Supplied to the Consulting Engineer
(I return to consider the meaning of these provisions.)
Clause 5.4 of the JCT conditions
"As and when from time to time may be necessary the Architect/Supervising Officer without charge to the Contractor shall provide him with 2 copies of such further drawings or details as are reasonably necessary either to explain and amplify the Contract Drawings or to enable the Contractor to carry out and complete the Works in accordance with the Conditions."
Earlier in these proceedings His Honour Judge Hicks QC considered this provision when in December 1999 he was asked to answer the following issue
"2(vi) subject to any defence relied on by AA arising out of the conduct of the parties, were AA obliged to provide co-ordination and builders' work information so as to ensure that the [claimant] complied with clause 5.4 of the main contract?
Or are AA's contentions at paragraph 39K(a) to (c) of AA's Amended Defence correct?
Judge Hicks gave an affirmative answer to the first sentence of the issue, subject to certain qualifications, clarifications and explanations, and a negative answer to the second sentence (see paragraph 39 of his judgment [2000] BLR 75 at page 80). In paragraph 27 of the judgment he said:
"The purpose for which the co-ordination drawings were required was to enable the contractor to carry out the M&E works in accordance with his contract, and in particular to prepare his installation drawings, and the temporal requirements on AA must serve that purpose. AA was therefore obliged to use reasonable skill, care and diligence to ensure that the co-ordination drawings were provided in time to enable the contractor to prepare installation drawings and thus to carry out and complete the works in accordance with the contract programme; indeed, as recorded in paragraph 11 above, my understanding was that Mr Bartlett eventually accepted that that was so. "
The arguments before me overlapped those presented to Judge Hicks but essentially concerned what might be meant by "on time" and whether RBH was liable to TW for non-compliance with clause 5.4 and what that might mean. Mr Bartlett for AA submitted that there was reason for the apparent contrast between the opening words of clause 5.4 concerning timing ("as and when from time to time may be necessary") and the subsequent words concerning the nature of the information ("such further drawings or details as are reasonably necessary"). He contended that the test of necessity regarding timing was not qualified by "reasonably" and that this showed that under this clause the Employer was only obliged to provide the information at the latest possible time and that the contractor was not entitled to insist on having the information any earlier than was strictly necessary. He maintained that what was "necessary" and "from time to time" depended upon the contractor's actual state of progress. If the contractor had not reached the position where it was ready to make use of the information, it was not at that time necessary to what it was doing. This submission seems to me both to encapsulate one of the divisions between the parties and not to recognise reality. For example, the reason why "as and when from time to time may be necessary" is not qualified by "reasonably" is not so that the test of necessity should be stricter than that required by "such further drawings or details as are reasonably necessary" but because of the need for certainty. The latitude given by the later words is inappropriate.
"25.4.6. the Contractor not having received in due time necessary instructions, drawings, details or levels from the Architect/Supervising Officer for which he specifically applied in writing provided that such application was made on a date which having regard to the Completion Date was neither unreasonably distant from nor unreasonably close to the date on which it was necessary for him to receive the same;"
Clause 26 entitles the contractor to recover loss and expense in the event of:
"26.2.1. the Contractor not having received in due time necessary instructions, drawings, details or levels from the Architect/Supervising Officer for which he specifically applied in writing provided that such application was made on a date which having regard to the Completion Date was either unreasonably distant from nor unreasonably close to the date on which it was necessary for him to receive the same."
Both provisions thus make entitlement dependent on a specific written application having been given for the information which arrived late. In addition both provisions require the contractor to give a notice (clause 25.1) or to make an application (clause 26.1) before the Architect is obliged to consider whether to grant an extension of time or to form an opinion about whether the contractor was to be able to recover any loss expense that might have been incurred. (I deal later with the relationship between clause 5.4 and these provisions.)
"5.3.1. So soon as possible after the execution of this Contract:
..
.1 .2 "the Contractor without charge to the Employer shall provide the Architect/Supervising Officer (unless he shall have been previously so provided) with 2 copies of his master programme for the execution of the Works ".
Clause 1/22C of the Specification said:
"MASTER PROGRAMME within fourteen days of acceptance of tender or as a result of a decision by the Architect under Clause 25.3.1 or 33.1.3 of the Conditions of Contract the Contractor shall provide for and in a form approved by the Architect a fully detailed master programme of the whole of the Works including a network analysis substantiating the programme contents. The programme shall comprehensively cover all aspects of and matters relating to the execution of the Works including indicating dates or periods for the issue of instructions or information necessary for the execution of the Works ."
The programme shall comprehensively cover all aspects of and matters relating to the execution of the Works "
Clause B1:03:08 of the M&E Specification provided for the programming of the production of installation drawings:
"The Contractor shall submit installation drawings of the whole of the works to the Engineer for consideration at a reasonable time before work is commenced.
A program for the production of this information shall be submitted at the pre-Contract meeting and dates agreed with the engineer.
Give due consideration to detailed co-ordination drawings where provided with the specification. No deviation from the positions indicated on the Engineer".
Clause B1:03 18 (Co-ordination of Working Drawings) also contained the following:
"The Contractor must produce all necessary working drawings for Architect/Engineers approval and shall allow 10 working days from submission the drawings for approval. All drawings must be produced in sufficient time to comply with all agreed programmes. Working drawings shall be similarly submitted for all purpose manufactured plant and materials."
Thus Mr Williamson contended that the obligation under clause 5.4 to supply information "as and when from time to time may be necessary " meant "as and when from time to time may be necessary in all the circumstances" and such circumstances included the extent to which the contractor has performed his own programming and information request obligations; the dates by which information needs to be supplied to enable the programme to be achieved; the contractor's state of preparation "on the ground"; the contractor's actual progress. Mr Williamson also made the point (reinforced by the specifications) that even under 5.4 standing alone, a contractor is not expected to sit back and wait for information (and then to make a claim if the information is not forthcoming). In Mr Williamson's language: "In the real world, the process of obtaining and supplying information is an interactive and iterative one. The Contractor will be in the best position to know what information he needs, and, generally, will not be shy to ask for it." Similar arguments were advanced on behalf of AA see later.
"Nothing contained in the Contract Bills shall override or modify the application or interpretation of that which is contained in the Articles of Agreement, the Conditions or the Appendix."
A standard form is supposed to be just that. It loses its value if those using it or, at tender stage those intending to use it, have to look outside it for deviations from the standard. On the other hand, it causes problems since the Contract Bills (being based on the Contract Drawings) are the appropriate place to set out specific requirements for the project. Clause 2.2.1 gives effect to that approach in part by requiring the contractor to "carry out and complete the Works shown upon the Contract Drawings and described by or referred to in the Contract Bills ", but it does not of course meet the difficulty that the Bills are in reality much more representative of the parties' intentions than the standard form JCT conditions. . The conventional way out of some of the problems is to read "the Works" widely as encompassing not just the work called for by the Drawings and Bills but the means of doing so which would in this instance include the provision of programmes. Thus clause 5.4 would have to be read together with such provisions. Since "necessary" and "reasonably necessary" are not defined and, indeed, should not be defined in the abstract without reference to their contractual context, it is my view clear that the provisions of the Bills are directly and intended to be relevant to the time when it would be necessary for information to be provided to TW by WGI or by other consultants via, notionally perhaps, WGI. I therefore accept Mr Williamson's submission that these provisions of the Bills supplement the Conditions, as suggested in Keating on Building Contracts, 7th Ed., paragraph 18-44 (see also Moody v Ellis (1983) 26 BLR 39). It is therefore permissible to look at them, but the meanings to be given in practice to the words "necessary" and "reasonably necessary" have to take account of the implementation of the provisions of the Bills and the M&E Specification. Similarly the potential difference between the opening of clause 5.3.1.2 ("so soon as is possible") and clause 1/22C of the Bills ("within fourteen days") should be reconciled by using the Bills to define what is otherwise undefined.
"... in any contract, whatever its nature, it is a general rule that, if the thing agreed to be done cannot effectually be done unless both parties concur in it, the proper construction of the contract requires the implication of a term that each agrees to do all that is necessary to be done on his part for the carrying out of that thing"
Mr Bartlett observed that the principle had been applied to the JCT conditions as it had been held that close co-operation was required between employer and contractor: London Borough of Merton v Stanley Hugh Leach Ltd (1985) 32 BLR 51 at 80-81 per Vinelott J. The obligation in clause 5.4 should be one which the employer could reasonably fulfil. Mr Bartlett referred to Neodox Ltd v Borough of Swinton and Pendlebury (1958) 5 BLR 34 at page 42 where, in relation to an implied term, Diplock J stated that the time for provision of information did not depend solely upon the convenience and financial interests of the contractor, but also upon the point of view of the architect, his staff, and the employer. Those observations deal with requests that are either premature or made late and cause inconvenience. Mr Bartlett accepted that the contract with TW sought to avoid the familiar problem of a contractor asking for information earlier than it was reasonably required in order to prepare the ground for a future claim (also noted in the report of AA's expert, Mr Miers). However it tends to be forgotten that such requests are quite often prudent in order to make the person providing the information aware of the need for it and, in any event, the mere making of the request may establish little. What has to be established is the date when the information was actually needed, its absence on that date and the consequences of its absence in terms of time or money (probably both). The Court of Appeal rejected AA's earlier case. Aldous LJ said:
"79. Mr Bartlett placed the blame upon Brompton for the way that the judge dealt with the timing claim independently from the quality claim. He went on to submit that the findings of fact were conclusive on the issue. I do not agree. I believe that Mr Edwards-Stuart is correct in his submission that clause 5.4 is a term which must be construed as imposing an obligation to provide the drawings when necessary in the sense that the drawings must be provided when actually necessary as opposed to when they were perceived to be necessary. No doubt in most cases the perceived need of a contractor will coincide with actual need, but this may not be such a case. ..."
"26.6 Reservation of rights and remedies of Contractor
The provisions of clause 26 are without prejudice to any other rights and remedies which the Contractor may possess."
In my judgment that means that, whatever the rights the Contractor may (or may not) have under clause 26, if any of the circumstances described in clause 26 as entitling the Contractor to apply for the reimbursement of loss and expense occasioned by it is also a breach of contract by the Employer then it remains actionable by the Contractor. That was the view of Vinelott J in London Borough of Merton v Leach (see 32 BLR 51 at page 108) in relation to the comparable provisions of the 1963 edition of the JCT form and, so far as I am aware, it has stood unchallenged. It has been accepted as correct by the leading commentators (see Hudson, 11th ed. at paragraph 8-070 and Keating 7th ed. at paragraphs 18-82, 18-318, 18-341) and it has been followed (see Fairclough v Vale of Bevoir Superstore (1990) 56 BLR 75). Mr Williamson did not argue to the contrary. I therefore accept the submissions of Mr Edwards-Stuart and reject those for AA.
"a principle well established at common law, that no one can take advantage of the non-fulfilment of a condition, the performance of which has been hindered by himself and also that he cannot sue for a breach of contract occasioned by his own breach of contract, so that any damages he would otherwise have been entitled to for the breach of contract to him would immediately be recoverable back as damages arising from his own breach of contract."
Background to M&E Drawings Issues
"Issue 2(e): Paragraph 19A (a), (b) and (c) of AA's Defence: Were the Board and/or PMI under any pleaded duty to comply with the provisions of Capricode?
"17. With reference to paragraph 19A of AA's Amended Defence, it is agreed between Brompton and AA that the correct position is as follows:
(a) As between the Board and the DHSS, the project was required to be conducted in accordance with the provisions of Capricode, as in force from time to time, save as otherwise specially agreed between the DHSS and the Board.
(b) As between AA and the Board, the Board could not agree a departure from the provisions of Capricode which conflicted with the terms of AA's retainer.
(c) The fact that at the time of AA's retainer the Board was required to comply with the provisions of Capricode (in the form then in force) was part of the factual matrix against which the duties and rights of the Board and AA should be construed.
(d) AA's duties under their retainer were formulated with express reference to Capricode's stages.
(e) Any failure by the Board to comply with the guidance in Capricode might excuse late production of drawings or other information by AA. Whether any such failure did give rise to such excuse would depend upon the particular circumstances.
(f) Breach by the Board of the provisions of Capricode would not, of itself, necessarily amount to a breach of contract by the Board as regards AA. Whether a breach of the provisions of Capricode would result in a breach of some obligation owed by the Board to AA would depend upon the particular circumstances.
(It is further agreed that the last sentence of paragraph 19C(d) shall be revised to read: "What was a reasonable time falls to be determined by reference (amongst other things) to the terms of AA's appointment and the provisions of Capricode").
"It is essential that the design is frozen as at the 1st November 1985 and a total design freeze following the display of the final presentation."
However PMI allowed RBH some latitude:
"All changes after this date may be proposed and these will be reviewed. Decisions will be taken on whether items may be incorporated prior to commencement of the contract or on practical completion. The Project Manager will have the responsibility to discuss the changes with the design team and report to the Project Co-ordinator with the effect on cost and programme and with recommendations on how the change should be actioned."
There can be no doubt that the evolution of the project in this way required consultants to work inefficiently, although since few, if any, major hospital projects at that time ran entirely smoothly it does not follow that the consultants had not anticipated such problems and had not taken them into account in arriving at their fees or internal budgets. Of immediate consequence was the effect on the performance by the consultants of their duties. Again there can be no doubt that such circumstances should be considered in deciding whether a consultant exercised reasonable skill and care in producing a drawing or other information on time It is common sense. Counsel for AA submitted that consultants do not then have a duty to apply unlimited resources to a job so as to do everything as quickly and effectively as the client would like. I basically agree, although the qualification should be: as quickly and effectively as required by the contract of engagement.
"1. The Authority is satisfied that this scheme has been prepared in accordance with Capricode procedures and that all reasonable steps have been taken to ensure that once a contract is let the scheme should be able to proceed to completion without delay. In particular the Authority is satisfied that the Design Brief was frozen at the appropriate stage and will not be altered during the course of the contract other than in exceptional circumstances, the scheme has been designed within budget, and there are no causes of delay currently foreseeable.
Some understanding may have been reached with the DHSS. On the evidence available it appears to have known what was happening or not happening. It was obviously made aware of the budget overrun. If however the DHSS was not kept in the picture some of these statements would have been wrong or conveyed a misleading impression. The Capricode procedures had been departed from, in part; the design had not been frozen before the start of detailed design and the co-ordination drawings were now to be issued after tender; the project was not fixed so in terms of time and cost there could still be overruns; the architectural drawings could not be completed until RBH's requirements had been finalised; in turn there was and could be no programme for the supply of production material not available at tender stage (such as the co-ordination drawings); the capital resources were not adequate as the cost was estimated by NNN to be about £16,563,957 and thus greater than the latest DHSS budget of £15,027,000 (unless it were revised). In the event at a meeting of 4 September 1986 approval was given to RBH to proceed with some misgivings being recorded and subject to the familiar caveat: "without prejudice to any action which the Department might consider necessary in the event of an excess tender". However, if it were relevant, I would have accepted AA's submission that the RBH did not meet its obligations towards AA as set in clause 7 of the Supplementary Annexure as it did not freeze its brief; it did not work within its budget; and it decided to go out to tender without co-ordination information and on Bills that were out of date because of further changes. Nonetheless whilst none of the consultants was happy with the situation and both PMI and AA pointed out the obvious to RBH (which was well aware of what it was doing), none in fact protested and accepted pragmatically the decision to go to tender without the co-ordination drawings.
Advice Claim
"1. The answers to the preliminary issues listed for trial on 1 November 1999 are as follows (those marked "*" are by consent of the interested parties, namely the claimant, PMI and WGI for Issue 1, .):
Issue 1(a):* Were PMI and/or WGI obliged to act as design team leader?
Issue 1(b):* Did the Project Procedures Document qualify the terms of PMI's retainer as alleged in paragraph 18 of PMI's Defence?
Issue 1(c):* Did the Project Procedures Document circumscribe and/or define the duties of WGI as alleged in paragraph 10 of WGI's Defence?
Issue 1(d):* Was WGI under the duty alleged in paragraph 50 of the Statement of Claim?
Issue 1(e):* Was PMI under the duty alleged in paragraph 51 of the Statement of Claim?
(b) PMI was under a duty to oversee WGI's administration of the Main Contract pursuant to clause 11(k) of its retainer.
Thus the answers in paragraphs 3 and 4 are to the effect that the Project Procedures Document did not qualify or limit the duties of WGI and PMI, but it provided some further definition of their roles and responsibilities. WGI's retainer included the following:
I. INTRODUCTION
- The provision of advice on organisational issues, and planning procedures to manage the project
[ ]
- The development, and implementation of appropriate procedures to be followed throughout the design/build/ commissioning stages by the Board, its officers, and the Project Team.
** [Footnote] The Board will consider that the Architect has take all possible steps if he can show to the Board's satisfaction that he has taken practical action to attempt to get the members of the Design Team to fulfil their obligations and to contribute information requested of them. This information may be related to the overall time and cost control system or to other systems and procedures as in operation at the time.
II. THE PROJECT ORGANISATION
III. GENERAL CONDITIONS
- Quantity Surveyor
- Structural Engineer
- Services Engineer (Mechanical and Electrical)
However, individual consultants shall be entirely responsible for the detailed design, supervision and for their own performance of the work entrusted to them.
V. ARCHITECTS' PROGRAMME
Design Programme
The footnote 1 to clause 5.261 provided, inter alia, that: "In the Terms of Reference the expression "production drawings" has been used to indicate the standard and detail of drawings as applied and used by the Architectural profession. In order to relate this term to other official documentation including that used by the professional bodies of the other members of the Design Team, this footnote has been written. Production drawings for the work of the M &E Engineer in the context of this project shall be deemed to be equivalent to the term "working drawings" as used in the Annexure to ACE Model Term of Agreement D with the proviso that as an additional duty these working drawings shall provide a level of detail that work could be built or installed using these drawings."
"Clause 11 (e): "Monitor and co-ordinate the design stages to ensure achievement of the dates set for the commencement of construction."
Clause 11 (f): "Oversee the preparation of design programmes for all elements of the project within the master programme."
Clause 11 (l): "Oversee the design team's administration of construction and building contracts "
Clause 11 (m): "Attend design and site meetings as necessary to co-ordinate the flow of production information to the contractor."
"1. PURPOSE OF THE DOCUMENT
Project Manager
Design Co-ordination and Integration
Construction
Architect
Design Co-ordination and Integration
Site Meetings
[ ] Chaired by: Architect
Design Review Meeting
[ ] Chaired by: Project Manager
Master Programme
Construction Progress
The Contractor will submit short term detailed programmes at 8 week intervals in accordance with the General Conditions of Contract. The Project Manager will advise on the acceptability of these programmes, monitor progress and report delays to the Architect.
.
Information Requirements
Recording and Monitoring
It is clear that therefore from PMI's retainer and the Project Procedures Document that the leader of the team was to be PMI and not WGI which was displaced from the traditional role of the architect. WGI had now to communicate with PMI (the "Management Advisers" in WGI's contract), when it had expected to deal only with RBH's resident project management or some general consultant. PMI was however more than a mere client's representative; it was an informed or intelligent representative (as indeed was RBH itself) so WGI was in my view entitled to expect that it did not have to tell PMI, as WGI's virtual client, what was expected of it as a client or as a client's representative for this major and sophisticated project. PMI referred to some observations of Goddard LJ, in relation to solicitors, in Yager v Fishman [1944] 1 AER 552 at 557:
"The nature and amount of advice which, in a matter of this sort, a solicitor would be expected to give to a person wholly unacquainted with business may differ very materially from what he would offer to an experienced business man, who would naturally decide for himself the course he thought it in his interest to take."
"The precise scope of that duty will depend inter alia upon the extent to which the client appears to need advice. An inexperienced client will need and be entitled to expect a solicitor to take a much broader view of the scope of his retainer and his duties than will be the case with an experienced client."
If expert evidence were here required (which it is not for the reasons that I have given) Mr Coleman gave a series of answers to Mr Taverner which in my view accurately described the contractual and working relationship between PMI and WGI and other consultants:
Q: My suggestion at this stage is that, in terms of them being the intelligent or informed client, looking at it from below and the design team below, they are entitled to proceed, when performing their own engagement and their own functions?
A. Yes.
Q. That PMI are knowledgeable about the programming of a hospital project such as this?
A. Yes.
Q. They are also entitled to proceed on the assumption that PMI know about co-ordinating the efforts -- they are knowledgeable and experienced in co-ordinating the efforts of all of the participants in the project to be able to fulfil that function of bringing home, or aim, of bringing home the project on time and under budget?
A. Of co-ordinating the activities of the various parties, yes.
Q. Indeed. Thank you. But what PMI are not are designers; would you agree with that?
A. Definitely not.
Q. They do not take responsibility for the efficiency or the practicability or the fitness for purpose of the design?
A. No.
Q. And it is also not PMI's job, is it, to co-ordinate in the sense of fitting together the pieces of the design?
A. No, that is the project -- that is the role of the architect.
Q. The fixing of the pieces, the bringing together of the design so that it can be construed in that qualitative sense --
A. Yes.
Q. -- is the responsibility of the architect?
A. Yes.
Q. And the architect's responsibility is to involve himself in what I think others call this iterative process, if one is concentrating one's mind on the engineering and architectural, mechanical and electrical aspects and the architectural aspects of the design?
A. Yes.
Q. And WGI are entitled to assume that the pieces of the jigsaw which are provided to them by CNM, in general terms, or by AA themselves, fulfil their function?
A. Yes. I believe all consultants should rely on advice from other consultants. That is the only way it works in practice.
Q. Notwithstanding that PMI have the ability within the regime set up to be able to direct the design team?
A. Yes."
Mr Coleman said also, later, that: "it would not be efficient and proper project management for the same function to be being done by two parties" and he would not expect WGI to fight with PMI as to who should be producing the programme. Happily this statement of practice or recital of relevant factors (or reading of the contractual documents) was reflected in Mr Hutchings' own approach. Although WGI started by preparing programmes it ceded responsibility to PMI so that whatever its contract might have required it now reasonably expected PMI to look after programming the issue of design information to TW. WGI would be concerned to see that it happened properly because any failure could result in delay. WGI remained responsible for the integration of the designs of the consultants (see cause 3.11 of its contract conditions) and for the co-ordination of such information (see clause 3.7 of the Project Procedures) and to that extent only was concerned with the timely flow of information to TW. I now return to the facts.
"1.0 Tender Negotiations T.T. reported that pricing of the Bill of Reductions would now be completed by Wednesday 4 February 1987. The pricing of the building sections was practically complete but following issue of the final information for services last Wednesday additional time was necessary. T.T. raised the question of other possible savings that had been put forward by them but not proceeded with. The Design Team had looked into all these and established that savings were not possible. .. 2. Contract Documents NNN would require 3 weeks to provide a set of Contract Documents from conclusion of the Bill of Reduction negotiations. Following this it would be NNN's intention to provide a working document summarising the B of Q, Addendum B of Q and the Reductions B of Q. It was agreed that March 2 1987 would be the start date for the Contract. T.T. would make arrangements with PMI to visit site next week. Entry to area allocated for site offices and car parking can be cleared for 9 February 1987. |
T.T. P.M.I. |
3. Joint Venture Agreement This would be based on the separate company requirement as proposed by T.T. P.M.I. to confirm. |
P.M.I. |
4. Programme of Work T.T. issued provisional Programme anticipating only minor amendments to this document. T.T. would discuss entry onto site next week and would expect to have accommodation available for the Resident Engineer 3 weeks after start date. |
|
NNN called attention to Programme Items 60 63 and related this to the 12 week plant commissioner requirements. |
|
T.T. saw no problems and confirmed that detailed commissioning programmes would be issued based on contract requirements. |
|
5.0 Information T.W. issued a preliminary issue of information schedule. Dates had been omitted from a number of items to allow discussions with W.G.I. W.G.I. would consider the list and make arrangements for meeting. |
W.G.I. |
C.N.M. issued 5 no. copies of drawings and bending schedules for southern half of Level 1 slab. Remaining Level 1 slab perimeter retaining walls, manholes etc, would be issued 13 February 1987. Level 2 slab and reinforcement would be available 20 March 1987. Agreement to be reached on issue of remaining reinforcement. |
|
C.N.M. issued the following schedule of information required by C.N.M. some of which was urgent. |
|
a. Sheet piling temporary works proposals with calculation and drawings. | |
b. Crane base proposals by T.T. | T.T. urgent |
c. Pump Mix and RMC information. | |
d. Reinforcement supplier, source, mill test certificates. Backup supplier. | |
e. C.N.M. noted that pull out bars cannot be used in all cases. | |
f. Details of holes through slabs for cranes precise dimensions. | T.T. urgent |
g. Mould suppliers trough formers. | |
h. Structural steel fabricator. | |
Stock steel C.N.M. to issue to P.M.I. proposed stock steel in form of Bending Schedule. | C.N.M. |
|
Issue Required By |
|
1. 1:100 general arrangements, sections and elevations. | 16 February 1987 | |
2. 1:2- general arrangements, elevations and details showing brickwork and blockwork layouts and details. | 9 November 1987 | |
3. Schedule of finishes. | 4 January 1988 | |
4. Roof asphalt details. | 29 February 1988 | |
5. External works details. | 23 May 1988 | |
6. Details of oxygen and refuse compounds. | 9 January 1988 | |
7. General arrangements, section and elevation. | 16 February 1987 | |
8. Reinforcement details and bending schedules for foundation and level 1 slab. | 16 February 1987 | |
9. Details of lightning pits. | 16 February 1987 | |
10. Reinforcement details and bending schedules for reinforced concrete frame. | 13 April 1987 |
|
11. Structural steel frame layout to plant room. | 9 November 1987 |
|
12. Structural steel layout to level 5 windows. | 30 November 1987 |
|
13. Underpinning details. | 28 November 1988 |
|
14. Structural steel layout to oxygen and refuse compounds. | 9 January 1989 |
|
15. Details of underground drainage. | 16 April 1987 |
|
16. Layout of incoming services. | 16 February 1987 |
|
17. Details of ductwork to level 1. | 20 July 1987 |
|
18. Setting out drawing and site investigation report. | ||
19. Details of any service diversions. 20. Details of demolition. |
||
21. L.A. planning permission details including working hours and site access. | ||
22. Concrete specification. |
||
23. Drawings and details of underslab drainage and services including sumps, pumping chambers, lightning conductor earthing points, petrol interceptors, manholes. |
||
24. Details of services connection routes and Instructions to place with Statutory Authorities. |
||
25. R.C. drawings and bending schedules for level 1 slab including machine and plant bases plinths, wall and column starters. |
||
26. Level 1 details: Builders work, lifts, MEPD, services, floor finishes, manhole and duct covers expansion joints, drainage channels, waterproofing. |
||
27. R.C. details and bending schedules for walls, columns, liftshafts and staircases level 1 to 2 including:- | ||
Builders work details, recesses and fixings required by lift sub-contractor. | ||
Drawings and fixing details of primary, secondary and tertiary steelwork including access and cat ladders, details of wall and column finishes. |
||
28. Plant installation details including access requirements. |
||
29. Schedule of M & E plant including loadings. |
||
30. R.C. details and bending schedules for level 2 slab including Builders work, floor finishes, cast in services, fixings, conduits etc, brickwork support and fixings. . |
||
54. Reflected ceiling plans. . |
||
60. Details of architectural metalwork and balustrading. | ||
61. Details of fire protection and fire stopping.
65 Mechanical, electrical , plumbing and specialist services drawings details and specification |
"Further to the issue of the schedule of information requirements, based on the preliminary programme TWC/86/176/001 revision A, issued by Taylor Woodrow, we have the following comments:-
Items 1 8 | Architectural/Structural issue. |
Item 9 | The position and details of earthing/lightning pits are shown on our tender drawings and detailed within our specification, but are subject to co-ordination with the revised structural drawings. |
Items 10 14 | Structural issue. |
Item 15 | Subject to final alteration to co-ordinate with structure as discussed, will be issued prior to date required 16 April 1987. |
Item 16 | Following alterations to plant areas at Level One, the final position of incoming services had to be renegotiated with the Supply Authorities. This process is still continuing and we shall pursue this with all power. |
Item 17 | We presume that this refers to structural floor ducts which have been agreed with Clarke Nicholls and Marcel and co-ordinated with Genever and Partners. But we are now awaiting final drawings from the Structural Engineers. |
Item 18 | Architectural item. |
Item 19 | There are no service diversions necessary. |
Items 20 and 21 | Architectural/Structural items. |
Item 23 | See comments on Item 15. |
Item 24 | See comments on Item 16. |
Item 25 27 | Structural items. |
Items 28 & 29 | All plant information is complete other than that altered by the Level One alterations and the pathology changes which still await Client approval. But the information shall be issued to meet any reasonable date set by the Contractor. |
Items 30 53 | Architectural/Structural items. |
Item 54 | Revised Level Two, Zone 6, plan awaited and co-ordination between Austin Associates and Watkins Gray International necessary. |
Item 55 | Mechanical and Electrical Contractor's responsibility. |
Items 56 64 | Architectural/Structural items. |
Items 65 | As previously discussed/or are ready for issue with the exception of the co-ordination drawings. |
Item 66 | Architectural item. |
Thus AA said that in respect of the balance of the M&E information (i.e. the rest of AA's drawings) the position was "As previously discussed/or are ready for issue with the exception of the co-ordination drawings". However, at that stage AA was in fact still altering its single service drawings upon which little or no work had been done for six months. Some also required alteration to deal with the savings and other changes required by RBH, so that many were not ready for issue, as Mr Tyler agreed. Indeed they were not issued until much later: those for level 1 although dated March were not issued until about 3 April; and the drainage drawings for level 2 and above about 16 April. Accordingly, as Mr Tyler accepted, the drawings needed several weeks' work before they could be completed and issued. Single service drawings for zones where significant alteration was not anticipated still had to be checked. Nevertheless AA instilled confidence in TW since Mr Robert Edwards had a meeting with TW on 13 February 1987 at which
"Taymech were shown a fair selection of the drawings for the site including detailed plant rooms, some single services drawings and a few co-ordination drawings for the Project. I can recall Mr Palmer [from TW] commenting on the good quality and detail shown on the drawings although I cannot now recall whether these comments specifically related to the sample co-ordination drawings. I am certain that AA did not receive any adverse comments about these drawings at the meeting. The quality and detail in these co-ordination drawings were the same quality and detail that AA had provided on previous Hospital projects on which I had worked. The co-ordination drawings shown to them were drawn in pencil rather than ink, and were only intended to be samples to allow Taymech to anticipate the type of drawings they would be receiving when they were ready and the various changes had been resolved. However, the quality and detail given in these example co-ordination drawings were the same as those provided to Taymech later during the year and they could have used them had they so chosen and if the design had remained static."
