England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Taylor Woodrow Holdings Ltd v George Wimpey Southern Counties Ltd Rev 1 [2006] EWHC 1693 (TCC) (03 July 2006) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2006/1693.html Cite as: [2006] 2 All ER (Comm) 735, [2006] EWHC 1693 (TCC), [2006] BLR 377, 110 Con LR 169, [2006] CILL 2375, [2006] ArbLR 61 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
B e f o r e :
____________________
(1) TAYLOR WOODROW HOLDINGS LIMITED | ||
(2) GEORGE WIMPEY SOUTHERN COUNTIES LIMITED | Claimants | |
- and - | ||
BARNES & ELLIOTT LIMITED | Defendant |
____________________
Harry Counsell &Co.
Clifford's Inn, Fetter Lane, London, EC4A 1LD
Telephone: 020 7269 0370
MR RICHARD FERNYHOUGH QC and MISS ELIZABETH REPPER (instructed by Fenwick Elliott LLP)appeared for the Defendant
____________________
Crown Copyright ©
MR JUSTICE JACKSON:
Part 1 – Introduction
"(1) Unless otherwise agreed by the parties the court may on the application of a party to arbitral proceedings (upon notice to the other parties) determine any question of law arising in the course of the proceedings which the court is satisfied substantially affects the rights of one or more of the parties. An agreement to dispense with reasons for the tribunal's award shall be considered an agreement to exclude the court's jurisdiction under this section.
(2) An application under this section shall not be considered unless:
(a) it is made with the agreement of all the other parties, or
(b) it is made with the permission of the tribunal and the court is satisfied
(i) that the determination of the question is likely to produce substantial savings in costs, and
(ii) that the application was made without delay.
(3) The application shall identify the question of law to be determined and unless made with the agreement of all the other parties to the proceedings shall state the grounds on which it is said that the question should be decided by the court".
Part 2 – The facts
"As discussed over the telephone on the day following our re-inspection, which was carried out on 13th December, there is still a considerable amount of water entering the structure via defects to the temporary roof coverings.
This has resulted in saturation to at least 60% of the roofing timbers with resulting wet rot and dry rot growth affecting wall plates, valley rafters, common rafters, and roof boarding. There could also be a possible problem with corrosion to reinforcement in concrete slab. Where water has penetrated through into the first floor areas pooling has occurred on floor boarded areas providing a gradual uptake of moisture in the surrounding fabric due to recycling condensation affecting joinery timbers and built in joist ends.
The rainwater penetration has percolated through to the ground floor areas resulting in excessively high moisture readings in all walls, flooring and joinery timbers. Where areas of floor boarding had been lifted to enable a sample inspection of the sub-floor timbers it was generally noted that the moisture content to the timber within the voids together with a high relative humidity are ideal conditions to culture Dry Rot. Three additional outbreaks of Dry Rot were recorded and have occurred in the time between our initial inspection and our most recent i.e. two weeks.
The problems that need to be overcome immediately are as follows:-
1. Prevent further water ingress and remove debris and insulation from roof void.
2. Remove fungal affected timbers and all superfluous timbers.
3. Lift floor board to all areas and levels particularly around the perimeter to the room to encourage ventilation.
4. Expose all built in joist ends.
5. Provide natural light and ventilation via existing window openings to reduce the incidents of trapped vapour and assist in drying out the fabric.
6. Ideally remove plaster from walls to assist drying to the main structure.
7. Monitor buildings during the moth-balling period at least monthly".
"Provide and maintain during the execution of the works all incidental shoring, strutting, needling and other supports as may be necessary to preserve the stability of the existing structures on the site or adjoining that may be endangered or affected by the works.
Support existing structure as necessary during cutting of new openings or replacement of structural parts.
Do not remove supports until new work is strong enough to support the existing structure".
"D1.1 The Employers seeks the Contractors' Proposals which achieve uniformity and consistency of final external appearance.
D1.2 Whilst the exterior of the building requires improvement in terms of cleaning and minor repair, together with the removal of redundant fixtures, fittings and services the character of the building should be retained and enhanced wherever possible.
D1.3 Whilst the Employers wishes all discolouration and staining to brick and stone surfaces to be removed back to sound original base wherever possible the building should not be "over cleaned"...
D1.7 The Contractor is to note the need for repointing and isolated brick repair. The Employer does not require each and every damaged brick to be cut out and replaced. Where very minor damage exists it is acceptable to take no action in order that the character and ageing of the building is not unnecessarily jeopardised. Where more significant localised damage exists execute a localised repair either by rubbing back the surface of the brick or carrying out a specialist epoxy material based repair.
D1.8 Where severity of damage dictates that the bricks must be replaced carry outwork using reclaim materials wherever possible ensuring that pointing type and material matches existing sound detail. Where repointing is required avoid a patchwork appearance to completed walls/elevations as far as practical".
"Our proposals have been fully and carefully considered, taking into account the Employers' Requirements and the footprint of the existing buildings. We believe that our solutions offer the quality of new accommodation, whilst maintaining he character of the buildings and their surroundings.