Mr Dix said in his report and confirmed in court that, depending on the manpower, rates paid and other factors affecting the effort that AA might make, 5-7 weeks would be the likely time needed for the co-ordination drawings for Level 1 (once the single service drawings for that level were drawn). The experts, Mr Dix and Dr Arnold, agreed that there was no identifiable reason "why AA could not have completed, in all practical terms, their co-ordination drawings prior to the end of May 1987." Mr Edwards wished to reserve his position until other changes had been discussed. However the effect of Mr McKenzie's agreements and his cross-examination by Mr Edwards-Stuart is that Mr Edwards' reservation does not warrant consideration. In my view Mr Dix's assessments in his report were based on the correct assumptions and thus were reasonable and to be accepted for, although they differed in part from those made by Mr Down, they were all justified by Mr Dix. I conclude that on 10 February 1987 a large number of drawings were not ready to be issued for various reasons, in particular that they had not been worked on for about six months during which there had been changes. The answer given by AA against item 65 was therefore inaccurate, or misleading.
"I have asked John Wragg to prepare a statement showing the action and results of our negotiations with Taylor Woodrow/Taymech, which were finalised on the 13 February.
Unfortunately we have been unable to reduce the tender amount by £754,000 and have finished with a £60,000 shortfall.
One of the problems in making proposals and negotiating savings with a single tenderer is that other factors come into play and a tenderer who presumably knows that we have no alternative tender, is less inclined to make generous gestures.
The Architect and myself met Taylor Woodrow Directors Frondigoun and Knight last Friday in an attempt to close the deficit. We have to report that Taylor Woodrow have contributed objectively to the savings exercise. They have stated that they wanted to build this project, they wanted the turnover, they had the right team available and they had the benefit of an in-house team bid. They had made a calculated attempt to land the project at minimal profit.
I do not recommend that we seek any further gestures from Taylor Woodrow and I hope that other funds may be made available to meet the shortfall.
If we proceed immediately as I have provisionally arranged with a formal commencement date on the 2 March, then we will have to ensure that all information is available to them in good time and that no changes are made during the construction period. We are satisfied that full information on architectural and structural aspects is available and Brian Teale visited Austins [sic] on Friday and has reported that they have the bulk of design information ready for issue"
Mr Robert Edwards said that bulk meant "if we take co-ordination out of it". However RBH was not told that the co-ordination drawings had been excluded, even if they were not required for some time. Accordingly RBH was misinformed, as Mr Robert Edwards said that it was.
"We are pleased to confirm on behalf of our Clients, the Chairman and Governors of the National Hearts & Chest Hospital that instructions have been given to proceed with Phase I.
Taylor Woodrow/Taymech are to be instructed to proceed with the construction in the sum of £17,967,623 with a contract commencement date of the 2 March 1987. This instruction was given following agreement with the DHSS to reduce the contingency and dayworks allowance by £30,000 and to reduce the provisional sums by a total figure of £30,000.
We have assured our Clients that the information required to construct the facility is available and that there is no reason that the Contractor shall be able to claim delay due to late release of information. Our Clients furthermore have agreed that no instructions to change the building will be made prior to practical completion, unless such changes are of a relatively minor nature and can be accommodated by the Contractor without delay."
"8.3.5 RBH/PMI thus placed the construction contract for the new hospital before all construction information was sufficiently complete and available in final form. Considerable design work was still in hand, and still more needed, much more than was sensible and prudent for the administration of a fixed price, lump sum, JCT80 contract. Substantial claims for disruption and delay were almost bound to follow."
"Further, I took the view that if no more changes were made and a tight control over the contractor was taken by PMI and the Supervising Officer then there was a chance that the scheme could be completed in the manner required."
He certainly thought that the risk being run was not "minimal".
From February 1987
4.1.3 It was the view of all present that under the terms of the contract TWC were not entitled to receive co-ordinated drawings but that they had been advised, both before tender and after award of the contract, that they would be provided by way of further information.
AA stated that in their view, having been advised that co-ordinated drawings were to be issued, it was reasonable for TWC to await their receipt before commencing their own drawing programme."
In addition there was agreement between the experts (Mr Dix, Mr Stephen Edwards and Dr Arnold):
"a reasonably competent consulting engineer could anticipate commencing co-ordination drawings for level 1 first and would not need a contractor's programme to know this on a project such as this"
Thus co-ordination information could and should have been issued within three or four months, and thus, once the contract with TW was made, RBH would be obliged under clause 5.4 to provide TW with that information within that time, unless and until TW presented a programme which showed a longer period or periods. A specific application was not needed since the necessity and the time were clear. Thus the drawings were due from early May 1987, and, technically, even earlier in the case of level 1 which ought only to have taken six to seven weeks to issue.
"DESIGN REVIEW MEETINGS
"We discussed the reinstating of the above meetings on site and would like to confirm the suggestion we made that the first meeting will be held in the Project Office Conference Room on April 14th 1987 at 2.00 p.m.
"The purpose of the meeting will be as follows:
"a) To review and ensure that production information is being released in accordance with the Contractors requirements.
"b) To resolve any current design problems.
"c) To resolve any outstanding queries that the Contractor may have.
"At this stage the meetings are to be monthly until further notice and will provide an opportunity for the Team to meet to review the overall situation."
That was an obviously prudent move by PMI in order to see that the consultants were producing their drawings and other information to meet TW's needs. As suggested by PMI on 6 April 1987, on 7 April WGI wrote to TW about the lack of a programme:
"(c) Master Programme.
The issue of the Master Programme was discussed at the pre-contract meeting held on 24 February and its issue was promised for 31 March.
"Despite our requests for its issue in sufficient time to allow comment to be made at the site meeting, it was eventually issued in preliminary form on that day and immediately withdrawn. Whilst no precise period is stipulated in the contract conditions for the original issue, we consider it to be in the spirit of the contract for it to have been available in proper form by 31 March. Would you please deal with this as a matter of urgency."
In addition in another letter of 7 April PMI specifically (and quite pointedly) asked AA about its drawings:
"Regrettably the prolonged period you have required to report on these items causes disruption all round and this will continue until we are in the position to obtain firm client instructions.
Last week we issued further Client Enquiry Sheets No 19-29 inclusive. Can we please request you report quickly on any M & E additions as we again would like to clear these within the next ten days, i.e. 14 April, 1987.
It would assist greatly if you would schedule the items of design co-ordination and drawings that are outstanding from you and your programme for completing. We could then discuss this at the Design Review meeting on the 14th April, 1987."
"Q. Would you not also agree with me, in terms of the big picture, as it were, as you have just been referring to it, that it made it rather difficult for the project manager or the consultants to identify an overall programme, in the absence of a master programme from the contractor and an M&E programme from the contractor?
A. I accept that is the case is [?]. However, the consultants should have been working to their own programme. What is missing is to link that programme to Taylor Woodrow's. The absence of Taylor Woodrow's does not excuse the consultants from not having their own design programme.
Mr Adams countered the suggestion that a programme that had not been agreed between TW and AA would not be worth the paper that it was written: "Other than it would be a mechanism by which the project manager could establish how these drawings were progressing in the M&E consultant's office".
"the Contractor through the Architect and ourselves, is being pressed to provide as a matter of urgency the network analysis of his planning, a detailed services programme and his needs for the working drawings of specialised subcontractors".
The minutes of the meeting record:
"Network analysis and detailed M & E programmes are now expected from the Contractor within the next 7 14 days.
Importance of early production of working drawings by specialist sub-contractors being stressed.
Report on drainage progress will be contained within next month's report.
Programme within report is a summary of the Contractor's construction programme.
PMI will produce overall programme including equipment and commissioning stages."
Later it was also noted:
"3.2.3 Variations
DHSS were concerned at the total of the list of anticipated variations with a view to setting these against the contingency sum.
(a) Client Changes
PMI explained that scheduled anticipated variations were items that had generally been raised sometime ago and information was now available on estimated costs. PMI confirmed that they had the Client's support to the 'no changes' ruling and that it was the aim to make any necessary changes in the immediate post contract period. The Design Team awaited instructions on how to proceed. DHSS stated that with this particular project there should be no changes and that in any case a change would be the subject of a separate approval. DHSS also reminded the meeting that non contingency items over £20,000 would require an application to increase the approved sum.
A schedule of proposed post contract changes should be included in the Monthly Financial Reporting."
The report also recorded that "alteration to drawings to comply with the bill of reduction amendments is proceeding satisfactorily". Mr Dix said that, at that stage had he been AA, he would have extremely worried that those drawings had not reached TW.
"H.S.D.U. information now complete.
M&E drawings issued as Construction Drawings.
H.S.D.U. drawings issued. Level 1. Boiler House drawings issued.
Level 1. Mechanical Plant Room issued.
Level 1. Electrical drawings not issued and will not be issued until 22 May 1987 (Required 6 April 1987).
Level 1. High level pipework ducting available very shortly (Required 6 April 1987)."
In my view, now that the HSDU information was complete, although there was a possible question over a riser duct and although Mr MacKenzie demurred, I consider that AA could then have got on and issued level 1, zone 4 co-ordination drawings. On 18 May 1987 Mr Wragg wrote to AA:
"The minutes of our Design Review Meeting No 2 will indicate that the issue of your information, both Mechanical and Electrical is in delay.
"In particular Level 1 electrics will now be some four weeks later than the date promised at Design Review Meeting No 1, and some seven weeks after the date when the Contractor requested information to commence being issued. There is a similar situation developing with the issue of mechanical information.
"Our letter of the 7th April 1987, did request your plan of operation and it would help if this was issued as we feel there is a great deal of co-ordinating work and reviewing of drawings to be done. It is obviously necessary to review your resourcing of the project to provide a consistent flow of information on programme.
"The Taymech requirements should be established more clearly than they are at the moment. It must be reasonable to assume that Level 2 Mechanical and Electrical drawings are now expected by them. If this is the case then a concerted effort will be needed to clear outstanding drawings, now that you have been able to clarify the situation for the Client and that Pathology can now be completed.
We would be pleased to meet and discuss the situation to ensure that there is no question of delays through lack of information."
It is therefore clear that at this late stage PMI had not got AA to produce any programme as it was still asking for it and that it thought, rightly, that AA was already late in providing its drawings. That was a strong letter (as it was put to Mr Teale) but PMI appear to have done very little (if anything) to follow up the letter that it had written six weeks earlier on 7 April or otherwise to pursue AA. Mr Edwards response was when the letter was put to him
Q .. So, Mr Edwards, it is perfectly clear in this letter to you, Mr Wragg is expressing concern that if a grip is not taken of the information flow to the contractor, delays might arise?
A. Yes, I think he is doing the good job as a project manager and chasing us all along. With regards to the electrical, I cannot say now why they were not done. I mean, you appreciate in April we issued all those drawings even those that were subject to change. I know on the electrical, two zones we had to completely redraw because of the boundary wall down there. I would probably argue that that was not going to cause the contractor a delay there, but John is doing the right job in geeing us up.
That reaction demonstrates Mr Edwards' complacency which should have led Mr Wragg to act and not merely to write. Mr Coleman thought that the situation was not properly under control and that "it had the potential to become serious". In my view Mr Coleman understated the position. Even so, on that view alone, I consider that a meeting should have been held with AA at which the "plan of operation" would be produced and PMI was again failing in its duty not to have obtained it. The letter of 18 May records the fact that a decision had by then been taken to get on with the pathology department on the basis that there would be no air-conditioning. The previous history has some memorable features (for example concerning predicted temperatures) and was at times quite complex. It is by no means clear that the decision could not have been taken earlier and if AA had been working to a proper programme I am sure that it would have assembled the information in time and sought a decision on the grounds that it was holding up the production of drawings. Accordingly I do not regard the apparent late decision as the reason why the drawings were late. The removal of air-conditioning for pathology cleared the way for RBH to authorise the redesign of the haematology department which had to be made at the insistence of a consultant who had required it in January. Evidently RBH could not resist the change even when it should have refused to make it as the design was supposedly frozen. This was an alteration which AA had to accommodate and had it been on time might have had certain consequences. As it was, AA was instructed to make the change on 26 May 1987 and AA produced the revised drawings by mid-June. I do not consider that much was involved, for the reasons given by Mr Dix.
"PROGRAMMING AND ISSUE OF INFORMATION
"Although the Project does not yet have a Contractors Master Programme, we are pleased to see the activity on site to produce this.
"Taymech's Project Manager is now in residence and with the Taylor Woodrow's Planner and Co-ordinator, also on site, we now understand that the Master Programme could be available by the next site meeting on 2nd June 1987."
By the time of that meeting TW had supplied a preliminary M&E programme to WGI and PMI - on 29 May 1987. PMI's continuing concern about AA over the previous two months surfaced with a letter of 27 May 1987 in which Mr Teale at last called for a meeting with Mr Edwards. In his witness statement Mr Teale said that he arranged it with AA, WGI and [TW] so "we could discuss the areas of responsibility with regard to the drawings.
"71. [TW] said that the drawing information provided by AA at the meeting was General Arrangement Drawings. [TW] claimed that builders work drawings could not be prepared on an accurate basis without co-ordinated services information. As [TW] began to prepare these drawings in detail, he began to complain that the AA drawings showed insufficient information.
72. There was some confusion or disagreement as to the responsibility owed by AA and [TW] over the production of co-ordination drawings. I was less interested in determining contractual responsibility than simply trying to determine what information was outstanding, who was going to produce it and by what time limit. I believe that in the circumstances this pragmatic approach was the best way forward. I would try and co-ordinate the release of information with the services installation programme.
73. The situation was still very much controllable and I saw no reason if all parties co-operated why the M&E installation date could not be maintained. I was continually monitoring the information and drawings being produced by AA and how this was being co-ordinated with [TW]'s activities. I did not want to create a "blame culture" and I believed there was little point in doing so and any problems in respect of the flow of information between AA and [TW] could best be resolved by holding regular meetings. Neither AA nor [TW] objected to attending these meetings and, in fact, I believe that they found them useful and necessary."
Yet to hold a meeting with WGI and TW effectively disabled Mr Teale from confronting AA as PMI could not have held AA to account in front of TW (or even WGI). It allowed AA to lead PMI to believe that dates had been agreed with TW. Some difficulties had arisen since WGI's agreement did not cover matters which AA thought were its responsibility. However Mr Teale said that the letter dealt with the wider issue of co-ordination of services generally. Mr Tyler saw the letter and wrote a note on it that he wanted Mr Edwards to discuss it with him before replying. In turn this led to Mr Tylers's memorandum to Mr Edwards of 4 June, the tenor of which speaks for itself:
"Re: Room Loading Information
Further to our recent discussions I have investigated further the situation with regard to provision of room loading information to the contractor. I would also comment on Brian Teale's letter to you dated 27 May, and give my further views on this overall matter.
Finally, if the Project Manager remains unsure about the architect's responsibilities, and/or Watkins Gray are still not prepared to co-operate, then I think we should suggest to the Project Manager that the matter be referred to the DHSS for their ruling. In this respect, they should refer to the final Draft of the comprehensive agreement and the Department's previous understandings of respective responsibilities of the various disciplines comprising the Design Team. They could also refer to the South West or South East Thames Regional Health Authorities Architects Department who should be willing to confirm their own previous rulings and views on this subject.
With regard to the Contractors, as previously mentioned to you, no one can expect them to provide this information as they are not in a position to carry out a location exercise without the architect's information and assistance. Nor should we air Design Team vagueness or disagreement in front of the contractor who must already be viewing the disarray and mismanagement of this project as a valuable contribution to the recovery of his losses on an alleged low tender.
I hope this information will assist you at your meeting with Brian Teale on 8 June and I would be grateful if you would let me know the outcome as soon as you can."
I have emphasised one sentence in particular. When Mr Tyler was asked about the mismanagement to which he referred he excluded TW, but not, it seems, RBH, who were to be blamed for a lack of rationalisation of the various consultancy agreements. This was odd first since they seem to me to be reasonably well put together and in any event the Project Procedures Document provided a practical solution. Secondly Mr Tyler then admitted that at that time he knew nothing of the terms of the commissions given to WGI and PMI and being reluctant to blame PMI was forced to admit that the statement was unjust. In the context of this paragraph and what TW was observing the only entity that could really be blamed was AA. Mr Edwards said that within AA memoranda were only used if there was something serious (but he could not explain the strange absence of memoranda in the disclosed documents). In my view AA by this time had realised the serious problems that it was creating for everybody. It is in my judgment a patent admission since at this stage the disarray was of AA's making. It made me wonder why RBH's case on the aspect of liability was being defended by AA.
" .As discussed with Mr Edwards, the signed Certificate is subject to the programme of completion of outstanding information as agreed with your goodselves; this programme having been related to the general production information to be provided to the contractor in accordance with his current programme of works."
The Certificate read:
"CERTIFICATE OF READINESS TO PROCEED TO TENDER
The Board of Governors of the National Heart & Chest Hospitals |
The Board of Governors of the National Heart & Chest Hospitals |
SCHEME | National Heart & Chest Centre Phase I |
I certify that the revised tender documentation which takes into account the reduction to the work scope is consistent with and fully reflects the general production information to be provided to the Contractor."
Neither Mr Edwards nor Mr Tyler could recall the discussion referred to in Mr Tyler's letter. Although in the previous year an indemnity might have been provided by RBH to a consultant who was then not in a position to issue such a certificate, none was sought in 1987.
"Master Programme
TWC will integrate their programme with the M& E programme and will then re-issue.
The network analysis will be discussed between TWC and PMI on 3 June.
Austen Associates will comment on the M&E programme as soon as possible.
TWC will produce short-term programmes covering a three month period by 30 June. These will be reviewed monthly."
TW also issued a further Information Schedule but the discussion did not relate to services.
"A. That is the everyday story of consulting engineering; that is what goes with the territory. That is part of the skill of being a consulting engineer; you have to go with these issues. You simply cannot turn round to the client and say, "I cannot deal with your issue today". It is the ebb and flow of workload, which is the normal professional control of the consulting engineer in the exercise of his duties.
Q. You agree that that sort of business can be very disrupting indeed for the engineer?
A. Oh, it is a challenge, without doubt. Always is. It goes to the nature of the work. Would we not just love a project where we start on it, work on it continuously and finish it, but life is just not like that.
Q. And it can be, in fact, very difficult to cope with, particularly at a busy time in the industry?
A. That is part and parcel of the job.
Q. You agree?
A. Yes, it is part and parcel of the job, on every job, every consulting engineering practice. It is normal."
In his statement Mr Tyler described how "by the autumn of 1987 the overall management of the project had deteriorated to an extent whereby the constant late information, changes, and lack of co-operation from [TW] had an impact on the morale of the AA staff. This was to the extent that the Associate in charge of the Mechanical element of the design work, David Hammond, resigned". Mr David Hammond became a partner in another firm. When asked why AA could not produce the co-ordination drawings for level 1 by mid-June, Mr Edwards said simply "Because of the workload". I infer that AA suffered from this at a much earlier stage than autumn 1987. In any event another opportunity was lost. In his evidence Mr Coleman thought that by June 1987 the provision of information to TW was "getting into the danger zone", and that Mr Teale should have taken it up with AA. Even Mr Teale acknowledged that by that time:
"there were difficulties in producing the information, and difficulties in the co-ordination area. There were difficulties with Taylor Woodrow. So one could say that, at this early stage, we were getting into some quite difficult water, yes.
Q. There was a need for a fairly firm grip to be taken on the provision of information?
A. There was, yes."
"4.2.1 e) Master Programme
TWC/Taymech anticipate the issue of a fully co-ordinated Building/M&E programme by the end of July.
The network analysis was discussed by TWC and PMI on 3 June. PMI to comment.
AA confirmed they had no comments on the M&E programme.
TWC will produce a short term programme each month in a form acceptable to PMI.
CONTRACTOR'S PROGRESS REPORT
TWC distributed copies of their report to 29 June. This indicates that, assessed against Programme Drg No. B364/P1 rev B, the contract is 4½ weeks behind programme. It was confirmed that it was TWC's intention to complete on time, bearing in mind the current situation. TWC are currently reviewing the situation and the steps required to redress the present position.
AA
AA had no comment at this stage but agreed to review the procedures for the issue of information since TW have been receiving part information in some cases."
The minutes refer to a network analysis which PMI had prepared. Mr Hutchings was certain that he did not see it and WGI's files had no record of it being sent by PMI on 9 July. It does not thereafter feature very much so I conclude that it was not used or not kept up to date or both. Furthermore in the light of Mr Hutchings' evidence and the absence of any reference to it by WGI I conclude WGI did not receive it or did not find it to be of any use. According to a PMI report for June it then contained a "free float time of at least nine weeks" but it is not at all clear how it was arrived at or whether it was sound. As Mr Edwards-Stuart demonstrated with Mr Miers the programme did not deal with commissioning, one of the last activities so I do not accept that what we know of PMI's work can be made to be relevant. It may be that PMI projected a float of that order. In a report on tenders in 1986 TW was said to be aiming for "building completion" at week 117 with "hand over" at week 125. This could have justified PMI's own estimate. However it remained unclear to me whether the gap was a true float or whether it would be occupied by commissioning etc prior to hand over. Mr Miers also accepted that without an analysis of how the subsequent programmes developed and were changed, one could not know to what extent any such float survived. In my view no float was or could therefore be established. Its existence was speculation and thus could not provide a proper basis for anything other than a tentative and equally speculative opinion.
"Further to our meeting held on 30 June 1987, we enclose, for your information, a preliminary (i.e. untraced) copy of drawings numbered 668.1/C/1H/10 and 668.1/C/1H/03. These drawings show the co-ordination for Level 1, Area 3. If there are any problems, please do not hesitate to contact us."
The same happened on 8 July 1987, when AA issued the first set of co-ordination drawings for Level 1, Area 4, "as previously agreed". They were followed on 14 July, yet again, by similar preliminary co-ordination drawings for level 1, zone 5. That was the best that AA could then do and it shows what a parlous state it was in. Not surprisingly PMI wrote to AA on 13 July 1987 a fairly sharp letter expressing concern:
"We are in receipt of your letter dated 8 July 1987, to Taymech, enclosing preliminary co-ordinated drawings for level 1 High Level.
We are concerned that these are preliminary at this stage bearing in mind our need for overall builders work drawings required from the Contractor for this level. We are also concerned with the contents/query document WO84/44.
Can you please forward as promised the agreed dates for issue of information to Taylor Woodrow which perhaps will help to reduce our concern on the overall situation of co-ordination."
Mr Edwards could not recall whether dates had then been agreed or had still to be agreed. In my view it was the latter since if they had been agreed PMI would have been told of them straightaway. I was referred to the transcript of Day 19 of an earlier trial (4 December 2000) when Mr Edwards seemed "to remember now that there was an agreement that they would have preliminaries on a certain date and the pukka drawings soon after." No doubt TW was able to make some use of the drawings but in my view it would have been disingenuous and would have smacked of desperation to have said to me that drawings designated as preliminary drawings were as good as "pukka drawings". PMI submitted that AA's actions showed that even if it had chased them more vigorously it would have had no effect. This point would have had some force if PMI had picked up AA's intentions. Of more consequence is the later treatment and acceptance of the dates when the definitive drawings were issued as the effective date for assessing extensions of time due to TW, e.g. 14 August for level 1, over six weeks after the time that TW was expecting them and some eight weeks after the time when AA was to have produced them.
"This was discussed at our meeting on the 31st July 1987 and at the Design Review Meeting on the 4th August 1987 and it was agreed that this was an inadequate document.
"We confirm that you will establish in detail the information release date required by Taymech, together with the dates that they intend to issue working drawings for you and other members of the Design Team to comment on. This now requires completing as a matter of urgency."
ITEM | DESCRIPTION | ACTION |
ACTION |
ACTION |
1. | Austin Associates stated that the services should be installed to the co-ordination drawings. |
Taymech | Taymech | Taymech |
2. 3. |
Austin Associates shall cloud the individual services layout where there are minor changes to these drawings compared to the co-ordination drawings. Austin Associates shall change the individual services layouts where there are significant alterations between these and the co-ordination drawings. |
Austin Associates Austin Associates |
Austin Associates Austin Associates |
Austin Associates Austin Associates |
4. | The following programme was agreed by both Taymech and Austin Associates for the issue of co-ordination drawings to enable Taymech to produce their installation drawings prior to Taymech's start on site dates. |
Taymech/Genevers/ Austin Associates |
Taymech/Genevers/ Austin Associates |
Taymech/Genevers/ Austin Associates |
Level |
Taymech Start-on-Site |
Co-ordination Drgs. Issued |
Issue of Genevers Invert Drgs. To A.A. |
|
1 | 5/10/87 | This Week | - | |
2 | 16/11/87 | 07/09/87 | 12/08/87 | |
3 | 04/01/88 | 12/10/87 | 28/08/87 | |
4 | 08/02/88 | 23/11/87 | 04/10/87 | |
5 | 14/03/88 | 04/01/88 | 13/11/87 | |
6 | 25/04/88 | 08/02/88 | 18/12/87 | |
5. | Invert level drawings to be issued to Taymech with co-ordination drawings, but to be issued to Austin Associates as above programme to provide Austin Associates with information for co-ordination. |
Genever/- Austin Associates |
Genever/- Austin Associates |
Genever/- Austin Associates |
6. | At the site meeting on 28 July 1987, it was agreed that these drawings would be issued starting that week. This has not happened but these drawings shall be issued in line with the above programme. |
Genever/ Austin Associates |
Genever/ Austin Associates |
Genever/ Austin Associates |
7. | Other Outstanding Information | |||
(a) Pipework Level 2 (revised) to be issued with co-ordination drawings for Level 2, i.e. 07.09.87. | Austin Associates | Austin Associates | Austin Associates | |
(b) Control drawings to be issued by 30.10.87. | Austin Associates | Austin Associates | Austin Associates | |
(c) Level 6 drawings to be issued by 27.11.87. | Austin Associates | Austin Associates | Austin Associates | |
(d) Schedules (equipment) Austin Associates to issue this week to Taymech a list of those schedules that have to be updated, then Taymech shall give dates as to when revised schedules are required. | Austin Associates/Taymech | Austin Associates/Taymech | Austin Associates/Taymech | |
(e) All revised electrical drawings to be issued by 30.09.87. |
Austin Associates | Austin Associates | Austin Associates | |
8. | Taymech shall reassess the issue of their drawings after they have received Austin Associates' drawing register. Austin Associates to issue drawing register on 12.08.87. |
Taymech Austin Associates |
Taymech Austin Associates |
Taymech Austin Associates |
9. | Taymech requested revised kitchen equipment schedule. Austin Associates to chase Northcroft Neighbour and Nicholson for price. |
Austin Associates | Austin Associates | Austin Associates |
10. | Taymech requested setting-out position of equipment etc. Austin Associates had previously referred them to Watkins Gray International but Watkins Gray International have not issued anything. |
Watkins Gray International |
Watkins Gray International |
Watkins Gray International |
11. | Taymech requested a current Watkins Gray International drawing register. |
Watkins Gray International |
Watkins Gray International |
Watkins Gray International |
12. | Taymech expressed concern that Watkins Gray International radiator setting-out details did not work in many instances and although Watkins Gray International had held several meetings to discuss the problem, no confirmation of these discussions or alterations to the setting-out details have yet been received. |
Watkins Gray International |
Watkins Gray International |
Watkins Gray International |
13. | Taymech stated that the issue of the Design Team comments on their Level 2 builders work drawing did cause some confusion. Austin Associates stated that the Design Team had agreed to meet, discuss and co-ordinate their comments and following this meeting issue one collective drawing back to Taymech in co-ordinating all the Design Team comments. |
Watkins Gray International/ Clark Nicholls Marcel/Austin Associates |
Watkins Gray International/ Clark Nicholls Marcel/Austin Associates |
Watkins Gray International/ Clark Nicholls Marcel/Austin Associates |
Taymech issued a programme giving dates for the builders work drawings to be issued, commented on, modified and issued for construction. |
||||
Austin Associates stated that as far as they were concerned the programme was acceptable, (copy attached). |
||||
14. | In view of the drawing programme (item 4 above) Taymech are now in a position to provide a schedule of those drawings to be presented to the Design Team, for comment, subject to the associated Architect's drawings being available. | Taymech | Taymech | Taymech |
The minutes were sent to everybody including Genever and Partners. On 12 August 1987, TW issued Construction Programme P01/C. The programme showed the same dates for commencement of 1st fix by Taymech as had been established at the meeting on 11 August. The only "info" requirement noted was for level 1. AA wrote to WGI on 17 August to say that it had no comments to make on this programme. This programme ought of course to have been issued months earlier. The periods agreed from the time when TW was to get the drawings had to cover the production and approval of TW's installation drawings, i.e.
Level | TW start on site | Dates agreed on 11.8.87 | Period |
1 | 05.10.87 | 14.08.87 | 8 weeks |
2 | 16.11.87 | 07.09.87 | 10 weeks |
3 | 04.01.88 | 12.10.87 | 12 weeks |
4 | 08.02.88 | 23.11.87 | 11 weeks |
5 | 14.03.88 | 04.01.88 | 10 weeks |
6 | 25.04.88 | 08.02.88 | 11 weeks |
On 14 August 1987 AA issued the last of the drawings for level 1 that for zone 2 (the preliminary version had been issued a few days earlier). AA sought to explain its late issue by reference to a decision taken in mid July to drop the idea for a new aeration room for the HSDU. However until that time, although there had been discussions about what was needed under HTM 10, the room had for planning purposes been included in the design approved at the beginning of April and shown on AA's mechanical layout drawings which covered the redesign. There is however no evidence either RBH or PMI told or expected AA not to issue any co-ordination drawings simply because there might be a change in design or that AA did not do so on that ground - see Mr Tyler's witness statements. Mr Tyler's 4th witness statement provides a very full and clear account of the steps that AA took from which it is clear no assumptions could be made that an aeration room would be included. I cannot therefore see that these events provide AA with a defence.
" . Nine weeks was the bare minimum it would have been to produce; it did not allow any tolerance. It did not allow for any further approval stage if we produced working drawings and they went to the consultants for approval. It assumed everything was perfect; that the information presented to us was perfect, and that our drawings contained no mistakes when they went to Austens. There was no leeway for any further alterations to those drawings and any resubmittal. So you are talking about a fair balance.
Furthermore, it did not give us any lead in time on things like ductwork. After our installation drawings had been approved the ductwork subcontractor had to prepare his installation drawings and fabrication drawings which then had to be submitted for approval. You have got the same situation, in an ideal world it might have taken four weeks; the chances are it would have taken about six weeks. So instead of the nine weeks that is conveniently put forward at that time, you are talking more in the region of maybe 18 to 20 weeks as being a more factual requirement.
Now, what we did say at that meeting, the agreement was that we would make every endeavour to meet our start programme on site. To this end we had a ductwork draughtsman on site working alongside our drawings, producing fabrication drawings. Now this was very risky, you know. He was actually taking information from our drawings, which were as yet unapproved or commented on, to produce his fabrication works. In fact, he produced his ductwork on that basis.
So we were talking extraordinary measures to try and meet this nine weeks that was thrown at us, and the way that my answers come across in the previous cross-examination does not bring this out. It makes it look as if we were always in agreement with these dates and we were happy with them. We were far from happy with them."
"Q. ..AA were moving heaven and earth to get the drawings out?
A. Yes.
Q. So the difficulty was not in identifying what you had to do or when you had to do it?
A. No.
Q. But in actually getting it done?
A. Yes.
Q. Is that fair?
A. We knew we had to do it and we [were] pushing for it."
However AA evidently suffered from lack of resources and good management (as did TW) since it was not able to provide drawings of the required quality by the dates required. Mr Edwards said AA had the resources ("we probably had between 17 and 20 people"), but that assertion was not supported. There was a general shortage of good staff as Mr Hall's evidence showed. I have referred to the lack of morale within AA. In any event it is not possible to accept Mr Edwards' assertion that AA was unable to do better to produce drawings any quicker. First, AA led everyone to believe in February and March it could and would get the drawings done on time. Secondly, AA has no records against which the credibility of Mr Edwards may be judged. AA was being paid a significant fee (3%) to produce the drawings. I was left with the distinct impression from AA's evidence that it was not going to risk cost exceeding revenue. As Mr Adams said in cross-examination:
"It depends on the pressures on that particular consultant. He may have two major projects and they go at the same time. In that case he who shouts the loudest gets the drawings. That is common practice within our industry, I am afraid.
Q. You are not aware, are you, of anything that you have seen that suggests that Mr Edwards is wrong in saying that a programme would have made very little difference to you?
A. I am in no position to comment on that. That is Mr Edwards' view."
Thirdly, Mr Edwards' own evidence is itself of no value. He showed himself to be partisan and determined to stick to his carefully prepared script. In my judgment had AA been taken properly to task at any time from March a feasible programme would have been devised which would have been implemented by both AA and TW.
"A BUILDERS WORK
1. 20/8/87 Genevers issued further comments on level 2 slab drawings which will involve further changes to drawing and re-issue.
2. We await information on gullies in plantroom to add the relevant builders work holes.
3. 21/8/87 No comments available on level 3 slab drawings. Programme B/364 BWP/1 calls for comments in sufficient time for Taymech to amend and re-issue by 24/8/87. Holds on this drawing still awaiting information from Watkins Gray.
4. No comments available on B/W drawings detailing holes through walls and beams for levels 1 and 2 issued as below:-
Level 1 (WO84/BW/07) 15/7/87
Level 2 (WO84/BW/05) 7/7/87
NB:
The above drawings were produced without co-ordinated services drawings being available.
5. Level 3 Holes through walls and beams drawing on board and will be available to meet programme. The drawing is being produced without co-ordinated services information being available.
..
C CO-ORDINATION
All level 1 co-ordinated services drawings received from Consultant to enable Taymech to produce working drawings.
Taymech have identified many areas where major clashes occur, query sheets attached.
The time involved in identifying the problems and then the Consultant resolving the same effectively delays the information flow agreed during the meeting with the Consultants of 12th August 1987. This will have a "knock-on" affect on Taymech producing working drawings which could affect the programmed start date.
Outstanding information affecting co-ordinated services working drawings:-
1. Revised ceiling layouts showing new levels as advised by A.A.
2. Ceiling layouts indicating positions of all ceiling mounted equipment i.e. grilles, diffusers, lighting etc.
3. Equipment positions i.e. fume cupboards, safety cabinets, sterilisers, laboratory furniture etc, with tie down dimensions."
"1. PREAMBLE PRIOR TO TAYMECH SITE ESTABLISHMENT
(a) Meeting held at A.A. offices 26 February. At the meeting A.A. informed Taymech they were producing full co-ordinated M & E drawings, also holes 150 x 150 had been detailed by A.A. in conjunction with C.N.M.; Taymech were to verify these holes and set out holes below 150 x 150.
No official minutes of this meeting were issued.
(b) Site meeting 31 March (item 1.5 11 & 12) states that Taymech must produce builder's work details in time to meet T.W.C. construction dates.
(c) General issue of "For Construction" drawings issued under A.A. draft instruction M1 dated 3 April issued to W.G.I. These drawings received by Taymech 13 April.
(d) Plumbing drawings levels 1 & 2 only collected from site 14 April. Only level 1 invert levels indicated. Levels 3 to 6 issued 16 April.
(e) T.W.C. preliminary programme T.W.C./B364/P1 Rev. B circulated prior to 28 April site meeting. Programme indicates that construction details for 1st and 2nd fix M & E installation required by 2 May.
(f) Taymech initial site team moved to site 18 May. Site team included J. Hanning, draughtsman.
(g) Trainee Junior Engineer/Draughtsman, Stephen Kane, arrived site 1 June.
Draughtsman, D Dickenson arrived site 15 June.
Draughtsman, S Maclenahn arrived site 20 July.
(a) At meeting on site 21 May with A.A. it was indicated that preliminary co-ordinated drawings level 1 zones 2, 3, 4, & 5 would be issued by 28 June (no minutes).
(b) At meeting on site 30 June with A.A. it was indicated that co-ordinated drawings would be issued as follows:-
Level 1 | Date | Preliminary Actual | For Construction |
Area 1 & 6 | Issued |
||
3 | 3 July | 3 July/7 August | 19 August |
4 | 8 July | 13 July | " |
5 | 10 July | 16 July/7 August | " |
2 | ? | 8 August | " |
Level 2 |
|||
Area 3 & 4 | To be checked |
8 September | |
2 & 5 | In production |
||
1 & 6 | ? |
||
Level 3 |
|||
Area 1 to 6 | Not yet commenced |
(c) D & C WO84/61 dated 24 July raised first co-ordination query reference drawing 668.1/C/1H/04.
(d) D & C WO84/66 29 July raised query reference drawing 668.1/C/1H/04.
(e) Taymech letter 31.07.87 request latest reissued drawing level 1 zone 4 drawing to reflect latest architectural changes.
(f) Drawings 668.1/D/1/2/3/4 issued 7 August amended for co-ordination issue.
(g) Co-ordination query documents raised 4th, 5th and 11th August. Level 1 Zones 3 & 4.
(h) Meeting held with A.A. on site 12 August to discuss co-ordination of working drawings and agreed programme of co-ordination issues. This was based on the premise that Taymech required 10 No. working weeks for two draughtsmen to produce line and level working drawings.
(i) Co-ordination query documents raised 14, 18, 20 & 25 August. Level 1 Zones 3 & 4.
(j) Site meeting 25 August Taymech tabled latest status report related to the preparation of building services drawings.
(k) Co-ordination query documents raised 26 and 27 August, Level 1 Zones 3 & 4.
(l) A.A. drawing register received 20 August.
(m) A.A. Q.A. Engineer issues Taymech with list of drawings that latest revisions have not been received.
(n) T.W.C. letter 28 August to W.G.I. informs of difficulties in producing working drawings and indicates our concern with the production of drawings to meet construction programme.
(o) T.W.C. 4 September letter to A.A. again states latest position.
(p) Taymech letters 4 & 7 September informs A.A. of latest drawing revisions not in our possession.
(q) Meeting held 8 September on site with A.A. to discuss latest co-ordination problems.
(r) Taymech informed by A.A. 9 September that full time A.A. co-ordination draughtsman will now be permanently site-based. A.A. Electrical & Plumbing engineers will also visit site twice weekly to resolve engineering and co-ordination problems that might exist.
The latest position regarding the production of working drawings for level 1 zones 3 & 4 is as follows:-
Zone 3 plan and sections ready for tracing by 19 September.
Zone 4 plan and sections ready for tracing by approximately 26 September.
(a) The following Q & A queries are outstanding 88 to 102 and 105 to 110.
(b) Revised kitchen equipment schedule.
(c) Setting out details of equipment.
(d) Laboratory equipment schedule.
(e) Reflected ceiling plans.
(f) Line and level on co-ordination drawings and sizes."
Thus, as para 3(r) records, TW had a meeting with AA at which AA agreed to base a co-ordination draughtsman permanently on site and that AA's electrical and plumbing engineers would also visit the site twice a week to resolve any engineering and co-ordination problems that might exist. Mr MacDonald was sent by AA to work alongside Mr Honey of TW in order to resolve the position of services in plan and level ("line and level"). Mr Honey was an experienced co-ordinator. It was suggested that had he arrived earlier TW might have got on better. I do not accept that submission as there is no justification for it either in the contemporary records or in the evidence. TW was then dependent on AA and, despite shortcomings elsewhere, it could not have made better progress on the installation drawings.
3. 20 October to 13 November 1987
4. 23 November 1987 to 6 January 1988
5. 4 January to 15 January 1988
6. 15 January to 8 February 1988.
The dates agreed on 11 August were therefore not met in full. The drawings issued were not always usable by TW for its purposes for reasons which I shall consider. In my judgment AA ought to have produced the drawings by mid June onwards at the latest.
WGI and Timing
PMI and Timing
"PMI should have agreed with Austin Associates, Taylor Woodrow and WGI, a programme for the provision of, inter alia, co-ordination drawings to Taylor Woodrow and established that Austin Associates and Taylor Woodrow were ad idem as to what was to be provided and when. PMI should then have reviewed regularly the progress of Austin Associates in producing and providing co-ordination drawings, identifying any potential delay or shortcoming on Austin Associates' part so as to ensure the timely and adequate provision of co-ordinated drawings by Austin Associates. This should have been done throughout 1987. In essence, PMI should have complied with paragraph 4.2 of PMI's Procedure Document dated the 22 May 1987 ("the Procedure Document"), which provided:
"The Senior Project Manager of PMI with the assistance of his Chief Planning Engineer will monitor the design process to ensure that the flow of construction information meets the requirements of the Contractor."
PMI should also have complied with paragraph 8.3 of the Procedure Document, which provided:
"The Main Contractor will prepare a schedule of Information Requirements covering the total project. In accordance with the Contract Conditions a fully detailed Information Requirement Schedule will be issued at each Site Meeting covering the forthcoming period highlighting information containing long delivery items. This information will be co-ordinated and monitored by PMI".
I have already made it clear that it is not an answer to point to TW's failure to produce proper programmes since the basic sequence and timing was clear. TW's failure did not lead to work grinding to a halt. PMI continued to monitor TW's work and by holding regular meetings were able to obtain enough information about TW's short term programmes. PMI's obligation under clause 11(f) to "oversee the preparation of design programmes for all elements of the project within the master programme " was not dependent on the existence of TW's programme. PMI had not established a programme for the production of AA's drawings before TW started on site. There had already been the major deviation from Capricode procedures in that TW had begun when the preparation of co-ordination drawings had barely started. It was incumbent on PMI to take every step available to it to see that that risk paid off. In my judgment it ought then to have convened meetings to obtain the programme from AA and to get dates agreed dates but it did not do so. It was left for TW to provide the dates until it was too late. In my judgment PMI did not do enough to obtain such a programme from AA. Mr Teale was far too trusting. By early May PMI was being fobbed off by AA. PMI ought then in conjunction with Mr Blair to have called the senior partners of AA to a meeting and had a showdown. According to Mr Hutchings (and to Mr Teale) that would have worked. Mr Hutchings said:
"Q. But usually, I imagine, Mr Hutchings, in your experience, once correspondence -- or once it gets taken into the hands of senior partners, the problem normally resolves itself?
A. Yes.
Q. Because inevitably, whilst, as it were, requests at site meeting level might get fobbed off, stern letters, senior partner to senior partner, usually get taken pretty seriously?
A. That is my experience, certainly."
Thus Mr Teale was wrong to think that the only effective sanction was the "stick" of termination. Mr Adams put it very well during the course of his cross-examination by Mr Williamson:
" Exactly, my Lord, and I think that is my suggestion; that notwithstanding what Taylor Woodrow were or were not saying, the project manager should have been marshalling the design team to produce a programme and get the drawings out as quickly as they can.
MR WILLIAMSON: On the basis of the documents that we have looked at together, Mr Adams, I would suggest that is exactly what they were doing?
A. I see no design programme; I see no co-ordination of that design programme. I do accept that I have not mentioned the pressure which PMI have quite correctly placed on Taylor Woodrow and AA. But the end product is that six months into construction we do not have the agreed design programme that will satisfy Taylor Woodrow's information requirements in the long-term.
JUDGE LLOYD: I mean, we have not seen, if I see things correctly from your point of view, a large round table meeting to confront people with their responsibilities?
A. Correct. There have been monthly design meetings; there has been one letter a month where the file has been reactivated; but the face-to-face meeting which you suggest does not appear to have taken place."
PMI did not pursue the request that it made to AA in its letter of 7 April 1987 for a programme for the release of the outstanding design information. Had it done so I am sure that the position would have been rectified and dates agreed between TW and AA. Even as late as June Mr Teale said: "The situation was still very much controllable and I saw no reason if all parties co-operated why the M&E installation date could not be maintained". PMI did no more than write a further letter of 18 May 1987, which was again not followed up. Thereafter the position was no longer "controllable". Had PMI taken AA to task, such as by contact with a senior partner then in my judgment TW would probably have got the drawings much earlier and in time to avoid the delays that it experienced. Accordingly I conclude that PMI was in breach of its obligation under its retainer to oversee the preparation of AA's design programme and AA's administration of its part of the construction contract and that but for such a breach AA's drawings would have reached TW in time.
Further Events
" .Bruce Walker at the meeting held on 13th November ..categorically assured the meeting that by adopting the CAD procedure he could recover the time lost in the production of the joint venture installation drawings for the engineering services, and re-establish the overall programme required target dates. This you have correctly recorded in the minutes of meeting no. 7 under item 3.1. There could have been no misunderstanding because you will recall that I myself demanded a clear statement from the joint venture representative confirming that his proposals to use the CAD avenue of drawing production would restore the programme target dates. He made the clear statement that this would be the case."
Mr Tyler repeated that view in a letter to TW of 26 November. Since TW could always have hired more agency staff I conclude that it thought that the additional costs that it was now bound to incur might be better used to engage a sub-contractor who might do better than a clutch of agency staff.
Level | Date CAD In | Date CAD Out |
1 | 20.11.87 | 04.12.87 |
2 | 20.11.87 | 04.12.87 |
3 | 07.12.87 | 23.12.87 |
4 | 07.12.87 | 23.12.87 |
5 | 14.01.88 | 24.01.88 |
6 | 02.02.88 | 18.02.88 |
It was also accepted at the meeting that the use of CAD would enable TW to achieve the target dates required for installation(see item 3.1). AA decided that it would use WOCAD for the production of co-ordination drawings (initially only for Level 4 Zone 2). AA had by this time issued co-ordination drawings:
Level | Zone |
1* | Zones 2, 3, 4 and 5 |
2 | Zones 3 and 4 |
2 | Zones 1,2, 5 and 6 |
3 | Zone 1 |
3 | Zone 2 |
3 | Zone 3 |
3 | Zones 4, 5 and 6 |
(*The list omits zones 1 and 6 as no co-ordination drawings were required for the boiler house and plant rooms as the services were detailed to a larger scale. There was basically only one service in each plant room.)
"In recent correspondence it appears that Taymech are suggesting their work is being disrupted and delayed due to lack of information from Austin Associates at the appropriate time having regard to their pre-construction programme.
Under the terms of your Contract you are responsible for the flow of information from the Design Team to the Contractor and in the event you consider Taymech's claim is justifiable we will be pleased to learn, at the very earliest time, what measures you intend to take to ensure the situation is rectified."
WGI sent a copy of the letter to Mr Teale and to Mr Edwards at AA. PMI replied to WGI on 16 November which reasonably clearly sets out the position at that time (at least as seen by PMI):
"With reference to your letter dated 6th November 1987, we comment as follows:-
A. The responsibility for the total direction, co-ordination and integration of the work of the Design Team remains with yourselves. PMI monitor the events and to this end we have since April 1987, registered our concern in letters and at our Design Review Meetings, at the lack of direction between Austin Associates and Taymech.
B. The problems of the preparation of working drawings by Taymech is not recent as your letter suggests, but in fact surfaced some 3½ months ago, As we learnt at the meeting last Thursday the success of the Services installation in meeting target programme now depends on the successful employment of the C.A.D. computer to provide working drawings.
Austin's letter to you dated 9th November 1987 provides a record of events following the meeting with Taymech on 12th August 1987, where dates were finally established for issue of working drawings from the Consultants and the Contractor. What is required is the schedule of events prior to this date in answer to Taymech's letter of the 28th August 1987 and to the schedule attached to the minutes of the meeting of 14th September 1987. This information will allow you to consider whether a claim for delays due to late issue of information is justifiable.
C. The Taymech issue of information requirements dated 12th August 1987 details dates for clearance of builders work drawings, location of equipment etc. (fume cupboards etc.) reflected ceiling plans. This still requires close attention on co-ordination on your part as not all dates have been met.
D. Many of the problems we are experiencing are due to information programming still not resolved by the Contractor and in non compliance with Clauses 1/15/A1, A2, A3, A4, A5, 1/22C & 1/22D.
This is reflected in the Contractor's report for the site meeting on 17th November 1987 where we hear for the first time curtain walling and timber studding details are awaited and may be the subject of delays. We have urged compliance with programming requirement for a long time to assist in co-ordination of information issue and we feel this should be clearly stated to the Contractor.
The next meeting with Taymech is on 27th November 1987 and we trust that the measures being taken will rectify the situation, but we request that we are kept informed of the progress of the C.A.D. operation."
In a further letter of 18 November to WGI Mr Massey of PMI noted "with concern some of the points raised" in a report received from Mr Agate of TW and said
"The situation regarding building services is well known and I will not dwell on that for the time being."
He concluded percipiently:
"I suspect that many of the points raised are all part of the "Agate Wind-up Strategy" and there is no harm in that. However I am concerned that in the fullness of time, others may seek to pin financial values to the allegations."
"Thank you for visiting our offices with Paul Tyler and Frank White on Friday afternoon.
I confirm that further to our discussions, we would be delighted to provide drawing services to Austin Associates based on the following agreed principles.
1. That Wocad would reproduce co-ordinated drawings for each level and zone of the project.
2. That these drawings will be the result of required changes indicated by Austin Associates from drawings previously produced by Wocad for Taymech, which indicate service clash points.
3. That Austin Associates will study and approve all drawings prior to their issue to the contractor, and that in this respect Wocad will only be providing a drawing service and cannot be held responsible for any design element of the project.
4. Drawings will be produced A1 size.
5. Drawing schedules noting the issue number used to produce these drawings will be indicated on each drawing produced by Wocad.
6. The production of the drawings will be charged on an hourly rate basis which in this instance will be charged at £23.00 per hour.
7. Excluding a nominated zone on level 4, the above drawings will be produced for a sum not to exceed £10,000 + VAT.
8. One zone on level 4 will be co-ordinated totally by Wocad from individual service drawings for the sum of £1500 + VAT.
9. Should Austin Associates wish to terminate this agreement at the completion of levels 1 and 2 and item 8 above they will only be charged by Wocad for hours expended to that time plus item 8.
I hope the foregoing is a satisfactory summary of our agreement and look forward to your instructions in the near future."
AA accepted this offer, promptly, on 19 November and employed WOCAD's services. As appears from paragraph 1 of WOCAD's letter there was no limitation: "each level and zone". Although at times Mr Tyler suggested otherwise it became clear that AA had retained WOCAD for every level but reserved the right not to continue after level 2 (see paragraph 9 of WOCAD's letter) and made special provisions. I do not consider that his recollection is correct. I also do not accept Mr Tyler's evidence: "Taymech's decision to use CAD was very foolish and really an act of desperation. I took the view at the time that this was a mistake. This was because CAD was still in its infancy and it appeared foolish to start using such technology part way through a complex project such as Phase I. Sadly, I was proved right". This is ex post facto justification. In my judgment, although the use of WOCAD was not successful, the reservations subsequently expressed by Mr Tyler are at variance with AA's actions.
"3. . The Project Managers and ourselves directed a clear question to you with regard to your proposal to use computer aided draughting and you replied in the affirmative, that the target dates required to comply with your installation programme could be achieved using this method. Your assurance in this respect was the main reason we supported you in this revised method of working drawing production.
AA was then (and subsequently) writing to protect itself from TW's claims that it had been delayed by AA's late issue of the co-ordination drawings and their quality. At a site meeting (no 10) on 15 December 1987 item 10.2.3 read:
"Item 9.3.04 Taymec reported the following regarding the production of co-ordinated drawings as follows:
Level 1: AA & Taymec are agreeing details where clashes have appeared and Zones 3, 4, & 5 will be issued before the last zone which will be 11.12.87.
Level 2: issued by 18.12.87
Level 3: issued by 8.1.88
Level 4: issued by 27.1.88
AA pointed out that because of the amount of time Taymec are using the computer, they have been unable to take advantage of the facility.
Taymech reported that there are problems of clashes occurring on level 1 as AA's co-ordinated drawings already in existence had not been used. Most clashes were due to line and level problems which had also been agreed earlier."
It was agreed that in future CAD would include a list of the drawings from which the information had been taken."
Later, under Contractor's Report, the following was minuted:
"TWC handed over their report and a copy is attached.
It was pointed out that TWC would complete the r.c. frame on time but there was an overall delay of some 9 weeks due to the M & E works. After discussion TWC agreed that the services installation could still finish by end dates on programme, on the understanding that the flow of information is maintained.
TWC pointed out that they did not agree with AA's statement at the previous meeting (Item 9.3.06) that they were not responsible for any delay and considered that there was some delay due to the Design Team.
PMI stated that they were impressed with the quality and progress of the work but considered that the blockwork could proceed quicker in several places around the site.
TWC advised that they did not want to be involved with cutting holes after the erection of the blockwork."
"11.3.0 Contractor's Report
a) The concrete frame was 3 weeks behind the programme.
b) The M & E works were 11 weeks behind programme
c) The M & E drawing programme was 20 weeks late and to date only 3 no working drawings had been produced.
11.3.3 WGI commented that the M&E part of the contract was further behind programme now than in November when manually produced drawings of level 1 had been issued. TW confirmed that they were using these drawings on site.
11.3.4 It was pointed out that the delay caused by Taymec's failure to produce drawings was the Joint Venture's responsibility and not the Design Team. It was Taymec's decision to use WOCAD who do not now seem capable of producing the drawings in sufficient quantities and in accordance with agreed programmes. It was considered that the level of information being produced by WOCAD indicated to the Design Team that not all the Design Team's information had been programmed into the computer and the Joint Venture were thus failing to meet their responsibilities.
11.3.5 TW made no comment on the statement in 11.3.4 but reported that they had evaluated the M&E situation and were using their best endeavours to mitigate the problem and complete the contract on time.
11.3.6 Because of the M&E delays work is proceeding on a site with drawings which have not been officially issued under the terms of the contract which requires drawings to be signed by the Design Team.
AA were therefore asked by the Contractor to confirm that the work being installed on site was in accordance with the contract. AA problems at the time were not aware of any problems at the time [written in by hand as a substitution for "AA could not confirm this"].
a) Taymec advised the meeting that they were applying pressure on WOCAD to produce drawings.
b) At the request from WGI, TW confirmed that they were satisfied with the M&E supervision and labour force on site. If there was a problem work would be sublet and the Design Team would be notified in accordance with the Contract. TW does not anticipate problems with labour.
11.5.0 Services Engineer's Report
11.5.1 AA handed over their report and copy is attached.
11.5.2 AA highlighted some areas where they thought services could proceed, eg the boiler house area.
(NB) Subsequent to the meeting TW pointed out to WGI that work to the services in the boiler house could not proceed as late changes in design and specification by AA had necessitated altering drawings and details which, although issued to AA, had yet to be approved (14.1.88).)
11.5.3 TW pointed out that the slippage in time noted on AA's report seemed rather optimistic.
.
11.7.0 PMI's Report
11.7.1 PMI confirmed their pleasure to hear the contract would be completed on time.
11.7.2 It was agreed that a meeting between the Joint Venture directors and the Design Team should be convened to discuss the present state of the contract.
"
" The writer must also remind you that it was clearly pointed out at the meeting by the Joint Venture that the co-ordinated drawings are Austin Associates drawings, will always be Austin Associates drawings and at no time are they Taymech/Joint Venture drawings. These facts are clearly set out in the Terms and Conditions of the General Specifications for the M & E Services and the General Specifications of the Main Contract.
We would be obliged if you would clearly report these comments as they were raised by the Joint Venture.
With regard to Item 2.1 we would, once again, point out that the issue of co-ordinated drawings is the responsibility of Austin Associates as a member of the Consultant Team and that it is clearly shown in the documentation (General Specification M & E) that the only line and level required by the Joint Venture is on working drawings. It should be therefore, be noted that at no time is the Joint Venture required to put line and level on Austin Associates co-ordinate drawings.
From these facts it is clearly established that the co-ordinated drawings are issued by Austin Associates to the Joint Venture and should by this time have received the input of all the necessary information for the drawing to be a co-ordinated drawing and that all the information to establish the co-ordinated drawing at this point is clearly the responsibility of the Consultants and the Consultant Team. This would include Austin Associates line and level of the services and any architectural input required to establish the co-ordinated drawings, such as reflected ceiling drawing and any other drawing by the Architect or the structural engineer that had a bearing on producing the co-ordinated drawing.
It is noted under Item 2.1 that there is a comment raised about solution of clashes to be shown on Taymech's highlight drawings. We would correct this situation. The solution of clashes is the responsibility of Austin Associates and the drawings that are to be issued with resolutions on are not Taymech highlight drawings but are, in fact, Austin Associates revised co-ordinated drawings.
It is, therefore, the requirement of the Joint Venture that all reference to so called Taymech highlight drawings are removed from the Minutes, as the Joint Venture does not accept that any drawings that have resulted out of clashes and resolutions of clashes on the co-ordinated drawings are anything other than revised Austin Associates co-ordinated drawings. We would be obliged if you would revise your Minutes to reflect this contractual requirement.
In connection with this we would also draw your attention to Clauses in the General Specification which clearly require the Joint Venture to notify Austin Associates of any clashes on their drawing and wait for rectification of the clashes on the Austin Associates drawings by Austin Associates, before progressing their work, their drawing work or site installation.
With regard to the flow of information, as raised in Item 7, it is necessary to once again make the point that the information flow requirements are contained on the P3 M & E agreed Programme. Much of this information requirement shown on the Programme is now late and the Joint Venture would be pleased if this point could be noted, particularly as the Joint Venture are using their best endeavours to accommodate this late information flow and, albeit, that information flow programmes have been shown subsequent to the Main Programme, they are merely representing the results of the initial late flow of information from the Consultant Team.
Referring to Item 13.1 in the Minutes, we would express our extreme concern with the Architect's comments in this Minute, particularly as the Architect appears to be taking the Joint Venture to task for failing to put into the so-called co-ordinated drawings further information from the Architect's drawings.
We would remind you that the co-ordinated drawings are supposed to be co-ordinated using all of the required information from the Consultant Team, from whatever source it is necessary to obtain it within the Consultant Team.
It would appear, from the Minutes and from letters since received from the Architect, that we are being instructed to feed further Architectural and structural information into the co-ordinated drawings to obtain co-ordination. Clearly this is a situation which proves that the drawings were not co-ordinated and that the information the Architect is requesting to incorporate in the revised Austin Associates co-ordinated drawings is, in fact, late information flow.
It is, therefore, not surprising that clashes are being seen on the co-ordinated drawings (such as light grilles and fittings) if the co-ordinated drawings never benefited from the input of the Architects and Engineers information in the first place. We would, once again, remind you that this should have happened prior to the issue of the so-called co-ordinated drawings.
We would be obliged if you would revise your Minute Report to include the comments raised by the Joint Venture members of the meeting and possibly a footnote with regard to the Architect's comment as a post-meeting footnote.
Your attention to these points would be much appreciated.
It is also noted that no Minute has been reported in the Site Meeting Minute with regard to the Joint Venture's comments reference Taymech's letter and Taylor Woodrow Construction's letter of the 7 January concerning the late information with regard to Boiler House Hotwell, Boiler Deaerator, Path Lab Air Supply Unit, Fume Cupboards and Safety Cabinets.
It must also be noted in the Site Minutes the points raised with regard to the Consultants (Austin Associates) holding meetings with the Joint Venture manufacturers, suppliers or sub-contractors without notifying the Joint Venture.
We would also require minuted that it was established during the course of this discussion that problems have already arisen with regard to instructions being given to suppliers at unofficial meetings by Austin Associates and that the meeting clearly took the decision that in future no meetings would be held with the Joint Venture suppliers, manufacturers or sub-contractors with the Consultants unless they were convened by the Joint Venture, attended by the Joint Venture and held on site.
These points were raised by the Joint Venture at the meeting and prior notification was given to the meeting. Will you please amend the Minutes accordingly."
In a further letter of 21 January 1988 TW also said:
"We must write and record our extreme disappointment with the Minutes of the meeting held on the 11th January 1988 at 2.00 PM in the PMI Sydney Street Project Office to discuss the drawing situation (Taymech/Austin Associates).
From the writer's reading of the Minutes it would appear that much of what was said has not been reported.
"We would particularly remind you of the Joint Venture's clear statements with regard to the production of the drawings and that the drawings that were being put through the WOCAD system were Austin Associates co-ordinated drawings and that these drawings were having to be fed through the WOCAD system to establish what clashes existed on these drawings for resolution by Austin Associates.
It was also pointed out at the meeting [on 11 January] that the need to use WOCAD was entirely as a result of Austin Associates co-ordinated drawings being not truly co-ordinated and exhibiting many problems.
It was further pointed out at the meeting by the Joint Venture that they could not be considered co-ordinated drawings until such times as all the problems and clashes of the co-ordinated drawings had been resolved. This would appear to be when WOCAD makes the final run on any given drawing incorporating all of the resolutions by WOCAD as well as a considerable quantity of late information input to the co-ordinated drawings by the Architect."
"Under Clauses 5.2, 5.4 and 7 of the Contract Conditions, the Joint Venture should be provided with Co-ordinated Drawings and other Drawings showing the levels required of the various services to enable them to install and complete the Works. It follows that the information on these drawings should be correct and in sufficient detail to enable us to produce our Installation Drawings. There is no responsibility under the Contract for us to check the Co-ordination Drawings supplied, only to check our Installation Drawings against the Co-ordinated Drawings to see that clashes do not occur.
Under Clause 2.3 of the Contract Conditions we have a responsibility to draw your attention to any discrepancies that become apparent between the Contract Bills and Contract Drawings, there is however, no responsibility to check the Drawings issued to us until such times as we are ready to prepare our Installation Drawings.
In the spirit of co-operation we have proceeded with advance checking and employed WOCAD to do this work as with no levels being shown on the drawings other that some undimensioned sections it was proving too excessive for this to be done manually. This is in excess of that required by the Contract Conditions.
We are now in the situation where the Joint Venture is being blamed for the delays in the production of Co-ordinated Drawings and in consequence of this its Installation Drawings.
The writer must also remind you that it was clearly pointed out at the meeting by the Joint Venture that the co-ordinated drawings are Austin Associates drawings, will always be Austin Associates drawings and at no time are they Taymech/Joint Venture drawings. These facts are clearly set out in the Terms and Conditions of the General Specifications for the M & E Services and the General Specifications of the Main Contract.
We would be obliged if you would clearly report these comments as they were raised by the Joint Venture.
With regard to Item 2.1 we would, once again, point out that the issue of co-ordinated drawings is the responsibility of Austin Associates as a member of the Consultant Team and that it is clearly shown in the documentation (General Specification M & E) that the only line and level required by the Joint Venture is on working drawings. It should be therefore, be noted that at no time is the Joint Venture required to put line and level on Austin Associates co-ordinate drawings.
From these facts it is clearly established that the co-ordinated drawings are issued by Austin Associates to the Joint Venture and should by this time have received the input of all the necessary information for the drawing to be a co-ordinated drawing and that all the information to establish the co-ordinated drawing at this point is clearly the responsibility of the Consultants and the Consultant Team. This would include Austin Associates line and level of the services and any architectural input required to establish the co-ordinated drawings, such as reflected ceiling drawing and any other drawing by the Architect or the structural engineer that had a bearing on producing the co-ordinated drawing.
It is noted under Item 2.1 that there is a comment raised about solution of clashes to be shown on Taymech's highlight drawings. We would correct this situation. The solution of clashes is the responsibility of Austin Associates and the drawings that are to be issued with resolutions on are not Taymech highlight drawings but are, in fact, Austin Associates revised co-ordinated drawings.
It is, therefore, the requirement of the Joint Venture that all reference to so called Taymech highlight drawings are removed from the Minutes, as the Joint Venture does not accept that any drawings that have resulted out of clashes and resolutions of clashes on the co-ordinated drawings are anything other than revised Austin Associates co-ordinated drawings. We would be obliged if you would revise your Minutes to reflect this contractual requirement.
In connection with this we would also draw your attention to Clauses in the General Specification which clearly require the Joint Venture to notify Austin Associates of any clashes on their drawing and wait for rectification of the clashes on the Austin Associates drawings by Austin Associates, before progressing their work, their drawing work or site installation.
With regard to the flow of information, as raised in Item 7, it is necessary to once again make the point that the information flow requirements are contained on the P3 M & E agreed Programme. Much of this information requirement shown on the Programme is now late and the Joint Venture would be pleased if this point could be noted, particularly as the Joint Venture are using their best endeavours to accommodate this late information flow and, albeit, that information flow programmes have been shown subsequent to the Main Programme, they are merely representing the results of the initial late flow of information from the Consultant Team.
Referring to Item 13.1 in the Minutes, we would express our extreme concern with the Architect's comments in this Minute, particularly as the Architect appears to be taking the Joint Venture to task for failing to put into the so-called co-ordinated drawings further information from the Architect's drawings.
We would remind you that the co-ordinated drawings are supposed to be co-ordinated using all of the required information from the Consultant Team, from whatever source it is necessary to obtain it within the Consultant Team.
It would appear, from the Minutes and from letters since received from the Architect, that we are being instructed to feed further Architectural and structural information into the co-ordinated drawings to obtain co-ordination. Clearly this is a situation which proves that the drawings were not co-ordinated and that the information the Architect is requesting to incorporate in the revised Austin Associates co-ordinated drawings is, in fact, late information flow.
It is, therefore, not surprising that clashes are being seen on the co-ordinated drawings (such as light grilles and fittings) if the co-ordinated drawings never benefited from the input of the Architects and Engineers information in the first place. We would, once again, remind you that this should have happened prior to the issue of the so-called co-ordinated drawings.
We would be obliged if you would revise your Minute Report to include the comments raised by the Joint Venture members of the meeting and possibly a footnote with regard to the Architect's comment as a post-meeting footnote.
Your attention to these points would be much appreciated.
It is also noted that no Minute has been reported in the Site Meeting Minute with regard to the Joint Venture's comments reference Taymech's letter and Taylor Woodrow Construction's letter of the 7 January concerning the late information with regard to Boiler House Hotwell, Boiler Deaerator, Path Lab Air Supply Unit, Fume Cupboards and Safety Cabinets.
It must also be noted in the Site Minutes the points raised with regard to the Consultants (Austin Associates) holding meetings with the Joint Venture manufacturers, suppliers or sub-contractors without notifying the Joint Venture.
We would also require minuted that it was established during the course of this discussion that problems have already arisen with regard to instructions being given to suppliers at unofficial meetings by Austin Associates and that the meeting clearly took the decision that in future no meetings would be held with the Joint Venture suppliers, manufacturers or sub-contractors with the Consultants unless they were convened by the Joint Venture, attended by the Joint Venture and held on site.
These points were raised by the Joint Venture at the meeting and prior notification was given to the meeting. Will you please amend the Minutes accordingly."
" .We do not accept that this is the correct position under the Contract and therefore give you formal notice under Clause 25.2.1.1 that there is a delay to the Contract due to us not having received the necessary drawings, details and levels as set out in Clause 25.4.6 of the Contract Conditions. In accordance with Clause 25.2.2 we would inform you that at the present time we estimate the delay to be in the region of 38 weeks.
We further give notice under Clause 26.1 that we shall seek [illegible] due to the matters contained in Clause 26.2.1 of the Contract Conditions due to the disruption likely to be cause, due to the delay, as well as the costs incurred due to the employment of additional draughtsmen and WOCAD in trying to obtain drawings without clashes to that we could prepare our Installation Drawings.
We would suggest a meeting between the Design Team and the Directors of the Joint Venture be convened in order to discuss [illegible] ..issues on the present state of the Contract and our operations overall.
We would suggest that the meeting is arranged for either Monday 8 February am or Thursday 11 February PM.
Please confirm by return if either of these dates are suitable.
That letter was certainly notice under clauses 25 and 26 of the contract conditions, but the estimate of delay of 38 weeks was obviously a conjecture. In my view had the preceding letters each stood alone, each would also have been plainly notices under clauses 25 and 26. (For example, WGI's view, albeit somewhat flawed, of the delay caused by late and inadequate information was of the order of 16 weeks.)
"In hindsight it is obvious to me that they were unable to produce meaningful drawings. The difficulty at the time was whether we carried on using the CAD system which created just the same difficulties as we had encountered previously manually. So we tried manually -- they could not do it -- and we tried it with the CAD, and we could not do it. And it really did not matter which method we followed. The crux of it was that the information was not there for either system of producing drawings."
In the circumstances, whilst the use of WOCAD fell within TW's sphere of risk under its contract with RBH, I am not satisfied that it would have used WOCAD had AA complied with its obligations towards RBH. There was correspondence with WOCAD blaming them - see for example Mr Hyde's letter of 7 March 1988, his memorandum of the same day and his evidence about it. That letter followed criticism by Mr Hyde, Mr Barrett and Mr Honey who had been alarmed at the quality of WOCAD's work. Undoubtedly WOCAD did not live up to the expectations that it had engendered but I do not accept that TW in some irresponsible manner went ahead with WOCAD knowing that WOCAD would be unable to highlight clashes automatically. I now turn to the issue of quality of the M&E drawings.
Quality of M&E Drawings
"The co-ordination drawings give less information than could reasonably be expected. In particular, being neither dimensioned nor shown on a grid, they fell short of the definition given in HN(78)(6) on which the engineers' commission was based. (paragraph 1.7)
and (paragraph 4.2):
"The co-ordination drawings provided by Austin Associates fell short of the requirements of HN78(6) in that they were undimensioned.
It is our opinion that more and better referenced co-ordinated sections should have been provided.
It is also our opinion that it was unreasonable to make the contractor responsible for ensuring that arrangements paid the necessary regard to the needs for servicing, maintenance and replacement."
This report fortified Mr Hutchings' belief that AA was wrong to reject TW's criticisms of its work, a view shared by PMI. However WGI initially did not consider that TW was justified in its claims under clauses 25 and 26 of the JCT conditions for extensions of time and the payment of additional loss or expense on the grounds of late and inadequate information. TW therefore felt that it should obtain an authoritative independent report. In September 1990 Mr Hall got in touch with BSRIA (The Building Services Research and Information Association) which provides expert services in relation to many aspects of construction and the building services industry. The BSRIA report 65120/1 of October 1990, concluded that AA's drawings did not constitute co-ordination drawings as defined in the DHSS conditions and in that respect supported TW's case for late and inadequate M&E information and that the M&E co-ordination information issued by AA was inadequate. TW submitted the report to WGI in March 1991 together with its answer to WGI's rejection of its claims. The report was written by Mr C.J. Parsloe who was the author of BSRIA Technical Note TN 8/94: "The Allocation of Design Responsibilities for Building Engineering Services - a code of conduct to avoid conflict." The report included the following conclusions:
" on the information provided, it is our assessment that the designer's drawings do not constitute co-ordination drawings as defined in the DHSS conditions. The drawings fail to meet two of the requirements of the definitions for co-ordination drawings.
Firstly the number of sections given on the drawing are insufficient to adequately show 'the inter-relationship of two or more engineering systems' in all areas where it would be reasonable to expect such information to be given.
In addition, the drawings fail to meet the requirement that:
'the clarity of the drawings shall be such that the Contractor/sub contractor(s) may use them for construction purposes'.
The additional information needed to enable the co-ordination drawings to be used as installation drawings is considerable.
It would not have been possible to produce installation drawings from the designer's layouts without further information.
" the true test of AA's co-ordination drawings is whether the contractor was able to use the AA drawings for construction purposes without difficulty".
Mr Tyler when asked whether he agreed that this was the correct test would say only, and then somewhat grudgingly, that it was "not unreasonable". Both the answer and the manner in which it was given told me much about AA's attitude to its obligations to its client and to a contractor. Mr Mackenzie also agreed, making the obvious point in relation to draughting conventions that not every error was culpable:
"Q. .In relation to the positions of services relative to each other, I imagine you would accept that co-ordination drawings should show clearly where services cross, which one is on top and which is below?
A. They should show that, yes.
Q. And that is done by the use of established drafting conventions, in particular indicating the one below in dotted lines?
A. Yes.
Q. Mr Mackenzie, at any point where services cross, one should be able to tell immediately from a properly prepared co-ordination drawing which service is on top?
A. One should be able to do that.
Q. Immediately; just looking at it straightaway?
A. Yes, but I had not seen, I think, many drawings in my life that do not have any errors of that nature on them.
Q. Yes, I am sure, Mr Mackenzie, that must be so. Nobody is suggesting that drawings have to be error-free. It is a question of the degree of these things; you understand?
A. Yes."
Under AA's contract with RBH the Supplementary Annexure to the ACE conditions gave AA the following obligations:
"1.1 The Consulting Engineer shall, if so requested by the Client, undertake responsibility for Co-ordination of Engineering Services designed by the Consulting Engineer and for the provision of Builders Work Information associated therewith.
(a) collaborate fully with other professional advisers appointed by the Client;
(b) collaborate with the appointed Architect, in the particular case of disposition of user outlets and environmental terminals, in accordance with procedures agreed by the Client provided that such procedures be neither more complex nor more comprehensive than those defined in Appendix B hereto;
(c) prepare Co-ordination Drawings and such other documentation as may be required in the opinion of the Consulting Engineer to fulfil his design responsibility;
(d) provide the Builders Work Information necessary in the opinion of the Consulting Engineer to enable detailed structural provision to be made by others for the engineering services designed by the Consulting Engineer."
His Honour Judge Hicks QC held ([2000] BLR 79) that it was the common intention of RBH and AA that co-ordination drawings would be provided to the contractor and, conversely, that there was no common intention that the specification for the M&E works would contain provisions placing the responsibility for co-ordination of M&E services on the contractor.
"1. The following headings and definitions as set out in the "Annexure to ACE Model Form of Agreement D" (the "Hospital Annexure" HM(67)7) shall be retained for the purposes of this Supplementary Annexure:-
DEVELOPMENT PLAN
DEVELOPMENT CONTROL PLAN
OUTLINE SKETCH DESIGNS
SKETCH DRAWINGS
PRELIMINARY DRAWINGS FOR ENGINEERING SERVICES
(a) CO-ORDINATION shall mean the provision of information clearly showing the inter-relationship of two or more engineering systems and, where appropriate, the physical or spatial relationship of the components of engineering systems to the remainder of the Project. This information will normally be provided in the form of Co-ordination Drawings.
(b) CO-ORDINATION DRAWINGS shall mean drawings prepared with intent to show clearly the inter-relation of two or more engineering or public health systems.
The clarity of the Co-ordination Drawings shall be such that the Contractor/Sub-contractor(s) may use them for construction purposes although it is recognised that the provision of Installation Drawings may be necessary.
The drawings shall be prepared to a scale of not less than 1/50 and shall depict the services in their allotted and co-ordinated position using conventional semi-diagrammatic style.
Where any dimension in cross-section is 150 mm or more, duct-work, electrical trunking and pipe work shall be shown in double line. Drawings shall demonstrate that adequate space has been made available for access and maintenance.
The use of drawings having a superimposed grid and an associated convention for the indication of actual positions of ductwork and piping in relation to the grid may be used to reduce the necessity for dimensions.
Additional drawings to a scale of 1/20 may be prepared to amplify detail in certain areas of the Co-ordination Drawings if, in the opinion of the Consulting Engineer, these are necessary for clarity. Similarly, sketch details may be prepared to indicate typical arrangements, or repetitive assembly details eg trap sets, PRV sets, heater or calorifier connections. These need not necessarily be to scale and will be issued as a guide to installation only.
Note: The drawing requirements for co-ordination purposes will vary from project to project and it is not possible therefore wholly to define the appropriate provision in terms of numbers, extent and service groupings.
(c) BUILDERS WORK INFORMATION shall mean documentation prepared to show requirements for work of a structural nature which is required to be carried out to facilitate the execution of the Works.
The Builders Work Information shall provide the Architect with the information to instruct the Contractor to carry out the Builders Work in connection with the Works except insofar as detail of minor items may not be available in default of issue of Authorised or Certificated drawings by manufacturers prior to firm orders being placed.
Full information shall be provided to illustrate the basic structural requirements associated with the engineering services eg lift shafts, chimneys, flues, sumps, ducts, holes above 150mm round or rectangular, sleeves of all sizes in RC or other structural members and access requirements wherever necessary.
Drawings of floor and wall ducts, chases and holes in RC or other load-bearing work, fixtures involving building trades and dimensioned details of bases etc for all plant items, with imposed structural loads shall be prepared.
Requirements for any abnormal builders attendance such as scaffolding and hoisting facilities shall be scheduled.
(d) INSTALLATION DRAWINGS shall mean drawings prepared, for approval by the Consulting Engineer, showing details of proposals for the execution of the Works.
Such drawings shall include fabrication details for manufactured plant and equipment, including pipework, ductwork and brackets or supports where site measurement is implicit to the fabrication process.
Drawings illustrating erection procedures fall into this category, as appropriate, as do conduit layouts for electrical and communication services and such specialist wiring diagrams as are necessary to demonstrate that control and other systems meet the specification.
Similarly, drawings and information for builders works which have no structural implications, small holes less than 150mm round or rectangular, bracket fixings and the like are erection orientated and should be so provided."
"The wording at Definition 3(b),"The clarity of the Co-ordination Drawings shall be such that the Contractor . . . may use them for construction purposes", did not mean that the clarity of the co-ordination drawings should be such that the contractor should be able physically to construct the works by reference to those drawings alone. On its true interpretation it meant that the co-ordination drawings should be clear enough for the Contractor to use them, with other relevant information, to prepare installation drawings as necessary (and as required by clauses B1:03:08, B1:03:18, and B1:04:15-16 of the Specification) in order to physically install the works. In other words, it was not AA's duty to prepare co-ordination drawings in such manner as to make it unnecessary for the contractor to prepare installation drawings. If the contractor was not able to proceed directly from AA's co-ordination drawings to actual installation, that does not mean that AA were in breach of obligation. "Other relevant information" does not include information that should be shown on co-ordination drawings.
(Note:
The Claimant does not contend that Taylor Woodrow/Taymech should have been able to install the works directly from AA's co-ordination drawings, i.e. without preparation of installation drawings by Taylor Woodrow/Taymech. Nor does it contend that Taylor Woodrow/Taymech should have been able to prepare installation drawings by using only the information on AA's co-ordination drawings. The Claimant to re-word the first sentence of paragraph 54.2 of Statement of Claim accordingly.)"
AA made the point that the general allegations in paragraph 54.2 of the RASC had to be considered in the light of more specific allegations in paragraphs 55.1 (38 co-ordination queries raised by TW), 55.2 (729 clashes and/or errors alleged by TW) and 58 (clashes during installation alleged by TW), but the effect of the particulars given was that RBH relied on the clashes or queries listed in paragraphs 55.1, 55.2 and 58.
"our drawings indicate the design intent but do not show sufficient detail for installation purposes without additional detail being added".
In a letter of 3 February 1988 AA said:
"Our co-ordination drawings have been produced to indicate the relationship of one service with another, i.e. either above or below, or to which side. There is no requirement that they should be produced with line and level as suggested by the Contractor."
Again on 10 October 1990 AA said in another letter (also written by Mr Robert Edwards):
"The Health Note allows the Consulting Engineer to apply an appropriate interpretation for the particular project, which in this instance was to place TWC under contract to prepare Installation Drawings of all services showing their intentions for precise line and level of Services."
The letter also said:
". . . our intent has always been that multi-service co-ordination drawings would be issued to show the general arrangement, which are diagrammatic in certain particulars, and the Contractor was to prepare Installation Drawings showing his proposed detailed arrangement of services and precise Line and Level. The contract specification is written in that manner."
These letters are however consistent with AA's approach from the start of TW on site, if not earlier. Mr MacKenzie accepted that AA had to provide full information about "holes above 150mm round or rectangular" (see above) but in March 1987 AA refused to provide CNM with that information relating to the locations of ducts or the holes for sumps in the level 1 reinforced concrete ground floor slab, even though AA had made Genever responsible for providing this information in their contract. Later AA did not provide and then provided the wrong information about the locations of the holes for the radiators through the RC slabs as they said all builder's work holes were TW's responsibility. Mr Tyler tried to brush this incident aside when he was asked about it, but it seems to me to provide a useful example of AA's double standards. (Holes return when I consider disruption to the blockwork.) Clearly the information was to be provided by AA so it was left to Genever to do so and the latter's claim for additional payment was rebuffed whilst at the same time AA was maintaining that TW was also responsible for details of this kind. In addition, and relevant to the timing of the co-ordination drawings was AA's failure to provide invert levels on the drainage drawings for levels 2-6 when they were issued "For Construction" in April 1987, as a result of which it had to be done later by Genever (in July) with marked reluctance . Since Mr Tyler accepted that levels were known earlier and that it was Genever's job to include them the reason why AA did not give them to Genever is inexplicable (and Mr McKenzie could not provide a technical reason). It could have been to avoid conceding to TW that it was not the latter's responsibility. Thus the reason why the co-ordination drawings for the next most critical level (2) were not issued until 7 September (level 3 on 18 September) was because AA failed to enable Genever to do so in time (as Mr Mackenzie effectively admitted). Yet at the meeting AA led TW to believe that the drawings would be issued on the dates given. AA's reliance on the change in the depth of the ceiling voids between levels 1 and 2 and between 2 and 3 is misplaced. The drainage drawings with the changed invert levels should have been issued at the beginning of April but were not issued for level 1 until about 1 May 1987.
"The use of drawings having a superimposed grid and an associated convention for the indication of actual positions of ductwork and piping in relation to the grid may be used to reduce the necessity for dimensions."
Co-ordination plan drawings showed the relationship of the various individual services along their routes. Co-ordination section drawings showed the relationships of the individual services as "layered" above the suspended ceilings on each floor. The level of each service would generally be determined by AA by scaling from the sections, which were positioned in plan in relation to the structural grid, and using the ceiling and structural floor levels detailed on the architect's and structural engineer's drawings and invert levels on the drainage drawings. The exact levels could not be finally determined until the contractor had established his equipment, fabrication and fixing details etc. Hence the need for development of the consultant's co-ordination drawings into installation drawings. According to AA, the installation drawings prepared by TW were to amplify and finalise the Design Team's drawings issued for construction (particularly in respect of items subject to open tender, as was the case here, and to suit fabrication and fixing details, installation sequence). These show the layout of each service in plan, and that same information should be on the co-ordination drawings.
"The result has been, subject to one important exception, to assimilate the way in which such documents are interpreted by judges to the common sense principles by which any serious utterance would be interpreted in ordinary life. Almost all the old intellectual baggage of 'legal' interpretation has been discarded. The principles may be summarised as follows.
(1) Interpretation is the ascertainment of the meaning which the document would convey to a reasonable person having all the background knowledge which would reasonably have been available to the parties in the situation in which they were at the time of the contract.
(2) The background was famously referred to by Lord Wilberforce as the 'matrix of fact', but this phrase is, if anything, an understated description of what the background may include. Subject to the requirement that it should have been reasonably available to the parties and to the exception to be mentioned next, it includes absolutely anything which would have affected the way in which the language of the document would have been understood by a reasonable man.
(3) The law excludes from the admissible background the previous negotiations of the parties and their declarations of subjective intent. They are admissible only in an action for rectification. The law makes this distinction for reasons of practical policy and, in this respect only, legal interpretation differs from the way we would interpret utterances in ordinary life. The boundaries of this exception are in some respects unclear. But this is not the occasion on which to explore them.
(4) The meaning which a document (or any other utterance) would convey to a reasonable man is not the same thing as the meaning of its words. The meaning of words is a matter of dictionaries and grammars; the meaning of the document is what the parties using those words against the relevant background would reasonably have been understood to mean. The background may not merely enable the reasonable man to choose between the possible meanings of words which are ambiguous but even (as occasionally happens in ordinary life) to conclude that the parties must, for whatever reason, have used the wrong words or syntax (see Mannai Investment Co Ltd v Eagle Star Life Assurance Co Ltd [1997] 3 All ER 352; [1997] 2 WLR 945.
(5) The 'rule' that words should be given their 'natural and ordinary meaning' reflects the common-sense proposition that we do not easily accept that people have made linguistic mistakes, particularly in formal documents. On the other hand, if one would nevertheless conclude from the background that something must have gone wrong with the language, the law does not require judges to attribute to the parties an intention which they plainly could not have had. Lord Diplock made this point more vigorously when he said in Antaios Cia Naviera SA v Salen Rederierna AB, "The Antaios" [1985] AC 191 at 201:
' if detailed semantic and syntactical analysis of words in a commercial contract is going to lead to a conclusion that flouts business common sense, it must be made to yield to business common sense.'
Lord Hoffmann's reference to Mannai Investment Co presumably includes what he said ([1997] 3 All ER 352 at page 380):
"In the case of commercial contracts, the restriction on the use of background has been quietly dropped. There are certain special kinds of evidence, such as previous negotiations and express declarations of intent, which for practical reasons which it is unnecessary to analyse, are inadmissible in aid of construction. They can be used only in an action for rectification. But apart from these exceptions, commercial contracts are construed in the light of all the background which could reasonably have been expected to have been available to the parties in order to ascertain what would objectively have been understood to be their intention: see Prenn v Simmonds [1971] 1 WLR 1381 at 1383. The fact that the words are capable of a literal application is no obstacle to evidence which demonstrates what a reasonable person with knowledge of the background would have understood the parties to mean, even if this compels one to say that they used the wrong words. In this area, we no longer confuse the meaning of words with the question of what meaning the use of the words was intended to convey."
Whether or not it is to be derived from ICS Mr Bartlett is right in his submission that the contracts are to be read not with literalism, but with an understanding of the practical background and the realities of the work involved and that in interpreting, or, rather, applying, the definition of co-ordination drawings in the Supplementary Annexure, the views of responsible engineers on what proper co-ordination drawings should be like in practice may be helpful. Those views, even if unanimous, cannot of course be decisive if the contract is not capable of being so read.
" the provision of information clearly showing the inter-relationship of two or more engineering systems and, where appropriate, the physical or spatial relationship of the components of engineering systems to the remainder of the Project".
It then makes the valid, if obvious, point that responsibility is a skein divided between architect, consulting engineer and contractor and varies from project to project "dependent upon whether the Consulting Engineers have had their appointments extended to include the duty of preparing co-ordinated drawings". It patently cedes place to the contract in question and cannot be used to interpret it. It refers to standard terms of appointment and in Mr Bartlett's submission set out "the understanding of consulting services engineers concerning the nature of their task when their duties under Form D were extended by the Supplementary Annexure (as happened in the present case)". I do not consider that ICS authorises the interpretation of a standard form by reference to the views of the organisation that published it, when, necessarily, those views are not consistent with the form itself. Standard forms are documents which are proffered by professional and other bodies as conditions which can be safely used by the inexperienced client (as well as by experienced clients) and have to be read without regard to the assumed interests of their proponents, even where they do not represent the product of potentially differing interests (e.g. the JCT, ICE, or I.Mech.E/IEE standard forms). In my view for that reason alone it is not permissible to refer to it. In addition, although the ACE Conditions (as amended) were incorporated in the contract with RBH, they were expressly subject to the directives specified and other directives. Clause 2(A) concluded: "In the event of any conflict between the provisions of Form D and this Agreement the latter shall prevail", i.e. the other provisions and the other documents referred in the Agreement (see the annexe to this judgment). However it has importance in that it shows that whilst as a matter of practice the ACE considered that under the ACE conditions a Building Services Engineer such as AA is basically "responsible for ensuring that co-ordination of those services which he designs is practicable" but that if
"appointed to undertake the preparation of fully co-ordinated drawings as an additional duty (i.e. by the PSA or DHSS, in accordance with special agreements, or by a private client agreement in similar circumstances) it becomes his responsibility to produce drawings to illustrate the practicability of inter-service co-ordination. (NB these are not working or installations drawings see definitions in special Agreements)."
Thus whereas final positions would not be required to be shown under general practice they could well be required by a specific agreement (as Mr Dix rightly, was in my view pointed out by his reference to the Supplementary Annexure, when asked about it.) It therefore recognises that the general M&E practice is subject to the terms of the appointment in question a point that Mr Dix made when questioned about it . If anything, therefore, as a statement of general and applied practice it supports RBH's case, and not AA's case.
"The clarity of the Co-ordination Drawings shall be such that the Contractor/Sub-contractor(s) may use them for construction purposes although it is recognised that the provision of Installation Drawings may be necessary.
The drawings shall be prepared to a scale of not less than 1/50 and shall depict the services in their allotted and co-ordinated position using conventional semi-diagrammatic style."
Furthermore I do not consider that the ACE Guidance Note should be regarded as a document which needs to be examined to understand AA's agreement which is already long and seemingly comprehensive and, by referring to other similar documents, contains all that is needed to make sense of it. So, although paragraph 3(b) does not in itself draw a clear line between the information to be provided on the engineer's co-ordination drawings, and those on the contractor's installation drawings, that line can be found once the remainder of the Supplementary Annexure (and other documentation) is looked at, such as paragraph 3(d) which, when its opening is read with what follows, effectively redefines para 3(b) by stating what a co-ordination drawing need not provide. Mr Dix said in cross-examination (at the end of a set of instructive and rational answers) that he did not think that statement was a better one: "That is what we work with within the industry".
"Similarly, drawings and information for builders works which have no structural implications, small holes less than 150mm round or rectangular, bracket fixings and the like are erection orientated and should be so provided."
When these provisions are read with the earlier paragraphs it is clear that these definitions mean, first, that the consultants have to provide drawings which show services which are capable of being constructed in the space or areas in question and do not clash with the structure or other services; secondly, that the drawings have to be sufficiently dimensioned that they can be used by the contractor to construct the services; thirdly, that installation drawings may only be needed for the final details of the works especially where they are dependent on information for which the contractor is solely responsible. The second conclusion is obvious from the reference to the use of "a superimposed grid and an associated convention for the indication of actual positions of ductwork and piping in relation to the grid to reduce the necessity for dimensions". Thus dimensions will be required, i.e. "line and level", not intended positions or schematic positions (as Mr Dix pointed out). This in turn shows what is practice is meant by the opening paragraph which defines co-ordination as providing information which clearly [my emphasis] shows "the inter-relationship of two or more engineering systems and, where appropriate, the physical or spatial relationship of the components of engineering systems to the remainder of the Project" [my emphasis]. TW had of course obligations to produce installation drawings with dimensions and levels. For example clause 1:04:16 of the M&E Specification (see annexe to judgment) states:
"The Contractor shall be responsible for the preparation of all fully dimensioned drawings of standard at least equal to, and of a scale sufficient to indicate to the Engineer, installation details of the following.
Layout drawings indicating all plant, equipment and pipework that is to be installed giving lines, levels and positions of equipment.
All plant rooms and works therein.
All ventilation ductwork and fittings.
Shop drawings of all manufactured and fabricated items and equipment.
".
"This clause states 'their allotted or co-ordinated positions'. I understand this clause to mean that they should be shown in the actual intended positions. Without the use of dimensions it should therefore be possible to scale off the drawings to an accuracy of ±50 mm or less. I do not take the term semi-diagrammatic to imply that the positions are semi-schematic, or semi-accurate. The term 'semi-diagrammatic' refers to the essential draughting freedom needed to depict the layouts clearly, using accepted draughting conventions."
"In practice, building services design is not a discrete activity with neatly defined edges carried out by a single company or individual, but is more typically an evolving process to which professional designers, specialist designers, manufacturers, installation managers and site tradesmen might contribute ...
Responsibility for some element of design is normally allocated to the installing contractor via an instruction that they produce drawings ..."
Mr Bartlett was right in saying that in practice on a project of this kind installation drawings by the contractor would almost certainly be needed, but not so as to do the work which ought properly to be done by the consultant.
"However, if the designer has been appointed to carry out a full design including spatial co-ordination, then the amount of design responsibility allocated to the installer will be minimal, possibly extending no further than that for supports and fixings."
In any event in the absence of some reasonably clear provision in the contract (e.g. where the contractor is left to decide how to meet certain performance requirements and is given the freedom to do so, such as where the choice of plant or equipment is left or left initially to it), a contractor working under the standard JCT contract conditions is basically not responsible for the conceptual or functional design, i.e. for the fitness of the work or services (unless selected by it), or the practicability of accommodating services (for example from the point of view of accessibility for maintenance). Mr Dix rightly said: "if you enter into a dispute whereby the services will not fit, then I do not think it is the responsibility of the contractor to resolve that issue"..
" .the onus on the consulting engineer, I believe, is to demonstrate that the services will fit. Then the contractor may adjust it slightly for his own purposes. If the services do not fit or cannot be made to fit, then I would consider that that was the responsibility of the consulting engineer." [emphasis supplied]
"Preliminary co-ordination drawings for Zones 3, 4 and 5 of Level 1 were issued by AA on the 3rd, 13th and 16th of July 1987 respectively. Upon issue of the preliminary co-ordination drawings two of our draughtsmen set to work to produce working drawings from the information presented. It soon became obvious that the preliminary co-ordination drawings contained insufficient details to enable our draughtsmen to make a meaningful start and the work undertaken by these draftsmen in relation to those drawings was abortive. The problem with the preliminary co-ordination drawings was that they only showed services having been superimposed one on top of another with no indication of the relationship of one service to another. Further, only a minimal number of sections were provided and these had only been provided for lightly serviced points. Apart from the drainage, AA did not provide levels for any of the services."
He explained what was thought to be part of the reason for the situation:
"We believed that the manner in which the co-ordination drawings were being issued indicated that AA were co-ordinating the works on a zone by zone basis rather than on a floor by floor basis. If drawings are co-ordinated on a zone by zone basis and, if when producing a drawing of a zone an internal co-ordination clash arises, the solution devised to overcome that clash may have co-ordination ramifications in neighbouring zones which may not be identified until the services are actually installed."
C. Co-ordination.
All level 1 drawings received to enable Taymech to produce working drawings.
Taymech have identified many areas where major clashes occur, query sheets attached. The time involved in identifying the problems and then the Consultant resolving the same effectively delays the information flow agreed during the meeting with the Consultants of 12th August 1987. This will have a "knock on" effect on Taymech producing working drawings which could affect the programmed start date."
The reference to the meeting should be that of 11 August at which Mr Hall and Mr Walker were presented by Mr Edwards and Mr Hammond with issue dates that AA would meet. As Mr Hall said in his evidence TW had no or insufficient time to produce and get approval for its drawings as AA 's drawings were much less detailed and thorough than TW had expected on 11 August. Mr Drummy said also that, in relation to the electrical services, the drawings issued in mid August
"were co-ordinated in name only, [they] showed the services superimposed over one another and contained a minimal number of sections within the zones. The sections provided showed some co-ordination details but were too few in number and did not show any detail at the corridor intersections, at electrical cupboards or at the services risers (the key areas where space was at a premium and consequently co-ordination was vital). The AA drawings also failed to show the final conduit routes to equipment and accessory positions. I consider that AA should have established the conduit routes in order to calculate the cable size and type relative to the environment in which it was to be installed, the length of route and the effect of the resulting volt drop. It is standard practice for the designer to provide some details of how conduits were to be routed from the soffit down to the electrical trunking, which was at the bottom layer of services in the corridor. AA's drawings failed to show these routes."
Mr Drummy explained in his witness statement and when cross-examined that he was not saying that as regards electrical services the drawings were generally deficient and that he was concerned with the areas of complexity where he expected sections to be given. Later in his evidence he gave examples of earlier conflicts with foul drainage (some of which were not persuasive) and of the need to lower the false ceiling to accommodate the foul drain in zone 4 of level 1 which nevertheless protruded 37mm. Similarly he provided a good further illustration from 1988 of the impossibility of installing some ladder racks required by AA's drawings as there was no room; I agree with Mr Drummy that these were not minor matters. During August TW continued to issue CO queries (and ultimately 38 were issued). CO 10 of 27 August 1987 was examined by the experts. The clashes raised by TW in it have been substantiated by all the experts although there remained disagreement about the weight to be given to them.
"our drawings indicate the design intent but do not show sufficient detail for installation purposes without additional detail being added".
"Two full-time site-based draughtsmen have now spent six weeks in checking the co-ordinated drawings, for zones 3 and 4 only, when producing our own working drawings. This has resulted in the generation of a large number of co-ordination queries. Although we have been using our best endeavours to produce drawings to meet the programme we consider the time now being spent in verifying these drawings in order to produce our own working drawing has now become excessive.
"Our own time allowances for the production of drawings has more than doubled that originally allocated in our estimate. We shall be seeking reimbursement for these additional costs which we will quantify when the full extent is known for zones 2, 3, 4, and 5."
Mr Hall agreed that this letter was correct and that TW had not on 11 August anticipated the sort of problems that it was encountering and that it was taking much longer to turn the drawings round.. In turn, as Mr Hall confirmed, the difficulties about the quality of drawings led to the Review Meetings, the first of which was held at the beginning of September. At the next site meeting TW reported that, although AA had a full time member of staff on site and many queries were being resolved with his help, there were still many outstanding co-ordination problems with the co-ordination drawings and, because more and more co-ordination clashes were being discovered, TW's queries vastly outnumbered the co-ordination responses received from AA who could not keep pace with the rate at which co-ordination problems were being found. Mr Hall's statement also explained the difficulties created for TW by having to issue builder's blockwork drawings based on AA's inadequate co-ordination drawings.
"2.10 I therefore proposed, and AA agreed, to sit our co-ordination engineer and AA's co-ordination engineer down together to resolve the clashes. Sometime in late January or early February 1988 we seconded our co-ordination engineer, Mr Honey, to AA offices to undertake pre-WOCAD investigations into the co-ordination drawings for Level 3. Working drawings for Levels 1 and 2 had either been completed or substantially completed by that date. After completion of this exercise, on the 4th February 1988 Mr Honey and AA's co-ordinator relocated to site to complete the co-ordination exercise. Whilst at the time I did not believe that we had any contractual obligation to produce line, level and dimension information for the drawings . and as AA were at that time rejecting any suggestion from us that this was in fact their obligation, in order to resolve these difficulties at a practical level it still had to be done by somebody.
He summarised the effect:
"2.15 The delay which had previously been experienced in producing the installation drawings for the horizontal services meant that it was not until about April 1988 that resources could be fully allocated to the production of drawings for the riser and plant room areas although the boiler house drawings had commenced in early December 1987. Had the M&E information been provided at the proper time and had it been of sufficient standard then the difficulties experienced in these areas could have been resolved on the drawings at a much earlier stage. As we had installed works to unapproved drawings to mitigate against further delays to the works, when approval was given alterations had to be made on site to works previously installed."
Mr Hyde accepted that TW had in fact received the boiler house drawings in May 1987 but that does not detract from his general conclusion which I consider was entirely justified. AA submitted that TW's failures were illustrated by the boilerhouse drawings, since in part it seems that by 25 June 1987 TW had overlooked their issue and TW had planned to start installation in the level 1 boiler room on 5 October 1987, and did not do so until December. However I am unable to discern the effect of this chain of events. TW's complaint related to being able to get on with all the work; no doubt there were parts that it could not do.
"Whilst throughout the construction industry there are differing views on the exact definition of the term "co-ordination drawings", what I believe is clear and indisputable in relation to all of the co-ordination drawings issued by AA on this project is that, on any definition, they were grossly under co-ordinated and totally inadequate for the purposes of preparing working drawings and builder's work drawings. As I have already mentioned, the other significant and compounding problem was that the co-ordination drawings which AA issued were not only inadequate but were also late. I believe that AA were simply not sufficiently prepared or advanced, in terms of co-ordination of the services, at the commencement of the project. As a result we had to spend the next 12 months assisting AA to co-ordinate their drawings to a state of co-ordination which AA themselves should have achieved at the latest by the 4th of May 1987. It was the extent of the inadequacies (and the lateness of issue) and the extent of the resulting delays and disruption to the works that led to a significant part of the losses now claimed."
This was a trenchant summary of the position. It contains, as did other passages, statements which are too general, e.g. "all of the co-ordination drawings", and later: "all clashes that occurred throughout the works arose because AA failed to properly co-ordinate the services". They were self-evidently hyperbole. In cross-examination Mr Hall agreed that he really meant the majority of clashes were AA's fault. He naturally accepted that there would be other reasons, but it was never clear to me which clashes were due to any of the other reasons suggested so as to rebut the conclusion that the majority were due to AA. I do not accept AA's submission that Mr Hall's evidence was not fair. It contained no more than the usual amount of emphasis that might be expected from a person in Mr Hall's position with his experience and background who had been genuinely surprised at the number of queries created by AA's drawings.
Grids, Dimensions and Sections
"Drawings to a scale of 1:50, with pipes/ducts above 150 mm drawn double-line and pipes/ducts above 50 mm to accurate centre-lines in plan. These should include either critical dimensions or a 300 mm grid to allow measurement of location, or critical dimensions and with inverts, gradients and cross-sections drawn to show levels."
He pointed out that 300 mm grids were to be used if the critical dimensions were not stated on the drawings. It was clear to me that Mr Dix was not of the opinion that a superimposed grid had to be used but it was an option which would achieve dimensioning that was essential. Mr Edwards said that he would have used the structural grid and that he did so in the 1980s. The structural grid was 6750 mm x 7200 mm. It was put to Mr Dix that Mr Mackenzie could not recall any job where the contractor's dimensions were not taken from the structural grid but Mr Dix pointed that a contractor would take the easiest course available and that such a practice was usual on non-Health Service work. Mr Dix rightly pointed out both that the detail required by the Supplementary Annexure work required more and that on AA's drawings the structural grid was barely legible, i.e. there was a lack of the clarity that AA was obliged to provide. He said that it was in any event often an imaginary line between columns whereas the contractor would take a dimension from a wall. In my judgment Mr Dix's reasons, especially under cross-examination, showed that both as a matter of practice and of good practice a superimposed grid was required (or some other means). Since I find that neither was provided AA's drawings were in this respect not of the required quality. Mr Edwards also said in his report:
"The dimensions needed to locate the M&E engineering systems could be scaled on AA's co-ordination drawings and reference could also be made to the chosen grid. I consider that dimensions can be scaled from AA's co-ordination plans (which were drawn at 1:50) to within plus or minus 50mm and from AA's co-ordination sections (which were drawn at 1:20) to within plus or minus 20mm. I consider that these tolerances provide adequate precision for an installer, who is then to prepare the actual installation drawings."
Mr Mackenzie agreed with that statement but said that in fact accuracies of ± 50mm or ± 20mm were not critical and the latter might be tighter than would have been needed. He also agreed that sufficient sections had to be provided to show changes in level for otherwise the contractor would assume that there was no change in the level of a service from that shown on a section, and that any change in level from that shown on a section would have to be approved by the consultant. These answers reinforce the conclusion that I have reached. It must be noted that from November 1987 AA issued a significant number of additional sections and part plans showing, inter alia, dimensions, invert levels and details of sets. An example is at Appendix 7 to Mr Down's report.
176A. Mr Dix produced drawing TRD-01 to demonstrate, amongst other things, where sections should have been shown by AA for zone 4, level 1. It superseded Mr Down's drawing PGD-02 which had formed part of his report and which showed the location of the clashes relied on by TW and to that extent was taken to be an agreed record. Mr Dix did not himself think that the number of sections advocated by Mr Down were all needed and therefore prepared TRD-01 to show where additional sections should be. That drawing showed the two sections provided by AA (in red dotted lines); three other further sections (in green) which were the minimum number of additional sections that Mr Dix thought ought to have been incorporated into the drawings to have provided sufficient information to enable the contractor to have properly located the services; these sections were fewer than those Mr Down had shown as desirable on PGD-02, although two were in the same position as Mr Down's and the third was in a very slightly different position. The point was that less than the minimum number of sections had been provided. Mr Dix did not show optional sections since he did not see the value in littering the drawing with any number of desirable sections, although he did not disagree with Mr Down's view that such sections might have been provided. However RBH no longer relied on PGD-02 for this purpose so it was of historical interest only in understanding Mr Dix's views with which I am concerned. RBH did not maintain that AA was in breach of its contract in not providing such additional sections as they were said only to be desirable. TRD-01 was served early in the trial, and, although then formally objected to, by the time Mr Dix was called, AA had had adequate notice and asked Mr Dix about it. Drawings of this nature are common place in trials of this kind and the parties' advisers have to be ready to deal with them and have to deal even on short notice (in this instance the notice was generous for a party such as AA and its experienced advisers). In my judgment RBH is right in its reason for disposing of AA's objection that RBH should have put forward a set numbers of sections. It is not so much a question of numbers of sections but the clarity of drawing. Mr Dix thought the drawings were unclear. He illustrated that by his choice of sections. Others might have had more. If AA suggested that none was required then I reject it. It is clear to me from the drawings referred to in the evidence and which I examined that there were significant (and not isolated and excusable) areas where there was a real lack of clarity. It is true that in certain instances (match line errors were perhaps the best example) further detailed investigation showed that Mr Dix's original surmise was mistaken (as he readily agreed) but had the drawings been really clearer such false impressions should have been rare; they were not. I do accept that AA's submission that the exercise showed how easy it was to make mistakes when dealing with the detail of drawings. Whether a drawing has the clarity required is a conclusion of fact, informed as it must be here by the views of experts and of those who were there at the time. The latter were in my judgment of one mind: the drawings were unclear. AA provided more and other steps had to be taken to overcome their lack of clarity, thereby meeting TW's complaints (e.g. engineers working along side TW's personnel, the joint, albeit unsuccessful, use of WOCAD). The additional drawings were listed in Appendix 7 to Mr Down's Report. It therefore also followed that the lack of clarity was not made good where ducts and pipes changed level since failures to use draughting conventions properly meant that this was not done, as was demonstrated to me by Mr Dix from TRD-01. He also said, with reason, when taxed on this subject by Mr Bartlett.
Q. An experienced person reading a drawing takes this sort of thing in their stride?
A. You cannot take it in your stride when you do not know whether a duct is going above or below, or a pipework is going above or below. You cannot take that in your stride, because you are left wondering what it is to be.
Q. It is nearly always obvious what the answer is, is it not?
A. No.
Q. And you are making a meal of a lot of trivia, are you not, Mr Dix?
A. No, I am not. The drawings that were produced by AA were extremely difficult to interpret. That is not just my opinion, it is Dr Arnold's opinion, where he states that the drawings have significant inconsistencies, and so do Cundall Johnston."
I do not consider that Mr Dix was "making a meal of a lot of trivia", any more than BSRIA or Cundall Johnston did. He was a highly experienced and balanced engineer. Had there been only a few "trivia" no one would have complained.
"A. No, I would not agree with that. This drawing is -- the intent of this drawing -- what this drawing should have shown, it should have been the drawing that told Taymech where to put the services. It may not have said what size the pipe was, and it may not have said always what it carries, i.e. whether it is a drain, et cetera, et cetera. It was the drawing that Taymech were to use to produce their installation drawings, and to do so they had to interpret this drawing, which is an enormous task. I found it an enormous task, and Dr Arnold found it an enormous task, and Cundall Johnson found it an enormous task."
and
Q. .. Just as a matter of interest, how long roughly did it take to do that analysis of section DD?
A. To ascertain the dimensions off the co-ordinated layout, and compare them with section DD as shown on AA's drawings, it took one of my technicians around about a day to do that and then it took me some half a day to ensure that he had actually got it right because of the degree of difficulty we had in interpreting the drawings."
and
"A. No, you simply cannot understand the level of the ductwork. I know, because I have been through the process myself, and spent many, many hours on the AA drawings. You simply cannot determine the level. You can make assumptions, but assumptions are wrong.
Q. After a short period of familiarisation, Mr Dix, with co-ordination drawings, you build up a three-dimensional picture in your head, do you not, and you start to understand where everything goes, and errors of this kind are then obvious, are they not?
A. No, they are not. You cannot build up a three-dimensional picture if the information is inconsistent and inaccurate.
Q. You would not have any difficulty building up a three-dimensional picture from figure 7, would you?
A. It is a relatively simple drawing. You could not get a complete picture from it, and I guess that there are sections associated with, inferred sections associated with this, I think, that would help. What I am saying is that when you look at the sections of AA's drawings and the plan drawings, you cannot build up a three-dimensional picture. I could not build up a three-dimensional picture, and neither could Dr Arnold."
and
"Q. Have you really tried to be fair to AA, Mr Dix?
A. Of course I have tried to be fair to AA.
Q. Where there were clashes what was required was minor adjustments, was it not?
A. Sometimes, yes.
Q. Generally speaking, yes?
A. Sometimes, yes. As I say, it is very difficult, because until you sit down and analyse the drawings you cannot build up a 3D picture that is necessary. In fact, Taymech should not have had to build up a 3D picture; they should have been able to take AA's drawings on face value and add the information that they needed to add to them to produce installation drawings. That should not have resulted in the relocation of services. It quite clearly did result in the relocation of services and that took an awful long time to resolve."
and
"What I would have expected to have seen are the services moved in a fashion that co-ordination was obvious; that somebody had given some thought to overlaying the pipework and the ductwork such that it meant that maintainability was there and that pipes and ducts missed each other. They clearly did not because there were some 22 agreed clashes from Taymech at this level. And I think we probably identified more on the section DD that we have produced."
"What really matters in most cases is the reasons given for the opinion. As a practical matter a well constructed expert's report containing opinion evidence sets out the opinion and the reasons for it. If the reasons stand up the opinion does, if not, not."
Mr Dix's report was criticised on the same grounds, but in my judgment, without foundation, certainly once his evidence before me is taken into account which left me convinced both that his conclusions had been arrived at rationally, whatever the seeming, but pardonable, brevity of bits of his report, and that his reasoning was valid. To take two of the paragraphs in his first report identified by AA: para 5.10 in fact instances the clashes which justify the conclusion and para 6.5.10 in so far as it contained opinion (since there was also comment which is not relevant) were amply supported by Mr Dix's evidence in court. I was left with the impression that Mr Edwards had relied on the work done by Mr Mackenzie and had not himself investigated the detail for it is not possible to accept conclusions such as the drawings "showed the approximate sizes and positions of pipework and ductwork", without dealing with RBH's case that the positions should not have been "approximate", or explaining the degree of accuracy comprehended and the clashes were "mostly of a minor nature". Mr Edwards' thinking here was almost certainly influenced by the importance he placed on the ACE Guidance Note which, as I have explained, was misplaced both in law and as an indicator of good practice.
"Q. You have not identified any clash that was serious enough to require a major modification either to AA's designs or to the building structure?
A. No. It comes back to this process we were talking about earlier on, that this is a very complex building with a great deal of services, restricted ceiling access and ceiling voids, therefore it would only take minor errors to give rise to significant problems in getting the services into the building.
Q. Mr Dix, the AA co-ordination drawings were adequate for that purpose?
A. They were not."
Q. You have not considered in detail the question of the impact of the queries on the contractor's drawing exercise, have you?
A. No, I formed a view based upon the correspondence, based upon the revised drawings that AA produced, based upon the number of queries, based upon the sketches that AA produced throughout 1987, to resolve those queries, and I formed the view that it must have been extremely difficult for Taymech to have produced proper installation drawings off that information."
"Q: What I am trying to find out, Mr Dix, is why you say you had such difficulty interpreting the drawings; whereas Hoare Lea & Partners' position [Mr Edwards and Mr McKenzie] was that they did not have the same difficulty. Is it because you and they have approached it with different assumptions as to what the drawings were intending to show?
A. I think in the hours and hours that we have spent with Hoare Lea in expert's meetings going through the precise location of services, I think Hoare Lea must have experienced the same difficulty. Because we spent hour upon hour looking at each individual clash. This is the reason why, of course, we did not get through all of the clashes. Time just would not have allowed us to do that because of the difficulty in interpreting AA's drawings with an accuracy that was sufficient for the Court.
Q. You had a different way of looking at them from the way that they had?
A. No, I do not think I did. There is only one way to look at them: you either show the allotted position or you do not show the allotted position.
Q. When you were looking at the clashes, you were in a very different position from the Taymech draughtsmen obviously --
A. I was indeed. I was in a much better position because Taymech had said, "Here are the clashes." Taymech draughtsmen, of course, had to go away and find them.
Q. Well, you were looking at individual points that Taymech had identified as alleged clashes, were you not?
A. Yes.
Q. Whereas Taymech's draughtsmen would be reading the whole drawing, building up a three-dimensional understanding of it and a mental picture of the whole zone in order to produce their installation drawings?
A. I was doing exactly the same.
Q. The nature of the exercise is different, is it not?
A. No, not really.
Q. Because you were just looking at clashes?
A. No, I was looking at a clash and determining whether the clash was a clash. But, in order for me to do that, I had to follow the same exercise that Taymech would have followed. In other words, I would have looked at the drawings at my disposal and said, "Where do AA intend to put this duct?" And I would use the information available to me. I certainly did not use: "I think that must be wrong; I think I ought to move it over here" because that would be wrong."
"In the final analysis the crucial test of co-ordination drawings is whether the contractor can rely on them substantially to show where the services are to be installed at construction stage. Little input should be required by the contractor in the production of the contractor's installation drawings by way of determining the position of the services."
I also agree with RBH's submission that the number and nature of the clashes show that no adequate attempt had been made to check that the various services were co-ordinated and that they created the situation in which moving a duct or pipe to resolve a clash could cause another clash elsewhere. The reason was that AA had not exercised sufficient skill and care to ensure that the single service drawings were co-ordinated. As a result AA's co-ordination drawings, which were simple overlays of the single service drawings, were not themselves properly co-ordinated, as Mr Dix said when cross-examined. In addition until the clash was resolved by AA TW's draughtsman had to move to another section. The facts therefore speak for themselves. AA had to get the drawings out in a hurry and so more errors than would be tolerated were likely to occur and in my judgment, did occur. AA did not at the time castigate TW for exaggerating the problems although they were played down. WGI thought that TW were faced with an unreasonable number of queries.
Ceiling Grilles
Hydrotite
"C. DRYING THE WORKS
The Contractor shall be responsible for the adequate drying out of the works during the extent of the contract and maintaining it at a suitable temperature and humidity until handed over. The Contractor shall allow for all costs in providing labour, appliances and fuel
E. The drying out of the works shall be the sole responsibility of the Contractor."
and at page B1/21/B:
"The Contractor's attention is particularly drawn to the description in the Bills of Quantities and British Standard Codes of Practice which calls for special methods of curing, laying and maintenance of materials in particular conditions or at certain moisture content or temperature range, and to conditions adopted by Association of Flooring Contractors and similar bodies
The Contractor must allow an adequate period in his agreed period for the drying out operations described herein."
Provisions such as these are commonly found. They are directed to ensuring that the Works have been properly dried out before practical completion. They were written for the work as originally specified (and temporary works) and not for the work as modified by the savings (although the text is wide). In 1988 and early 1989 there was discussion between PMI, WGI and TW about TW's responsibility for drying out. It concerned matters such as the need to provide heating in order to avoid further delay in completion and was in the context of TW's claim that it had not priced for a second winter.
"We enclose a copy of a letter received from the London Flooring Company Limited, on the subject of moisture contained within the power floated suspended concrete slabs.
You will note that their recommendations are for a light scabbling of the floors followed by a damp-proof membrane application and then a levelling screed for the lino to be laid on.
Your comments on this matter are most urgently required as we are informed that the flooring companies will not be prepared to accept responsibility for the lino covering to the floors without this requirement."
The letter from the London Flooring Company read:
"We confirm having carried out a single hygrometer test on level two in conjunction with F Ball & Co Ltd, the latex manufacturers.
The hygrometer was left in position for a total of not less than 72 hours, and a reading of 92% was obtained.
Flooring laid before the base has dried will in most cases fail because of excessive moisture. It is not the moisture in the slab or screed which is important, but the quantity of moisture leaving the slab and generating the vapour pressure. Hence a hygrometer test is recommended to check the suitability of moisture equilibrium before flooring is applied a maximum 75% RH is required. However referring to our letter dated 23 February 1989 we would reiterate that with slabs as thick as the ones on this contract, a hygrometer test is not always reliable, i.e. it may indicate that the floor is dry enough, when it is not. We shall however be carrying out a further two hygrometer tests simultaneously during this current week.
We have now received the recommendations from the Contract Flooring Association, Long Furlong House, Holt, Norfolk, NR25 7DD, telephone number 0263 740370, they are as follows:-
The CFA abide by the BS8203 (1987) rules and regulations for installing linoleum, and that is the legal document.
The CFA feel that there will be problems with the slab drying out if it is 400mm thick in places, as nobody knows if the moisture will rise that far or if it will stay in the bottom of the slab causing no problems! The safe answer would be to install a surface DPM! If a surface DPM is installed, then the slab surface must be clean, and the surface roughened to form a key to receive the DPM, after which latex must be applied to the DPM as with power floated concrete.
The CFA recommendation is in fact to lay a surface DPM.
We would point out that BS8203 was March 1987. CP203 was in force before this date but it is very similar. Both standards do not mention "power floated or early ground systems".
"We enclose a copy of a letter received from the contractor regarding the laying of lime on the power floated slabs. The Code of Practice current at the time of tender certainly refers to an RH value of 75% but the document only refers to a d.p.m. being required in slabs in contact with the ground. We believe that any residual moisture in the slabs will be drawn out in the course of time via the underside where the top surface is sealed by lime and the contractor is being ultra-cautious in his approach. However we are now in a situation where the contractor is seeking instructions as to how he should proceed. Under normal circumstances we would respond that the contractor is responsible for drying out the works, but this would delay progress to an unacceptable extent since it is not possible to forecast just how long it would take to reduce the RH to 75%. Similarly we are aware that there are no funds available to provide some form of membrane even if it were though desirable.
We would be pleased to receive your advice as to the approach we should adopt in this matter."
WGI itself replied to TW on 6 April suggesting that dehumidifiers should bring the RH values to acceptable levels.
"We are unable to proceed until such times as this instruction is received and in accordance with Clause 25.2.1.1 we hereby notify you that there may be a further delay to the progress of the Works due to the lack of necessary instructions".
WGI replied on 17 April 1989. WGI referred to the items in the BOQ and said that there was "no reason why our Client should be expected to bear additional costs to enable you to achieve standards which were known to you at the time of tender". The letter was copied to NNN and to PMI (site) and was seen by Mr Massey.
"We are in receipt of a letter from The London Flooring Co, the lino floor finish specialists, and attached to this document are letters from Contract Flooring Association and Colas Building Products.
The contents of London Flooring Company's letter and Contract Flooring Association's letter is a recommendation for the surface of the suspended power floated floors on this Contract to have damp proof membrane applied prior to the lino flooring being installed. The letter from Colas Building Products gives a specification that they recommend for the application of their damp proof membrane, the cost of the application of this system by London Flooring would appear to be £5.10/m2 for the general floor areas, and £1.25/1.m. for the wall and skirting treatment.
We would be obliged if we could receive as a matter of some extreme urgency your comments and instructions on this matter as we are fast approaching the programme date for the installation of this element of the works."
Mr Hutchings accepted that the estimates were only for the direct costs of the work. (Mr Coleman also agreed that it would be so understood). Mr Hutchings said that he passed the figures on to Mr Wragg. TW's letter or the figures in it reached PMI somehow (even if Mr Hutchings' recollection is mistaken) as it would have been normal practice for TW to have sent such a letter to PMI and for the subject to have discussed with PMI. Thus at a meeting on 28 April PMI advised the DHSS that the "estimated additional cost for lino finished areas is £75,000.00". PMI's subsequent advice as to cost was at the same figure or just below. This was not the budget cost of just levels 2 and 3:
"The budget estimate for laying the moisture membrane, of all areas where lino occurs are treated, will be £75,000.00. The next area of test results will indicate whether this can be reduced."
"The report from yourselves this morning that the moisture content of suspended slabs tests undertaken by Stanger for Taylor Woodrow, are showing moisture contents of 90% or more obviously was received with concern.
However, as you had informed us previously, these tests were not being carried out in accordance with BS 8023 recommendations.
In order to come to conclusions of whether we have a problem or not, it would assist we are sure, if Taylor Woodrow carried out tests and samples with yourselves fully involved at every stage. This would enable a detailed report being submitted for the Clients consideration.
Can you please give instructions accordingly, even to witnessing laying samples of lino flooring, with details of adhesives being used etc.
We would like to have available some positive facts during next week with your advice and recommendations."
On the same day Mr. Wragg had a meeting with Mr. Fisher of the DHSS. The minutes recorded
Any Other Business
"4.1 PMI stated that a problem with the power floated suspended concrete slabs had been reported by [TW]. Tests taken by [TW] on the slabs indicated that moisture content were still too high to commence lino laying in accordance with the guidance of BS 8203 (1987). Investigations were still be carried out, but it may be necessary for a moisture membrane to be used if the project was to progress. Estimated additional costs for lino finished areas is £75,000. The Department of Health is to be kept informed of the progress of the investigations."
Although it is not recorded that PMI passed on WGI's views on TW's contractual liability the note assumes that RBH would have to pay. In its Progress Report to RBH of 2 May 1989 PMI said
"The attitude of the joint venture contractor's site staff continues to be a positive one in the attempt to complete the Phase 1 project as early as possible. Detailed programmes for floor levels have been issued enabling the work to be closely monitored. These programmes show, as we have previously reported, a programme completion date of mid-February 1990, 30 weeks later than the contract completion date. Overall, progress in the past month has met the targets set by the programme issued .".
"We have now received a preliminary report from Taylor Woodrow on the testing carried out by Stangers on the concrete floors. The tests with hygrometers were carried out on each level and readings taken during the period 26th-29th April with the following results:
24.4.89 | 27.4.89 | 29.4.89 | |
Level 1 | 62% | 75% | 79/80% |
Level 2 | 68% | 77% | 79% |
Level 3 | 72% | 75% | 80% |
Level 4 | 70% | 72% | 75% |
Level 5 | 80% | 77% | 79% |
Level 6 | - | 62% | 73% |
In addition further tests were carried out to sample the moisture of the concrete below the surface with the following results:
Level 1 | 95.1 96.6% |
Level 2 | 89.6 96.7% |
Level 3 | 90.8 95% |
Level 4 | 89.4 95.2% |
Level 5 | 93.7 94.9% |
Level 6 | 91.2 92.9% |
We believe that the difference between the two tests indicates that the hygrometers were not left in place long enough to ensure equilibrium between the concrete and the air sample being tested, but the readings do show a tendency to higher RH as time increases. Nevertheless the fact that readings in excess of 75% are being obtained after the minimum period of test specified in BS 8203 leads us to believe that the contractor is correct in his statement that the floors cannot be considered as a satisfactory base for vinyl and lino floors. In addition it should also be noted that carpets to be installed are rubber backed and are designed to be fixed with adhesive.
It is now essential that the contractor is given clear instructions on how to proceed and we are of the opinion that to seek to place responsibility for drying the structure to this extent on the contractor is not reasonable. BS 8203 which has highlighted this problem was not published until after the contract was awarded. In addition all the advice we have been able to obtain indicates that constructions of up to 350mm may take several years to dry out. We are reluctantly forced to the view that it will be necessary to install some form of vapour barrier to the slabs to enable floor laying to proceed since the only alternative is to delay installation which is fraught with danger since, as it is not possible to forecast the length of any delay, it could possibly have the effect of triggering clause 28.1.3.4 of the contract allowing the contractor to determine. Under these circumstances would you please obtain the client's authority to issue the appropriate instructions." [Emphasis supplied].
Although Mr Hutchings did not agree, the reference to clause 28.1.3.4 (see annex to judgment) shows in my view that WGI was worried that an instruction to wait until the slab was dry enough would be treated by TW as an instruction to suspend the works whereby it would or might be entitled to determine its employment under contract.
"We acknowledge receipt of your letter dated 3rd May 1989, regarding the apparent continuing dampness of the suspended floors on all levels when laying of lino would not be in accordance with BS 8203.
We are aware of the serious implications to the progress of the works. However, as the tests were done in isolation albeit by Stangers and in the absence of a report or even method statement on how the tests were carried out, it did seem necessary for further work to be done before you could provide a final report and recommendation for the Client's consideration.
This was discussed and to this end we are pleased to see that further dampness tests have been instigated and daily readings are being taken. We also arranged for the visit of Mr C Stewart, who advises the Department on aspects of building and is familiar with flooring problems. This will take place on Tuesday 16th May 1989, at 10.30 am, when we would hope to finalise the outcome of all investigations. This timing you thought still enables the 29th May 1989 date for lino laying on Level 2 to be achieved.
We have informed the Client and Department of the current problems, together with the possible need for a damp proof membrane to resolve the problem and also of the financial implications. We have also warned that in accordance with your letter a similar situation could be expected with the adhesives for rubber backed carpets, but that you would be advising further on this.
Perhaps we could inspect the locations of the hygrometers on the floors together during your visit to site tomorrow."
Since the letter referred to PMI having informed RBH and the DHSS of "the financial implications" (which included the meeting on 28 April), PMI was not in my view thereby relieving WGI of responsibility to provide advice on factors which might affect the actual cost to RBH of the work that it was to propose. The purpose of the letter was to get a firm basis for a decision as to whether or not a dpm was necessary and if so, the consequences in terms of time and money. At that time TW was saying that the lack of an instruction could result in delay. In a letter of 10 May TW said "due to your inability to resolve this problem quickly we now estimate that the delay incurred beyond the current completion date is 40 weeks". In addition on 16 May 1989 there was a meeting at which TW report that "problems with the vinyl flooring could cause a further eight to twelve weeks delay" (item 28.2.1) and PMI report (28.6.1) that the likely delay was six weeks. It is clear therefore that there might be delay and its length was not at all certain. TW was not going to be helpful as it presented the problem as one of design. WGI confirmed that advice about the drying out problem and power floated floors was to be given after the meeting.
"We are advised by the contractor that the readings of the three hygrometers installed by Mr Stewart are as follows:-
Level 2 80%
Level 3 81%
Level 4 75%
It is clear that these readings are tending towards the long term readings of the instruments installed by Harry Stanger and that the floor slabs are not dry enough to install sheet floorings in accordance with BS8203. We need therefore to instruct the contractor on the steps they should take. There are 3 options:-
(a) Instruct the contractor to delay floor installation. Our pervious correspondence indicates the dangers inherent in this course of action.
(b) Instruct the contractor to proceed without regard to the condition of the slabs. We could not recommend this course of action and would have to decline any responsibility should it be selected.
(c) Instruct the contractor to install a moisture resistant membrane at additional cost. We understand that the flooring sub-contractor and the specialist supplier of the membrane and adhesives are prepared to guarantee the installation if this course of action is agreed. However we must draw your attention to paragraph 6 of the Stanger Report dated 17th May, a copy of which is being handed to you by the contractor. We have discussed this with Stanger who say that any moisture which can migrate to partition locations will do so and it might be that the partitions will draw up any such moisture in the manner of a wick giving the impression of rising damp. There does not appear to be any firm evidence available upon which to form a judgement on the extent of any risk.
As was mentioned at yesterday's site meeting until this matter is resolved the order with Forbo-Nairn cannot be confirmed and further delays may be unavoidable. We also confirm that we share Mr Stewart's view that the use of dehumidifiers would not offer any significant improvement in the situation. Since water in concrete migrates from large to small voids with increasing difficulty as the size of the void decreases the very nature of power floated slabs inhibits this migration to the point where evaporation can take place, and it is not possible to extrapolate the drying time to a point where flooring could be laid without risk.
We would be grateful if you would obtain direction from the client as to the cause [sic] of action to be adopted."
Mr Hutchings accepted that, if a variation was being proposed by a member of the design team, then the proposal had to take account of cost and programme and that the project manager had to be advised of such effects, although he maintained that matters of cost were for PMI to obtain from NNN. Mr Hutchings said also that they were not then in mind since the change was not a variation which WGI was proposing but "was something which had developed between the contractor and the design team and PMI". However he agreed that as the architect, he would need to have in mind the possibility that an instruction might give rise to delay and disruption, and therefore to the need to ascertain loss and expense, and that time would be very much a matter for the architect to take the lead on, together with the project manager. It is obvious that, in the context of the debate at the time, option (c) would give rise to a variation. It could not have been classified in any other way, although WGI could have sanctioned TW to lay hydrotite to extricate it out of its contractual predicament. Clause 13.2 of the JCT conditions states the Architect "may sanction in writing any Variation made by the Contractor otherwise than pursuant to an instruction of the Architect/Supervising Officer." Mr Hutchings was very firm in his evidence that PMI had instructed WGI that TW was not to be held to its contractual responsibilities. I do not accept that evidence as the documents do not support it and option (a) in WGI's letter of 10 May is inconsistent with it. It would not have featured if Mr Hutchings were right. Option (b) would of necessity have been a "calculated risk" as Mr Adams put it.
"Following our advice that we were experiencing problems with excess moisture in our power floated floors on Phase 1, which will delay the progress of lino laying on site, we now enclose the Architects letters dated 3rd May 1989, 12th May 1989 and 17th May 1989.
Advice has been sought from many sources, Department of Health, Building Research, Cement & Concrete Association and what is evident from discussions is that little is known on the rate that moisture is given up from concrete slabs. Obviously, with the well constructed slabs the rate is slower. In our own case Level 2 slab is now 21 months old, yet has been in protected conditions with roof and windows completed for many months.
We arranged on Tuesday of this week for the services of Mr Charles Stewart, an independent Architect, who advises the Department on building matters to come to site to discuss the problem and verify with his own instruments the readings being obtained by the Joint Venture Contractor.
The Architect's letter dated 17th May 1989 confirms that the readings taken by Mr Stewart demonstrate that the slabs are not dry enough to lay lino in accordance with the British Standard 8203 (1987) and consequently the Joint Venture Contractor is unable to appoint a subcontractor until the way ahead is resolved.
The Architect's letter details the options open. The use of the moisture resistant membrane entailing a guarantee of this as a satisfactory method of overcoming the problem is recommended by ourselves as the way forward.
This will bring additional costs and for the lino areas alone it is estimated that a budget of £70,000.00 should be allowed.
With carpeted areas the Joint Venture Contractor has programmed the earliest laying start date in August 1989. We have to investigate whether there are problems with carpet adhesives and moisture in slabs, but in any case a further 3 months may establish further drying to the extent when the problem is no longer with us. To establish this it is agreed with the Architect that moisture readings continue to be taken and monitored.
Mr Fisher of the Department of Health has been kept informed of the problem and the possible costs involved. Obviously, the new British Standard issued in 1987 is bringing to light the inherent problems with power floated suspended slabs and Mr Fisher has been made aware of this.
We obviously need as a matter of urgency your instructions on how to proceed. Work is due to commence on Level 2 on the 29th May 1989 and a decision should be made this week if delays to progress are to be avoided.
Please let us know if further information is required."
(The letter was not copied to WGI but it was not necessary to do so.)
"I told Mr. Plant that it was clear little was known about the rate at which moisture is given up from the slabs (this was the advice of the DHSS recommended consultant) and because of that PMI had to agree to the use of a moisture resistant membrane. I believe I took the letter to John Plant personally. The construction phase was at this time almost Ύ complete and in the circumstances I could not recommend delaying the project indefinitely. I explained to John Plant that I was in favour of spending additional monies to maintain progress on the project; it was the lesser of two evils. John Plant instructed me that WGI should issue a site instruction to JVC to lay a membrane."
Mr Plant agreed that such was the gist of the conversation. Plainly Mr Wragg knew that TW might not be entitled to the instruction but nevertheless considered that it should be issued. It is not therefore open now to PMI (nor of course to WGI) to contend that RBH should be dealt with on the basis that it was an instruction to assist TW and that TW was not entitled to its consequences under the contract. If that had been PMI's view it should have advised RBH that the instruction should have been qualified. WGI's Site Instruction No 6 of 18 May read:
"POWER FLOATED SLABS
Slabs which are shown to have an RH in excess of 75% when tested in accordance with BS8203 shall be treated with Colas Hydrotite in accordance with the manufactures instructions subject to a written guarantee from the flooring sub-contractor underwritten by the manufacturer of the membrane smoothing compound and adhesive.
Tests are to be maintained on levels 4, 5, & 6 to monitor RH values.
This instruction does not extend to level 1 or other areas where a screed has been applied."
Level 1 was excluded by the last sentence as TW laid hydrotite on that level of its volition (and apparently did not subsequently claim that the work should be sanctioned under clause 13.2 of the JCT conditions, although it resurrected a claim in the arbitration and evidently the costs of level 1 was taken into account in the settlement of the arbitration). PMI's later report No 6 set out the position:
"2.0 PROGRESS
2.1 Phase 1
In our last report we indicated that the completion of services in ceiling voids was not meeting the target dates of the Joint Venture Contractor's detailed rescheduled programmes.
It is evident that the amount of work, particularly regarding electrical wiring, has been underestimated. The evident shortage of electricians on site four weeks ago has been rectified and up to 80 no electricians are now on site, with a large proportion of those prepared to work Saturdays and Sundays.
Despite the steps that have been taken the work to the erection of false ceiling grids, which is the most critical item on the programme, is now 1½ weeks in delay related to the rescheduled programme. Completion of services in the ceiling voids is 4 weeks behind the revised target dates.
The services partner of the Joint Venture Contractor, Taymech Ltd, has now placed on site a Divisional Director and a Senior Planning Engineer to oversee the services installation. This is certainly a welcome move with the continuing under-estimation by Taymech Ltd, of the task ahead.
The Architect has made known the concern of all at the inability of the Joint Venture Contractor to achieve programmed target dates and although this report has concerned itself with ceiling void services, erection of false ceilings to allow general floor finishes, equipment installations and decorations to proceed, concern has also been registered that other service installations are not making the expected progress.
An unexpected problem has occurred with the suspended power floated floors and despite being under cover now for nearly 12 months, they have not given up sufficient moisture to allow lino laying to commence. Screeds from Level 2 Level 6 were omitted at the Bill of Reductions time to make financial savings. The advent of a new British Standard on floor finishes in 1987, has brought to light inherent problems with the drying out of power floated structural slabs.
Advice has been sought from many sources, Building Research, Cement & Concrete Association and Oxford Regional Health Authority. We have also had the benefit of advice from Mr Charles Stewart, an independent Architect, who advises the Department of Health on building matters and particularly on floors.
Mr Stewart came to site on Tuesday, 16 May 1989, to look at our particular circumstances and also to take readings of the moisture content on Levels 2, 3 & 4. These readings were completed on the 19th May 1989 and showed moisture contents of 82%, 82% & 77%, all greater than the 75% required by the British Standard 8203.
What is evident from our enquiries is that it is not possible to establish how long it will take for the slabs to give up what is a small amount of moisture to achieve a 75% reading.
In order to make progress on the project, advice has been given to the Client that a moisture membrane will have to be used. This advice has been accepted and instructions issued to the Contractor to proceed on this basis. Moisture readings will continue to be taken on the upper floors and if readings of 75% and under are achieved on any floors the use of a membrane will be omitted from these locations." [Emphasis supplied]
"We are in receipt of your Site Instruction No 6, the contents of which are noted.
We must, however, notify you that whilst we are quite prepared to carry out the installation of the floor covering using Colas Hydrotite in accordance with their recommendations and instructions, we are not prepared to enter into a situation of Guarantee with regard to this work.
If it is your requirement to obtain a Guarantee with regard to the Hydrotite system you will have to obtain any such Guarantee directly from the flooring Contractor/Manufacturer. As you are aware we, as the Contractors, have our responsibilities clearly set out within the Contract and we cannot enter into any other agreement other than the commitment contained within the Contract for the Works.
We have arranged a meeting with the London Flooring Co Ltd, Colas Ltd, Taylor Woodrow Construction and, hopefully, yourselves for 11.30am on Wednesday 24 May 1989 to discuss the situation and, hopefully, arrive at a final solution to the problem.
Your acknowledgement that these arrangements are to your approval will be appreciated."
Mr Hutchings believed that he had had a meeting with TW and Colas on 16 May at which he was given trade literature about hydrotite. However in his evidence he was not at all clear about the meetings that he had had (which included a meeting with Mr Stewart of the DHSS, strangely after Mr Stewart had had a separate meeting with Mr Wragg). I consider that the meeting which Mr Hutchings had with TW and Colas was confined to the technical aspects of hydrotite, as Mr Hutchings had never heard of it before the meeting. Mr Hutchings could not even recall whether he had the "manufacturers' instructions". Yet although it is common for work to be specified in this way it is rarely (or properly) done by an architect without sight of the instructions. In my view SI 6 therefore referred to the manufacturer's instructions and to the guarantee because they had been handed over to Mr Hutchings on 16 May. I am sure that there was no discussion about the effect of the work on TW's other work. It was assumed that there would be no further delay as that concern was uppermost in Mr Hutchings' mind. Mr Hutchings however accepted that it would have been prudent to have got a method statement before issuing any instruction and that the nature of the work was likely to prevent access not only to where work was being done but other areas from which there would be no escape in the event of fire. The minutes of a site meeting held on 16 May 1989 record that TW was now estimating a delay to completion of 43 weeks.
"The floor area having been inspected by D Whitcomb and A S Harris on the 23.5.89, we would confirm that providing all surface contaminants, such as plaster, cement droppings and oil spillages are removed, especially congealed material at wall floor angle areas, leaving sub-floor clean and dry prior to applying Hydrotite.
We confirm that Hydrotite can be applied over existing and sheened areas and areas subject to staining from plaster and surface laitance, thereby removing the necessity to abrade sub-floor surface.
In order to obtain maximum penetration of Hydrotite we would recommend the first coat be applied using a 1½"- 2" fairly stiff bristle brush to achieve a coating of about 35m2 per unit and carrying the coating up the wall for some 5 10 m i.e. above ultimate level of smoothing compound.
The first coat should be allowed to dry overnight to give clear pink film. When dry, the second coat must be applied using either a short mohair roller or brush. Whilst curing, the surface must be kept free of traffic to avoid any damage to the coating.
When dry apply a slurry coat of Laybond Smoothing Compound underlayment as per our recommendations in our Guide to Good Flooring 89/90 page 6.
When dry apply average 3mm level of standard mix Laybond Smoothing Compound. Allow to dry as per our Guide before bonding linoleum using Laybond 987 adhesive.
Having laid linoleum as per manufacturers instructions, we would draw your attention to premature trafficking. We recommend that newly laid floors are subjected to only light foot traffic for 24 hours to allow adhesive to dry out sufficiently as per our Guide, page 6. Prior to fixing coving we would recommend Hydrotite being applied to finish plastered rendering, to same height as pvc coves.
The coving must then be fixed within 4 days of the cured Hydrotite using Laybond Quickstick Plus and applied as per Guide.
London Flooring's letter was:
"Further to our meeting on 24 May 1989, we enclose herewith a copy letter from Colas Building Products dated 25 May 1989.
We concur with their observations in respect of the installation of floor coverings on this contract, but would like to add the following.
Latex is not a levelling screed as such, its primary use is for smoothing an open surface as well as providing a suitable base to receive an adhesive, over the Hydrotite surface membrane.
It would be ideal if the building could be left to dry out, as reported by Harry Stranger's laboratory, but this being impractical, the only recourse is to lay a surface membrane.
Our price for laying two coats of Hydrotite to floors has already been confirmed to you at £5 45m 2. We note from Colas's specification that the will need, prior to laying latex, a slurry coat of a latex mix. Our price for this will be £0 75/m2. Regarding applying the Hydrotite to the plastered walls where PVE skirting is to be installed. This will be carried out to the height of the skirting line, and our price for this will be £1 25/1.m.
Our work method will be as follows.
Minimum of 300m2 to be ready and properly cleaned for us to commence.
Then areas to be got ready on a smaller scale once we are on site eg 70m2 at a time.
Operation 1. First coat of Hydrotite on floors and turned up 20mm to walls.
Operation 2. Second coat of Hydrotite ditto.
Operation 3. Slurry coat of latex.
Operation 4. Lay latex to slurry coat.
Operation 5. First coat of Hydrotite to plastered walls, to skirting height.
Operation 6. Second coat of Hydrotite ditto.
Operation 7. Fix PVC skirting within four days of completing operation six.
Operation 8. Lay lino to floors.
Operation 9. Weld joints in lino.
It is vital that no other trades are in any of the areas whilst all of the above operations are being carried out.
We suggest that we work one floor at a time in areas free from anything that may contaminate any of our operations. Needless to say there must be no foot traffic on the floors until 24 hours after the lino has been completed.
May we point out that it is not our responsibility to protect floors during or after our operations."
"We would inform you that due to the conditions under which it is recommended this material is laid, there could be programming implications. When this has been assessed by our site management they will communicate with yourselves."
PMI wrote to Mr. Fisher on 2 June 1989 recording what had happened:
"At our last meeting on 28 April 1987 on site, we reported the problem being experienced with moisture still retained in to power floated floor slabs to the extent that line laying would not be able to progress to programme.
The Joint Venture Contractor first registered this problem with the Architect in a letter dated 13 April 1989, when it was established that proposed subcontractors expressed their unwillingness to enter into subcontract unless the moisture content of the slabs complied with British Standard BS8203.
This British Standard specifies the type of tests to be carried and advises that laying of floor finishes dependant on adhesives should not progress on slabs with moisture contents greater than 75%. Preliminary tests taken by both prospective subcontractors and the Joint Venture Contractor indicated that the moisture content was higher than this.
Obviously, the new British Standard BS8203, has made the flooring industry more aware of the potential problems and in particular of failures that have occurred with power floated floors.
In all the investigations with the Cement & Concrete Association and Building Research, it was evident that the unknown factor was how long it would take before the slab would give up sufficient moisture.
The Joint Venture Contractor employed Stangers, to take a series of moisture content tests of the slabs from Level 1 to Level 6.
We ourselves with the Client's agreement, employed Mr Charles Stewart, an independent Architect who advises the Department of Health on building matters and has particular experience on floors, to come to site and take readings.
Letters dated 3rd, 12th, and 17th May 1989, from the Architect are enclosed which provides information on the tests carried out by the Joint Venture Contractor and expresses concern at the need to agree the way forward.
Also enclosed is a report from Mr Charles Stewart, together with a summary of the results obtained from his own readings from instruments provided by himself, which complied in all aspects to the recommendations of BS8203 (1987).
The results confirmed that the slabs still contained too much moisture, despite in some cases being cast over 21 months ago and protected from all weather for well over 12 months.
Without at this stage any possible method of extracting the moisture quickly, it was necessary to recommend to the Client the application of a moisture membrane to the slabs, to allow lino laying to proceed.
This advice has been accepted and the Architect has been requested to instruct the Joint Venture Contractor to proceed. Further moisture content tests will be taken shortly by Mr Charles Stewart, to establish whether drying is taking place to the extent that slabs are suitable to lay on without a membrane.
The budget estimate for laying the moisture membrane, if all areas where lino occurs are treated, will be £75,000.00. The next set of test results will indicate whether this can be reduced.
We will keep you informed of any further outcome and please let us know if further information at this stage is required."
"Further to your Site Instruction No 6 and our meeting on 24 May 1989 we attach a copy of the Method Statement supplied by the London Flooring Co Ltd for the application of the surface membrane and flooring on power floated slabs. The effects of this variation are:
1. To halve the output of the floor laying Subcontractor.
2. Require the complete isolation of floor areas causing disruption to the regular progress of the works.
We hereby give you notice under Clause 25.2.1.1 of the Contract that compliance with your Site Instruction No 6 dated 18 May 1989 is likely to cause a delay to the progress of the works. Compliance with this Instruction is a relevant event under Clause 25.4.5.1. We estimate that the likely delay to the completion of the works beyond the current completion date will be 33 weeks."
"In an attempt to improve the situation, we have changed the programme sequence by making the vinyl flooring the critical path activity. This is seriously disrupting other trades due to the isolation of floor areas and the increased duration caused by the addition of the hydrotite membrane."
Mr Hutchings said that as a result of the discussions in May he had anticipated that TW would have to resequence the works and would move to a new critical path in order to avoid delay, although the grounds for this assertion are not clear to me. If true, then plainly he ought to have considered what it might entail and whether it would attain its objective and what the consequences might to RBH if it did not. I do not consider that Mr Hutchings ever thought about the effect of SI 6 as there is no indication of it.
"Thank you for your letter of 7th July regarding the M & E claim. You have now confirmed by telephone that, despite previous assurances, no additional advice can now be made available to assist in the evaluation of this claim.
We must re-iterate that the extremely technical nature of this claim requires specialist expertise to assess it fully, and this level of speciality can only be provided by an appropriate specialist consultant. Without such expertise we will have to rely solely on the advice of Austin Associates who are of course the Mechanical Engineers involved in the project.
The programme position is generally as reported at the last meeting. The snagging and inspection of high level services is gaining momentum and we are optimistic that there will be a visible improvement in the completion of services over the next few weeks.
In an attempt to improve the situation we have changed the programme sequence by making the vinyl flooring the critical path activity. This is seriously disrupting other trades, due to the isolation of floor areas and the increased duration caused by the addition of the Hydrotite damp proof membrane."
"Further to our letter of the 19th June 1989 informing you under Clause 25 of a likely delay due to your Site Instruction No 6, we would now inform you that due to this instruction that we have incurred and are likely to incur direct loss and expense in the execution of this work due to disruption of the regular progress of the works by reason of the sequence of works as set out in London Flooring Co Ltd's Method Statement.
We therefore make application for reimbursement of this loss and expense under Clause 26.1 of the Contract Conditions, the relevant matter being Clause 26.2.7.
We would appreciate it if you would instruct the Quantity Surveyors to ascertain the amount of this loss and expense and include a recommendation for same in interim certificate."
Thereafter, although consideration was given to the possibility of avoiding the application of hydrotite to levels 4, 5 and 6, it was decided that it was too risky not to do so.
"Further to our recent notification regarding the delays being incurred by the inclusion of the hydrotite damp-proof membrane, we are pleased to enclose, in accordance with Clause 25.2.2.2 our Programme indicating the effect of the hydrotite membrane and the completion of the linoleum flooring. As you will see this indicates completion by Week 150, which is 17 weeks behind the original completion on the revised programme of Week 133.
We look forward to receiving your extension of time to cover this, but if you require any further particulars please specify their nature within the next 7 days, failing which we will assume that the information we have given is sufficient."
At Design Team meeting was held on 12 October 1989 at which TW's claims for extensions of time were discussed. The minutes, which were prepared by Mr Hutchings included the following relating to Hydrotite:
"2.0 Claims related to finishes
2.1 WGI reported that TWC had submitted a claim for delay in respect of the application of the Hydrotite system of damp proofing concrete floors. This had been amplified by a programme which showed that if applied strictly to the target completion programme the additional works would add 14 weeks to the floor laying activity.
2.2 It was accepted by all present that the instruction for this additional work had been unavoidable and that the effect of this was to disrupt the regular progress of the work.
2.3 WGI assessed the delay at 5 weeks."
WGI formally reported its views to PMI on 12 October 1989:
"With reference to the discussions at the Design Team Meeting held on 12 October, we confirm that we have examined the submission made by the contractor for extension of time in respect of the damp proof membrane being applied to the floor slabs. The contractor claims that in complying with this instruction he has been involved in additional operations which have had a delaying and disruptive effect on the regular progress of the works, to the extent of 14 weeks.
The contractor has reorganised his work patterns, albeit with disruptive effect upon other trades to reduce this period wherever possible. We are of the opinion that:-
a) The cause of the delay is a Relevant Event, i.e. clause 25.4.5.1.
b) The effect of this additional work would delay the completion of the works beyond the Completion Date.
c) A period of 5 weeks would be a fair and reasonable extension of time in this respect.
In accordance with our previous agreements we shall delay the issue of our Notice of Revision to the Completion Date in order that you may advise the client and the Department. The revised Completion Date will be 12 November 1989."
On the same day WGI told TW that an extension of time for 4 weeks for the vaults and variations to reinforcement would have been granted but for the extensions already granted see also later.
"Immediately prior to the issue of the architect's site instruction 6 were Taylor Woodrow contractually responsible for the drying out of the concrete floor slabs at such times and for such periods as might be necessary to facilitate the progress and completion of the works."
RBH, PMI, and CNM argued that it should answered: Yes. WGI took "no position". Judge Hicks therefore decided the issue on written submissions from RBH, PMI and CNM (but not WGI) and without oral argument. Not surprisingly in such circumstances, he concluded that TW was "contractually responsible for the drying out of the concrete floor slabs at such time and at such periods as might be necessary to facilitate the progress and completion of the Works". As I have already set out that conclusion was not held by either PMI or WGI in 1989. SI 6 was then treated as a variation under clause 13 of the JCT conditions.
"When a member of the Design Team considers that a variation is required in any category except Category 2 then he is responsible for notifying the Project Manager, and for requesting other members of the Design Team to investigate and assess the design and programme implications of the change, providing sufficient information to the Quantity Surveyor to estimate a budget cost."
RBH submitted that since WGI was the relevant member of the design team it was responsible for obtaining the assessments of other members of the design team and in providing sufficient information to NNN for NNN to estimate a budget cost. RBH's case was that WGI had failed to do so. On 10 May 1989 it had been asked to provide "a final report and recommendation" for RBH to consider. If WGI had done so with reasonable skill and care it would then have told RBH that hydrotite would delay completion as it would cost more than £75,000.
(1) theoretically, to dry out the slabs, but as that was impracticable (which it was both physically and commercially),
(2) to wait until the slabs had dried out naturally and to suffer any liability for liquidated damages that would ensue, or
(3) to ask WGI to sanction the laying of a hydrotite as a variation required to extricate TW from its own difficulty (which would thus not be eligible for a valuation or other compensation under clauses 13 or 26 of the JCT conditions).
At first sight it is odd that a firm with the experience of WGI did not present RBH with such orthodox advice. There are two probable reasons: either Mr Hutchings was not sufficiently experienced or he appreciated that to present TW with such avenues would probably lead to an investigation as to why RBH was not told of the implications of the decision to omit the isocrete screed. Given the belligerent stance which TW was by then adopting such an investigation would more than likely have resulted. Mr Hutchings was certainly not inexperienced in contractual matters.
"I think there should be dialogue between all of the parties such that when a recommendation is put to the client the client knows that it has been discussed with the contractor and price has been agreed and method statement has been agreed and we can move forward on a sensible instruction."
He said that the architect should lead that discussion and that the project manager would have served his client's best interest either by having that discussion with the contractor prior to the instruction being issued as his negotiating position would be substantially better than trying to have that discussion subsequent to the instruction being issued or by finding out from the architect whether he had exercised that judgment and if so the basis upon which he arrived at his conclusion. TW should have been required to produce a method statement which was comprehensive as there would be a change to its previously established methods of working which would have far-reaching effects, as Mr Adams said, adding, in a reply to Mr Williamson, that he had specific experience prior to 1989 of contractors being asked for such proposals (which accords with my own understanding). In my judgment WGI did not take care to see that it had the full picture. Thus its advice to RBH was not as it could and should have been, had that care been taken. The fact that the information came forward shortly after SI 6 was issued shows in my judgment that it would have been available had WGI pursued RBH's interests with reasonable diligence. I note that in a joint statement the architects commissioned by the parties to provide expert opinions said:
"3.12 We agreed that WGI, knowing that PMI would report the situation to the Board requesting instructions how to proceed, should have reminded PMI of the further option, that TW should be held to their contractual responsibility and instructed to resolve the problem at their own cost.
.
"3.16 We agreed that WGI should have advised PMI that by issuing an architect's instruction to TW to lay Hydrotite there would, in addition to the direct additional costs, be the possibility of claims for delay and disruption and an Extensions of Time from TW".
Some reliance was placed (by PMI) on Mr Adams' apparent agreement that there was no practical alternative to issuing the instruction. However Mr Adams was careful to make it clear that his view was predicated on the assumption of due and thorough consideration and RBH being aware of the implications accepting them.
"Examine and advise on all variation orders proposed by the Architect and advise on the effect on programme and cost. Recommend implementation either at the time, at a defined time or on completion of the project and agree action with the General Manager."
PMI accepted that this obligation required PMI to consider whether there might be such an effect and, if so, to collate the relevant information for the client. Equally, in my view, the obligation to "recommend implementation" follows the general obligation to advise on all variation orders so PMI was obliged to tell RBH if it thought that a proposal from the Architect should not be implemented, either at all or until further information was available. PMI maintained that its obligations had to be determined in a manner consistent with the related obligations of WGI and NNN. Only WGI could issue instructions to TW and only NNN could value them. Thus PMI too relied on clause 7.10 of the Project Procedures Document (quoted above) which provides:
"7.10 When a member of the Design Team considers that a variation is required in any category except Category 2 then he is responsible for notifying the Project Manager, and for requesting other members of the Design Team to investigate and assess the design and programme implications of the change, providing sufficient information to the Quantity Surveyor to estimate a budget cost."
PMI submitted that this obligation was the key to the approval procedure set out at Clauses 7.11 to 7.13 of the Project Procedures Document. They read:
"Approval Procedure
7.11 When evaluating the effects of a variation in any category, each member of the Design Team will be required to formally confirm his assessment in writing, accompanied by any necessary drawings, sketches or other documentation. The Project Manager is responsible for ensuring that this back-up exists and that all assessments have been made on a consistent and reasonably accurate basis. Where he judges it appropriate the Project Manager will endeavour to obtain the Contractor's assessment of the effect of the proposed change on costs and programmes.
7.12 On receipt of the Design Team assessments and, where appropriate, the Contractor's assessment, the Project Manager will prepare a Change Order Form set for consideration by the Client. The Project Manager is responsible for ensuring that the Change Order Form accurately reflects the assessments provided and will endorse the form to indicate this.
7.13 The Change Order Form will contain the following information:
Serial number
A description of the change
Variation category
Bill references
Drawing references
Net cost effective on the Approved Sum by Building and M&E, including direct and indirect costs
Effect on programme
7.14 A Change Order Form set authorised within the delegation limits defined in 7.4 will be separated and distributed to the Client and the Design Team by the Project Manager."
"An architect's duties are comparable, in some aspects, to those of ecclesiastical surveyors, of whom it has been said that, they "could not be expected to supply minute and accurate knowledge of the law; but we think under the circumstances they might properly be required to know the general rules applicable to the valuation of ecclesiastical property.""
The analogy is not perhaps precise but the point is correct. However in this context knowledge of the law has two elements. An architect must have an understanding of the fundamental principles of law relevant to construction and an ability to apply those principles in the management and administration of projects and contracts. However contractual questions do not necessarily require a knowledge of the general law but simply a good understanding of standard forms. That is something which is also to be expected of project managers. In this case it is clear that WGI had or purported to have a good knowledge of the principles of law relevant to construction contracts: in a letter of 3 August 1989 it referred to the judgment of Vaughan Williams LJ in Wells v Army & Navy Co-operative Society as relevant. That letter was addressed to PMI and in the ensuing correspondence (to which I shall come) the provisions of the JCT conditions were discussed in some detail. PMI evidently understood the points being made. In my judgment WGI's advice and attitude on TW's supposed right to determine its employment was quite untenable and not thought through at all. It was in my view so obviously unreasonable and apparently wrong that PMI ought to have questioned it either before or at the time that WGI's views were transmitted to RBH. (However the case against PMI does not turn on this point.) There were no technical issues upon which PMI might legitimately have deferred to WGI. A project manager is appointed to evaluate for the benefit of its client the opinions and advice of the other members of the project team. PMI did not do so and so failed to exercise the skill and care required by clause 4.1 of its retainer.
"My experience, and that of many of my contemporaries, is that the project manager is expected to ask more questions, add more value, and I would have expected the project manager to say to the architect: should you not be obtaining a method statement from the contractor as to how he is going to incorporate these works and at what cost?"
That evidence, coupled with Mr Adams' other answers (such as those already quoted in my consideration of the position of WGI), helpfully show what a project manager should do, although as I have said earlier, PMI's conduct is to be judged by ordinary common sense as there was no established practice to which PMI could have had recourse. (Nor is there likely to be even now for such mundane circumstances.) In my view it was clear to a project manager that there was at least a possibility of disruption (as well as delay - as the meeting on 16 May shows). Mr Coleman agreed that this was so. He said: "You cannot predict the way contractors react." In addition, I have accepted Mr Adams' observation that TW's failure to produce a critical path programme made it all the more important for PMI to make its own analysis and to advise the RBH (and WGI) whether what WGI was proposing was likely to affect progress or completion of the works, and what that effect might be. I have also recorded Mr Adams' evidence (which I fully accept) that it was common for contractors to be required to produce a comprehensive method statement where there would be far-reaching effects.
"69.1 In order to apply Hydrotite, Taylor Woodrow's sub-contractors had to have sole access to the area where it was to be laid, so that temporary partitions had to be erected and other trades directed to work elsewhere.
69.2 This resulted in both delay and disruption to Taylor Woodrow.
As a result
69.3 .1 Taylor Woodrow submitted claims under the main contract on the 17th December 1990, the 18th December 1990, the 11th April 1991 and/or the 31st May 1991 set out in paragraph 29 above.
.
69. 3 .2 WGI granted Taylor Woodrow extensions of time on the 19th October 1999 and the 24th November 1989 as set out in paragraph 28 above.
[69.3 .3 The Board paid Taylor Woodrow £858,123 as set out in paragraph 30 above.
69.3. .4 Taylor Woodrow advanced claims 10, 11, 12, 13, 18, 20, 22, 23, 24, 29, 31 and/or 34 in the arbitration set out in paragraph 32 above]".
The parts in square brackets were not selected for decision at this stage. The case against WGI and PMI continued in paragraph 74:
"74.2 Had PMI and/or WGI not been in breach of contract and/or negligent as set out in paragraphs 71.4 to 71.11 inclusive above and 72.5 and 72.12 inclusive above respectively, then:
74.2 .1 the Board would not have agreed to the giving of the instruction to lay Hydrotite; and/or
74.2 .2 the extensions of time and payments to Taylor Woodrow in respect of the instruction to lay Hydrotite referred to in paragraphs 69.3.2 and 69.3.3 above would not have been granted or made; and/or
[74.3 .3 in the arbitration Taylor Woodrow would not have advanced the claims in respect of the instruction to lay Hydrotite set out in paragraph 69.3.4 and/or those claims would have stood significantly less chance of success; and/or
74.4 .4 in the arbitration the Board and/or the Plaintiff would not have had to make the claims set out in paragraph 70.2 above and/or those claims would have stood a significantly greater chance of success]".
Paragraphs 74.2.1 and 74.2.2 have been selected for decision (although not so as to bring back paragraph 69.3.3 which was not selected). Thus PMI and WGI saw RBH's case as requiring it to establish that but for the breach or breaches, RBH would not have agreed to the issue of SI 6; that SI 6 caused delay and disruption to TW; and that, as a result TW was granted extensions of time.
Causation
"Thank you for your letter of 26 July regarding the extension of time granted to the Contractor.
As you know we had at the end of the Contract, received two outstanding claims for extension of time, on in respect of M & E works dated 19th June and one in respect of the Chelsea Hospital for Women site dated 9th May. The M & E claim was for 45 weeks' extension and the C.H.W. claim was for 31 weeks. Under Clause 25.3.1, we have to come to a decision on any outstanding claims no later than the completion date which, in this case, was 23rd July. In our letter of 10th July, we advised you that it was not possible to come to a conclusion on the M & E claim by that date but we were of the opinion that an extension of time was justified in respect of the C.H.W. site as the site was not finally made available to the Contractor until 13th March, 10 weeks after the date inserted in the Contract Bills and Drawings, and that we proposed to award an extension of time of that amount.
We do not accept the claim of 31 weeks delay due to the non-availability of the C.H.W. site, but you will recall that the Design Team has always taken the view that the only operation taking place on site during the last 12 weeks of the Contract were cleaning of the new building and the external works. A delay in making this area of the site available must have a significant effect on completion. We considered that a fair and reasonable extension of time would be the period during which the Contractor was unable to progress the whole works in this area, i.e. 10 weeks. It should also be noted that when demolition of the last outbuilding was attempted, it was found to contain toxic waste and the attempt had to be abandoned until such time as it could be rendered safe.
To summarise the situation, the Contractor was entitled to possession of the main site from 2nd March 1987 until 23rd July 1989 and the C.H.W. site from 1st January until 23rd July 1989 in order to complete the Contract works. In the event the employer, albeit through no fault of his own, was unable to comply with his Contract commitment and the extension of time awarded seeks to remedy the situation with respect to time. We should point out that we do not accept at this moment, that there has been any loss or expense which is recoverable by the Contractor other than the double visit by the sheet piling Sub-Contractor which has already been awarded.
Although Clause 25.4.12 is a new provision in J.C.T. Contracts, the question of possession has been considered by the courts on a number of occasions, the judgment of Lord Justice Williams in Wells v Army & Navy Co-operative Society is, we consider, relevant:-
"If in the Contract one finds the time limited within which the builder is to do the work, that means, not only that he is to do it within that time, but it means also that he is to have that time within which to do it".
WGI did not receive any material comments and told PMI of the consequences see its letter to PMI of 4 August:
"Thank you for your letter of 7th July regarding the M & E claim. You have now confirmed by telephone that, despite previous assurances, no additional advice can now be made available to assist in the evaluation of this claim.
We must re-iterate that the extremely technical nature of this claim requires specialist expertise to assess it fully, and this level of speciality can only be provided by an appropriate specialist consultant. Without such expertise we will have to rely solely on the advice of Austin Associates who are of course the Mechanical Engineers involved in the project.
The programme position is generally as reported at the last meeting. The snagging and inspection of high level services is gaining momentum and we are optimistic that there will be a visible improvement in the completion of services over the next few weeks.
In an attempt to improve the situation we have changed the programme sequence by making the vinyl flooring the critical path activity. This is seriously disrupting other trades, due to the isolation of floor areas and the increased duration caused by the addition of the Hydrotite damp proof membrane."
"We have now completed our examination of the M & E claim for extensions of time submitted on 19th June and the analysis prepared by Austin Associates. Our views are as follows:-
Clause 2.2.1. | There is nothing in the Bill of Quantities or Specification which overrides or modifies the principal contact conditions |
Clause 5.4. | Copies of the contract drawings were issued to you at the commencement of the contract and such further information as was necessary was issued in accordance with a programme agreed by you. It should be noted that your programme P01/C was not issued until August 1987 and the noted dates of 4th May 1987 for the issue of information does not comply with the requirement of clause 25.4.6 in that it is retrospective. |
Clause 7. | As we have previously stated this clause relates to setting out of the works at ground level and is thus irrelevant. |
In view of the above and the detailed analysis prepared by Austin Associates, a copy of which is enclosed for your information, your claim is rejected."
TW did not accept WGI's views and replied at some length on 29 September:
"We are in receipt of your quite unacceptable letter dated 10th September 1989 in which you have rejected our claim submitted under cover of our letter of 19th June 1989 for extensions of time in respect of delays to the mechanical and electrical services installation.
Your letter concentrates on 3 clauses and a subjective defence document from Austin Associates which may be the subject of a very detailed response in the near future dependant upon our deliberations as to the appropriate action at this junction.
You do not begin to address one of the most salient points, namely that upon our late receipt of the co-ordination drawings prepared by the services Consultants most of them proved entirely inadequate for our use in the production of installation and working drawings by virtue of the number of clashes and discrepancies that they contained. We refer below to the particular comments by reference to the several clauses mentioned in your letter.
Clause 2.2.1
On the assumption that you are interpreting the Bills of Quantities and Specification in the way which Austin Associates have (which we find very surprising) it is patently clear that there is indeed a conflict as you are attempting to suggest that we have design obligations contrary to the provisions of the conditions of contract. You have also failed to note that our arguments were submitted in the alternative and we suggest that you reconsider our claim.
Clause 5.4
Whilst we accept that our programme no TWC/B364/B/P01/C was referred to in the claim document, your suggestion that we have only retrospectively applied for the information and that our application therefore falls outside the requirements of clause 25.4.6 is not correct. The programme to which our claim refers is revision C of our initially prepared contract programme, revision A of which was tabled at our meeting of 31st March and revision B of which was forwarded to you under cover of our letter dated 10th April 1987.
We enclose for your information a copy of our programme TWC/B364/B/P1/B which makes quite clear that all information relating to the mechanical, electrical, plumbing, and specialist services installations was required to be provided to us by 4th May 1987. In addition, we would refer you to the minutes of our meeting held on 31st March 1987, a copy of which is attached, during which a schedule of required information was discussed. The schedule clearly indicated those dates upon which the services details were required. There was no suggestion at that meeting that our requirements could not be complied with. Indeed, Austin Associates undertook to produce all such information during that week. In the event as our claim document makes entirely clear, the information relating to the services was issued extremely late and had a significant effect upon our ability to produce our installation drawings in a timely manner which in turn seriously delayed and disrupted our work.
The fact that the information we required was issued extremely late is a matter upon which there can be no doubt. Furthermore, there can be no doubt that you and Austin Associates had previously been made fully aware of our requirements fully in accordance with our contractual obligations.
Clause 7
We have had many exchanges on this clause previously, and we are quite clearly diametrically opposed. We have previously given detailed reasons why interpretation is correct and on every occasion you have failed to justify your most novel interpretation. This is the style adopted by Austen Associates in their document.
In the light of the further information that we have now provided, in particular, under clause 5.4 above, we must urge you to urgently reconsider your position in the interests of all concerned."
WGI did so. WGI's view changed on consideration of TW's letter of 29 September 1989, which altered the basis of their claim from reliance on P01/C to reliance upon P01/B and the information schedule of 31 March 1987. It carried out its own analysis and accepted the new basis as set out in its letter of 3 October 1989. Essentially instead of working forward from the date by which information might be required it went to the start of installation and worked back. It took TW's six weeks' drawing programme, two weeks' approval period, and eight weeks' mobilisation (making 16 weeks). That approach was in my view correct and certainly reasonable for an architect to take. It was accepted by AA in paragraph 94B of its Defence and by Mr Miers I have already concluded that P01/B was (and certainly would have been regarded in an arbitration as) sufficient for the purposes of clauses 25 and 26 of the JCT conditions. WGI was therefore entitled to act under clauses 25 and 26. WGI wrote to PMI on 3 October with the results:
"Thank you for your letter of 26 September regarding the M & E claim. In our letter of 18 September we stated that our assessment of the claim was based on the analysis prepared by Austin Associates. This analysis had taken the whole of the 12 week period allowed by the contract for the determination of claims and we accepted that it would be factually correct.
The contractors claim document was referred to programme P01/C as evidence for this request for M & E information by 4 May 1987. In their analysis Austin's correctly point out that this programme was not issued until August 1987. They thus claim that the request was retrospective. We have now received from the contractor a letter dated 29 September, a copy of which is enclosed, pointing out that programme P01/B was issued on 10 April 1987 and this document also calls for the information by 4 May. In addition it has been pointed out that the Schedule of Information Required issued at Site Meeting No 1 held on 31 March 1987 calls for all M & E information to be issued commencing 6 April 1987.
We have carried out an analysis of the dates when information was called for and when it was actually issued. This shows that the issue of co-ordinated drawings was on average some 15Ό weeks after the date required. We believe that this matter should be discussed at a meeting of the Design Team when the doubts raised in your letter could also be discussed. We have therefore arranged a meeting for 12 October at 10.00 am at Alexander House."
"4.0 M&E Services
4.1 Late issue of information
4.1.1 WGI reported that in coming to this decision on the M&E claim they had relied upon the claim document and the analysis of it prepared by AA. Both these documents were based on TWC Programme P01/B issued in April and the schedule of Information Required issued at Site Meeting No 1 on 31st March 1987. Both of these documents called for the issue of all M&E information in April/May 1987.
4.1.2 AA stated that whilst they could find no record of having received Programme P01/B they acknowledged the schedule. They pointed out that the same schedule issued at the next Site Meeting showed that this information had been received. They therefore concluded that the information asked for did not at that time include co-ordinated drawings, although TWC now contend that it did.
4.1.3 It was the view of all present that under the terms of the contract TWC were not entitled to receive co-ordinated drawings but that they had been advised, both before tender and after the award of the contract, that they would be provided by way of further information.
4.1.4 AA stated that in their view, having been advised that co-ordinated drawings were to be issued, it was reasonable for TWC to await their receipt before commencing their own drawing programme.
4.1.5 AA further stated that although the meeting held on 11th August 1987 was the first time a programme for the release of co-ordinated drawings had been discussed, with the benefit of hindsight they should have been pressing for them earlier.
4.1.6 WGI stated that in analysing the latest information for TWC they had used a period of 19 weeks from the issue of co-ordinated drawings to a start on installation. This was made up:-
9 weeks drawing period
2 weeks approval
8 weeks mobilisation
4.1.7 AA did not consider that this was a reasonable period. In their view a period of 16 weeks, made up as follows, was more reasonable:-
6 weeks drawing period including queries
2 weeks approval period including queries
8 weeks mobilisation period including queries
This period was based on the actual times taken for the upper levels which had been carried out jointly with TWC in AA's office.
4.1.8 It was agreed by all present that TWC were entitled to an extension of time and that WGI should use 16 weeks in assessing the claim.
4.2 Inaccuracies & Inadequacies
4.2.1 AA stated that they accepted that there had been errors in the co-ordinated drawings but contended that the effect of these had been countered by their placing of a co-ordinating engineer on site. They did not accept that the drawings were in any way inadequate."
"With reference to the discussions at the Design Team meeting held on 12th October we confirm that we have now reassessed the contractors claim for extension of time due to the late issue of co-ordinated M & E drawings. We are of the opinion that: -
a) The cause of delay is a Relevant Event, i.e. clause 25.4.6.
b) The delay would delay completion beyond the Completion Date.
c) A period of 9 weeks would be a fair and reasonable extension of time in this respect.
d) The extension of time will be in addition to these already granted in respect of the main building works but will be concurrent with the period granted in connection with external works.
The current situation regarding extension of time are as follows: -
Main Building
Sub-structure/Superstructure delays 4 weeks
Late issue of M & E co-ordinated drawings 9 weeks
Hydrotite floor membranes 5 weeks
Total 18 weeks
External Works
Late availability of CHW site 11 weeks
As these categories are concurrent events the total extension at this time is 18 weeks resulting in a revised Completion Date of 26th November 1989, would you please advise the clients and the Department of our conclusions."
The letter was copied to AA. On 2 November AA was also sent WGI's formal determination that the time for completion should be extended to 26 November under clause 25.4.6, i.e. 9 weeks for M&E (with 7 weeks concurrent with CHW). For what it is worth, PMI raised no objection to WGI's extensions of time either on the grounds that WGI could not act under clauses 25.4.6 or 26.2.1 or otherwise. It is accepted that the extension of nine weeks was arithmetically incorrect by two weeks and should have been seven weeks so in part the case in paragraph 97D of AA's defence is correct.
"We refer to your Minutes of the 12th October 1989, Design Team Meeting, held for the purpose of considering claims for extension of time submitted by Taylor Woodrow Construction Ltd.
We wish to advise that the Minutes are not wholly agreed in the following: -
Minute 4.1.1
The claim document and the analysis were based upon Taylor Woodrow Construction's Programme P01/C issued in August 1987, not Programme P01/B, as stated in your Minutes.
Subsequent to Taylor Woodrow Construction's claim document, a further submission was made by Taylor Woodrow Construction, in their letter to Watkins Gray International dated 29th September 1989, which referred to programme P01/B and the schedule of "Information Required" as attached to Site Meeting No 1. Neither of these documents was referred to in the original Taylor Woodrow Construction claim document.
Your minutes also state that the schedule and P01/B both called for the issue of all M & E information in April/May 1987. We should emphasise that we have no doubt that the contractor was not then calling for co-ordination drawings, as is clearly demonstrated by: -
a) The Schedule of "Information Required" was annotated by the contractor to acknowledge receipt of the M & E information required at that time.
b) Austin Associates statement in Minutes of Site Meeting No 1, regarding the Schedule, when we advised that the drawings called for would be issued in one week. This clearly was not a reference to co-ordinated drawings.
We also stated at your Design Team Meeting that we understood that the contractor required the issue of certain information in April/May to enable him to prepare builders work drawings and commence detailed planning, ordering and appointment of specialist sub-contractors. He was readily able to carry out these tasks using the individual service drawings, prior to issue of co-ordination drawings.
Minute 4.1.5
It should be clearly understood that relative to the agreed dates for issue of co-ordination drawings, the "Benefit of hindsight" would be on the part of Taylor Woodrow Construction who should have been pressing for the co-ordination drawings earlier, based upon their knowledge of numbers of draughtsmen available, capability of their drawing office to cope with the preparation of working drawings and the mobilisation period needed.
Minute 4.1.7
Regarding the 6 weeks drawing period, our advice at the Meeting was that based on the actual times taken by the combined resources of Austin Associates/Taymech on the upper levels, this period could be reduced to 3 weeks if the contractor wished to use his best endeavours to minimise the drawing period. We agreed that a reasonable assessment of a "normal" period would be six weeks.
Regarding the 8 weeks mobilisation period, we did advise that the contractors initial activities were to commence installation of drainage and general support brackets. The preparation of manufacturers ductwork drawings and delivery of ductwork would therefore overlap beyond the start on site date. The contractors assessment of mobilisation period was not declared at planning stage. The 8 week mobilisation, worked back from 5th October, is thus a generous allowance considering the above and additional comments below.
1) An 8 week mobilisation period equates to the time between the 11th August 1989 meeting and their start on site of 5th October 1989. It was clearly not the contractors intention to use the 8 week period solely for mobilisation, as final issue of Austin Associates co-ordination drawings was not required by the contractor for Level 1 until week commencing 11th August 1989 to enable him to commence on time. The contractor was confident, at that time, that he could continue to programme, but subsequent events demonstrated that he had grossly over estimated his drawing office capabilities. "Hindsight" applies here.
2) The contractor did, in fact, commence on time but did not proceed to programme due to the failings of their drawing office to continue to prepare working drawings on time, not because of late issue of co-ordination drawings. The extent of claimed aborted installation, following the 5th October start, we believe was grossly exaggerated with a view to introducing a claim for delay. At this stage, they had now perceived the inadequacies of their drawing office and they commenced consideration of using WOCAD.
3) Our analysis of their claim document clearly demonstrates that the use of WOCAD introduced a further considerable delay, particularly as their approach was to produce "clash highlight" drawings rather than diligently proceed with working drawings. The analysis clearly demonstrates their erroneous claims of service clashes. Therefore, we consider that the contractor failed to use his best endeavours in preparing the working drawings, particularly considering that he was behind programme. It should be noted that our previous assessment of a possible 3 week drawing period would normally be expected to apply in these circumstances where the contractor was facing delays. (Refer to our analysis pages SH/17 to /21). It is, of course, feasible that less than 3 weeks drawing period could have been achieved by WOCAD but, as our analysis demonstrates, the contractor failed to input the latest information, which resulted in an extended drawing period.
4) The Watkins Gray International use of the 16 weeks drawing/approval/mobilisation period as discussed at the meeting, is agreed as being a reasonable mathematical calculation of a contractors possible approach to a contract of this nature, but it is equally true to say that the period could have been reduced by the contractors better use of resources and/or an approach intended to mitigate delays rather than introduce them.
5) We note your current assessment of an effective 9 week delay due to late issue of M & E co-ordination drawings. The final Watkins Gray International assessment of the Taylor Woodrow Construction claim, some of which we understand is still to be submitted and/or resubmitted, should obviously take the above into account as well as our detailed analysis."
The letter therefore did not take exception to Minute 4.1.2 (although the comments on Minute 4.1.1 were plainly relevant to it), or to Minute 4.1.8. If AA really thought that a 16 week extension of time was not justified it would (and should) have said so. Anybody reading AA's comments on Minute 4.1.7 would have concluded that AA was only questioning WGI's methodology, and was not saying that its conclusion was untenable. Again I find AA's explanation unconvincing as to why it did not do so either on 12 October or later. I am sure that Mr Edwards would have told WGI on 12 October or later of the period that he thought was justified (as opposed to writing to protect AA from criticism of why it had created the situation in which TW had to be given the extensions). Mr Hutchings said, perfectly understandably, that there was nothing in the letter which caused him to think that the record of the discussion on 12 October was inaccurate in any sense that mattered. In the circumstances it is not surprising that WGI did not reply. In addition, by the time it received the letter, it had acted.
"Generally the matter of assessing an extension of time is a difficult and highly demanding process, and in my experience many architects make errors in the application of the principles under the contract and the methodology to be applied."
His experience was that "lots of competent architects actually deal with extensions of time in very different ways and in ways in which [he] would consider them to be making mistakes". AA's case seems to me to involve being very wise after the event, especially since, in order to establish it, AA needed a very large and detailed report from Mr Miers which in my judgment showed how, even with due care, mistakes can easily be made, although some were quite minor and of little proven consequence. I was not satisfied that WGI had ignored anything or taken something into account which no competent architect should have done (nor did Mr Miers so suggest). WGI formed a judgment. For the purposes of this litigation, Mr Miers showed that, had WGI the time and resources available to him, it would have formed a different judgment. So far as I am concerned the judgment of WGI was not gravely mistaken. It is plain that at the time WGI and Mr Hutchings understood the requirements for the determination of an extension of time. Not only are there the extensive discussions and correspondence in 1989 but on 28 February 1990 Mr Hutchings wrote:
"With regard to your general assertions regarding your obligations to provide such additional information as we require, we should point out that the conditions precedent to the award of the extension of time you seek are: -
(i) that the progress of the works has been or is likely to be delayed
and
(ii) that the completion of the works is likely to be delayed beyond the Completion Date.
Since both of these conditions are the subject of the Architect's opinion, it seems reasonable for us to require such additional information as would allow that opinion to be an "informed opinion". What better way of demonstrating compliance with i) above can there be but an analysis of the critical path at the appropriate time?"
"Following recent discussions we write to confirm that further payments against the contractor's claims for loss and expense will be included in the current interim valuation (Number 33). These are against items accepted by the Architect, the details of which are as follows:-
1. (a) | 1. (a) Direct loss and expense under clause 26.2.7 of the Conditions of Contract, based upon Watkins Gray International's letter to the Contractor dated 21st April 1989, due to disruption to the regular progress of the works whilst carrying out the substructure and superstructure operations (see also Watkins Gray International's letter to the contractor dated 12th October 1989) | £157,000 |
|
(b) | (b) Additional cost for construction of the covered walkway based upon Watkins Gray International's letter to the Contractor dated 27th April 1989. | £ 15,160 |
|
2. | 2. Direct loss and expense for two stage piling operation along the western boundary of the site, based upon Watkins Gray International's letter to the Contractor dated 8th May 1989. | £ 5,788 |
|
3. | 3. Prolongation costs associated with the four week extension of time for substructure and superstructure works and the five week extension of time for Hydrotite flooring membrane. These are based upon Watkins Gray International's letters to the Contractor dated 12th and 23rd October 1989. | £214,000 |
|
4. | 4. Prolongation costs associated with the nine week extension of time due to late issue of co-ordinated drawings, based upon Watkins Gray International's letter to the Contractor dated 2nd November 1989. | £216,000 |
This information supersedes that set out in our letter to you dated 11th September 1989 and all ascertainments are interim.
Could you please notify the Department of Health of these amounts which now total £607,948 and contact us if further information is required.2
"We have now completed our consideration of the claims for delay contained in your letters of 30 October and 10 November. We are of the opinion that:-
a) the cause of delay is a Relevant Event, i.e. clause 25.4.5.1.
b) the works would be delayed beyond the Completion Date.
c) A further period of 5 weeks would be a fair and reasonable extension of time.
As this further extension would prolong the works into the statutory Christmas holiday period we enclose our Notification fixing a new Completion Date of 14 January 1990.
With regard to loss and/or expense the Quantity Surveyor will extend his ascertainment of the previous Hydrotite extension to include this further extension.
TW was granted the extension of time to 14 January on the same day. As already recounted and considered, WGI gave a further extension of time of two weeks on 14 August 1990 for the late issue of M&E drawings. On 6 April 1992 WGI granted TW five weeks for inadequate M&E drawings.
"97A. Further in relation to paragraph 59.4 of the Re-Amended Statement of Claim, AA adopt the Claimant's primary case that for the reasons set out in paragraphs 91.1-3, 95, 101, and 108 of the Re-Amended Statement of Claim the extensions of time dated 2nd November 1989, 14th August 1990 and 6th April 1992 ought not to have been granted by WGI. In addition AA contend that the said extensions of time were incorrect and unreasonable on the further grounds pleaded at Paragraphs 97B to 97H below."
Paragraphs 59.1 of the RASC recited that TW had made claims and paragraph 59.2 pleaded the extensions of time granted by WGI. AA's Defence in paragraphs 97 to 97H was very specific: for example paragraph 97D read:
"When calculating the alleged period of delay under the extension dated 2nd November 1989, and possibly the extension dated 14th August 1990, WGI either made a two week calculation error or erroneously allowed an additional two week period for Easter when no such period should have been allowed."
The issues arising from these paragraphs were to be tried by the order of Judge Hicks. RBH did not in the event pursue the claims in the paragraphs in the RASC adopted by AA. Mr Miers was called by AA to establish its case but not to say that WGI was negligent (with the exception of the extension for safety cabinets which Judge Seymour found not to have been negligent). Thus he said on a number of occasions in the conclusions to his report:
"I consider that WGI were mistaken in the way in which they approached the assessment of this EoT and in their calculations, and that as a consequence the extension of time they awarded was greater than it should have been.
As to whether in making the mistakes I have identified, WGI fell below the standard to be expected from a reasonably competent architect, this is a complex issue and a difficult question and is a matter I wish to consider further in the light of the continuing discussions with the other expert architects and the release of the expert programmers' reports."
In his evidence Mr Miers did not really depart from that view since the opinions that he was called to express were based on the documents (which appeared at times not to be complete e.g. he had not been asked to look at TW's preliminary programme P01). Indeed he accepted that neither in his report nor anywhere else had he criticised PMI or WGI for falling below the standard of care that he had considered, i.e. the contractual standard. AA also cross-examined Mr Hutchings on the reasoning behind his decisions. After some discussion at the outset of the trial I said that the point would be dealt with in the final submissions.
"296. WGI's grant of 11 and 5 week extensions of time, respectively, was a natural and probable consequence of the late issue and poor quality of the drawings, as were the instructions to NNN to ascertain TW's loss and expense. Brompton's position on quantum is that it is entitled to recover the costs that it occasioned by these extensions of time, since it is not alleged that they were granted negligently (irrespective of whether either the extension of time or the sum ascertained was in truth right or wrong as to amount).
[RBH added a footnote: "In fact, on the current state of the authorities these costs may even be recoverable if the EOTs were granted negligently".]
297. For this reason, Brompton submits that the question of whether there was in fact any, and if so how much, delay in fact does not have to be considered, save possibly in the context of certain sums claimed based on the settlement of the arbitration."
(There was a comparable paragraph in relation to the hydrotite claim.) AA did not therefore in its final submissions, both written and oral, grapple with the point that had earlier been canvassed, although its own submissions naturally required consideration of some of the same territory. It was not until some way into the final submissions of Mr Williamson that it emerged that the point or some point had not been abandoned. This was not satisfactory, nor were the explanations offered for the absence of any response to Mr Bartlett's queries ("to formulate detailed issues meeting all the objections was going to take time that we just did not have to devote to it"). The next day, just as Mr Bartlett was tendering submissions on paragraph 296, Mr Edwards-Stuart produced further "Notes on the 'point of Principle'". These began:
"The Nature of the 'Issue'
1. The 'issue of principle' is in fact a practical issue which arises to be determined on the evidence before the court. In essence the issue is
"Has the claimant established a causal link between the breaches of duty and the extensions of time?"
2. This, of course, gives rise to a potential issue of principle, namely:
"If WGI decision to grant a particular extension of time was wrong, what quality of error must be established to break the chain of causation?"
3. In practical terms this is encapsulated in the submission made in paragraph 296 of Brompton's Closing (and paragraph 374 for Hydrotite)."
The formulation still left something to be desired. For example, issue 1 did not record AA's case which raised the question of the causal link between the event which was the breach of duty and the extension of time. The question of the proposed point of principle was ultimately the subject of further written submissions made after the end of the hearings.
"5.1 | In case any dispute or difference shall arise between the Employer or the Architect/Supervising Officer on his behalf and the Contractor, either during the progress or after the completion or abandonment of the Works, as to | In case any dispute or difference shall arise between the Employer or the Architect/Supervising Officer on his behalf and the Contractor, either during the progress or after the completion or abandonment of the Works, as to |
5.1 | .1 | The construction of this Contract, or |
5.1 | .2 | Any matter or thing of whatsoever nature arising hereunder or in connection herewith including any matter or thing left by this Contract to the discretion of the Architect/Supervising Officer or the withholding by the Architect/Supervising Officer of any certificate to which the Contractor may claim to be entitled or the adjustment of the Contract Sum under clause 30.8.2 or the rights and liabilities of the parties under clauses 27, 28, 32 or 33 or unreasonable withholding of consent or agreement by the Employer or the Architect/Supervising Officer on his behalf or by the Contractor, but |
5.1 | .3 | Excluding any dispute or difference under clause 19A, under clause 31 to the extent provided in clause 31.9 and under clause 3 of the VAT Agreement, |
then such dispute or difference shall be and is hereby referred to the arbitration and final decision of a person to be agreed between the parties to act as Arbitrator, or, failing agreement within 14 days after either party has given to the other a written request to concur in the appointment of an Arbitrator, a person to be appointed on the request of either party by the President or a Vice-President for the time being of the Royal Institute of British Architects. |
then such dispute or difference shall be and is hereby referred to the arbitration and final decision of a person to be agreed between the parties to act as Arbitrator, or, failing agreement within 14 days after either party has given to the other a written request to concur in the appointment of an Arbitrator, a person to be appointed on the request of either party by the President or a Vice-President for the time being of the Royal Institute of British Architects. |
|
5.2 | Such reference, except |
Such reference, except |
.1 | On article 3 or article 4; or |
|
.2 | On the questions | |
Whether or not the issue of an instruction is empowered by the Conditions; or whether or not a certificate has been improperly withheld; or whether a certificate is not in accordance with the Conditions; or |
||
.3 | On any dispute or difference under clause 4.1 in regard to a reasonable objection by the Contractor, and clauses 26, 32 and 33, |
|
shall not be opened until after Practical Completion or alleged Practical Completion of the Works or termination or alleged termination of the Contractor's employment under this Contract or abandonment of the Works, unless with the written consent of the Employer or the Architect/Supervising Officer on his behalf and the Contractor. |
shall not be opened until after Practical Completion or alleged Practical Completion of the Works or termination or alleged termination of the Contractor's employment under this Contract or abandonment of the Works, unless with the written consent of the Employer or the Architect/Supervising Officer on his behalf and the Contractor. |
|
5.3 | Subject to the provisions of clauses 4.2, 30.9, 38.4.3, 39.5.3 and 40.5 the Arbitrator shall, without prejudice to the generality of his powers, have power to direct such measurements and/or valuations as may in his opinion be desirable in order to determine the rights of the parties and to ascertain and award any sum which ought to have been the subject of or included in any certificate and to open up, review and revise any certificate, opinion, decision, requirement or notice and to determine all matters in dispute which shall be submitted to him in the same manner as if no such certificate, opinion, decision, requirement or notice had been given. |
Subject to the provisions of clauses 4.2, 30.9, 38.4.3, 39.5.3 and 40.5 the Arbitrator shall, without prejudice to the generality of his powers, have power to direct such measurements and/or valuations as may in his opinion be desirable in order to determine the rights of the parties and to ascertain and award any sum which ought to have been the subject of or included in any certificate and to open up, review and revise any certificate, opinion, decision, requirement or notice and to determine all matters in dispute which shall be submitted to him in the same manner as if no such certificate, opinion, decision, requirement or notice had been given. |
5.4 | The award of such Arbitrator shall be final and binding on the parties. .." |
The award of such Arbitrator shall be final and binding on the parties. .." |
"The authorities
We had cited to us Galoo Ltd (in liquidation) v Bright Grahame Murray (a firm) [1994] 1 WLR 1360 in particular Glidewell LJ's judgment from 1369 to 1375 of the latter report. In that case it was agreed that in the context of that case the principles applicable to liability in either contract or tort are the same (1369H). It is common ground that in assessing liability under s. 6 of the Water Act 1981, the court is not applying any different principles. At the end of the passage at 1374H Glidewell LJ poses the question:
"How does the court decide whether the breach of duty was the cause of the loss or merely the occasion for the loss?"
and he answers it by applying the Australian decisions to which he had been referred "By the application of the court's common sense".
In a recent Lecture "Common Sense and Causing Loss" given on 15 June 1999 Lord Hoffmann has suggested that simple appeals to common sense do not provide the answer. He argued that in answering the question whether a certain loss or damage was caused by a breach of duty, what was really required was to identify the right question as to what damage the duty was meant to guard against or from which a party was intended to be protected.
Mr Allen relied on The "Sivand" [1998] 2 Lloyd's Rep 97, and in particular the judgment of Hobhouse LJ in that case. It is of interest that he commences his judgment by saying that:
"As is often the case, once the question has been correctly identified, the answer to be given to that question is straightforward."
In that case the plaintiffs' harbour works including dolphins had been damaged. They employed a contractor to repair the damage. During the repair work a jack-up barge collapsed due to unforeseeable sea-bed conditions. The plaintiffs under the contract were liable to pay the extra costs of the sub-contractor. Hobhouse LJ's legal analysis is at page 107 concisely summarised under five heads as follows:
"(1) The defendants negligently and in breach of the duty of care which they owed to the plaintiffs, damaged the plaintiffs' property (the harbour works including the dolphins) thereby causing the plaintiffs loss.
(2) The plaintiffs' cause of action was then complete and the sole remaining question was the assessment of the plaintiffs' loss.
(3) The plaintiffs were under a duty to mitigate their loss and in reasonable mitigation chose to employ the contractors on the ICE terms to carry out the necessary repair work.
(4) The cost of this mitigation was the sums which the plaintiffs became liable to pay to the contractors for the carrying out of the repair work under the ICE contract. This cost included the sum of £178,2350.47.
(5) The defendants' liability in damages to the plaintiffs includes the expenditure which the plaintiffs have thus incurred in the reasonable mitigation of their loss. There is no allegation that the steps which the plaintiffs took increased rather than mitigated their loss but, even if they had, this would have made no difference to the defendants' liability provided that the plaintiffs had acted reasonably."
Pill LJ put the matter this way. He would accept the above legal analysis but thought there should be added to proposition 2 the words "for which the defendants are responsible". His conclusion at page 109 was:
"The defendants accept that the damage to the harbour works caused by their vessel had to be made good and that it was reasonable for the plaintiffs to contract with contractors who would do the work on the terms of the ICE contract. Clause 12 of the conditions of the relevant contract provides an entitlement to additional remuneration for the contractor who encounters physical conditions which could not reasonably have been foreseen by an experienced contractor. Having conceded that it was reasonable for the victim of the tort to accept a condition involving a contractual liability for unforeseen physical conditions, the defendants seek to argue that they are not liable for the contractual liability upon the plaintiffs held to result from the operation of the clause."
"Four issues need to be addressed. Was the intervening conduct of the third party such as to render the original wrongdoing merely a part of the history of events? Was the third party's conduct either deliberate or wholly unreasonable? Was the intervention foreseeable? Is the third party wholly independent of the defendant i.e. does the defendant owe the claimant any responsibility for the conduct of that intervening third party? ...
The most that can be said is that deliberate interventions are more likely to breach the chain of causation than negligent acts, negligent conduct is more likely to constitute a novus actus than non-negligent conduct, and positive acts are more likely to operate as novus actus than omissions"
Later Buxton LJ said in another part of the judgment:
"It was not suggested by Mr Crowther, and was not held by the judge, that Delyn had actually been negligent. Indeed, the passage that I quoted from his judgment establishes that he would have come to the conclusion that he did, even if Delyn had been positively found merely to have been incompetent or ill-advised or ill-judged, rather than negligent. This combination of circumstances falls far short of what is required in law to constitute a successful defence of novus actus interveniens. To some extent that is a matter of impression but only to some extent. What has to be demonstrated, in my judgement, is that the intervention has, as Cooke J said, turned the negligent act of the defendant into a matter of surrounding circumstances. That is plainly not this case. What was done was in direct response to a hazardous situation created by the defendants. It was at their peril that an intervener might not act with full competence and might cause some further or different injury. That is apparently, on the evidence before the judge, what happened in this case, but it does not exculpate in law, in the circumstances of this case, the defendants from the consequences of their original act of negligence. The point is a short one. But I am satisfied that the judge approached it too shortly and approached it on a too mechanistic and narrow view of the doctrine of novus actus."
These extracts show that, even if WGI's decisions had been "incompetent or ill-advised or ill-judged", the chain of causation would not have been broken, unless they had been negligent. Thus even the admitted error of two weeks may be ignored. I answer the questions posed in Clerk & Lindsell as follows, though not in quite the same order. The intervening conduct did not render the breaches of duty part of the history; one of the reasons for the existence of the duties (certainly AA's) was to avoid that subsequent history, and, as such, was foreseeable. WGI's conduct was obviously deliberate, but not in the sense of a deliberate intervention, as it was required under the contract. It was not the act of an independent intervener, as WGI was appointed by RBH. It was certainly not wholly unreasonable. Accordingly, applying that approach, the chain of causation was not broken.
Summary of Conclusions
Blue Land
Advice Claim
Timing Claim
Quality of Drawings
Hydrotite
Causation