We have made numerous visits to sites, gaining advice from specialists where appropriate, and obtaining further information via independent investigation. Our belief is that we have established a competitive tender covering all aspects of work required".
"Demolition and Alterations
Carefully demolish areas of the buildings not required for the development, and place all debris within the floor voids.
Infill areas of the perimeter where demolition has taken place, matching the existing as near as possible. Facing Bricks used to be Charnwood Multi imperial bricks, similar to those being used in adjacent buildings.
Remove internal walls where not required, placing all debris within the floor void.
Allow for all temporary propping required to support the roof slab prior to installation of new steel.
Remove all existing windows and doors, adapt openings as required, and make good to receive new.
Remove all existing roof coverings.
Remove existing chimney breasts where necessary, and provide permanent support to the stacks at roof level.
Remove all existing stairs.
Remove all existing ceiling finishes, wall finishes and the like.
Remove any remaining services, fittings and fixtures, both internally and externally.
Allow for the specialist removal of asbestos in accordance with the Asbestos report provided with the tender documentation...
Roof
Allow for removal of defective roof timbers and replace with new. Our assessment of the quantity that will need to be replaced, bearing in mind the limited access to the roof, is no more than 30%. (See Clarifications)
Allow for treating all roof timbers against future rot growth and damage.
Provide new felt, battens and Spanish slates, including all hips, valleys, ridges and the like, and 100mm rockwool rollbatts, or similar.
Allow for removing all existing guttering, rainwater pipes, fascias and soffits, and replace with new UPVC. Guttering to incorporate a leaf mesh. Fascias to include vents for roof space ventilation...
External Walls
Allow for cutting out severely defective bricks and replacing with new, as described above – 30% of total elevation area. (See clarifications)
Allow for raking out and repointing mortar joints, again where severely defective – 25% of total elevation area. (See clarifications)
Prepare 2nr test panels 2.00m x 2.00m including stone and brick detailing, to illustrate level of cleaning and repair that will be offered.
Allow for fine sand blasting of the elevations to remove dirt, algae and the like, as being used on the adjacent clock tower building.
Chemically inject the existing external walls with damp proof course to the perimeter of each block.
reat the cavity to prevent future damp growth and damage".
"1. We have only allowed for structural works as specifically detailed in these proposals. Whilst we have made several visits to the site, including additional investigation works to the roof slab, and carefully inspected the documentation available, we are unable to accept responsibility should the structure not be in accordance with this information once we commence on site.
2. Our detailed inspection of the elevations has been the basis of our assessment on the repairs required. However, since we have been unable to view at high level, or cannot be certain of the cleaning effect on the brickwork, any repairs, repointing and the like required over and above the % allowed may be subject to additional cost. We would be pleased to discuss this matter with you further should our offer be of interest".
"Further to your tender for the above project can you please confirm the following...
- Remove structural and repair percentage clarifications and take risk on the percentage replacement of roof trusses and the percentage for repairs, repointing etc.
Can you let me have the implications of the foregoing before Friday please".
"With regard to removing our percentage clarifications for the structural and repairs, and for us to take the risk, we would request further time on this matter. You will appreciate that during the limited time available during the Tender Period we have given a considered view on the extent of works required. We would be happy to re-assess our provisions with a view to taking the risk on these elements, but require the opportunity to revisit the site and our assessments before commitment".
"Further to your faxed letter of 19th June I would make the following observations and comments...
- With respect to the provisional sum of £180,000.00 included for external repairs it is confirmed that sufficient scaffold has been evaluated and included within the tender to carry out works to the aforementioned valley. Please provide a Schedule of Rates for additional scaffolding/hire that may arise should additional repair works in excess of the foregoing sum be instructed. Please confirm also that the rates quoted for repair works etc. are inclusive of an addition for profit and overheads".
"Further to your fax dated 19th June in response to our letter of the same date we respond as follows...
- We confirm that our Tender does include sufficient scaffolding to carry out the £180,000.00 of external façade repairs/cleaning. We enclose a Schedule of Rates for additional hire of scaffolding should this sum be exceeded.
- We also confirm that the rates provided for the repairs/cleaning are inclusive of overheads and profit".
"Following our telephone conversation, we confirm that bullet point 8 in our letter dated 19th June removes our Tender Qualification regarding the existing structure as it is now covered by the Provisional Sum of £180,000.00".
"Further to your faxed letter of 27th June 2000 and the meeting at Taywood Homes' offices earlier this week I would confirm that the Tender Qualification regarding the existing structure (which for the avoidance of doubt is deemed to be Clarification Item 1 included towards the end of section 5 – Design Proposals within your original tender submission document) is not deemed to be removed by virtue of the inclusion of the Provisional Sum which only covers external repair works.
Can you please confirm that Tender Clarification Item 1 regarding the existing structure is deemed to be removed".
"In response to your fax dated 14th July 2000, we confirm that we have included for all structural works necessary following alterations made to the buildings by us in order to complete the development proposed.
We confirm that this allowance is within our tender, and will not form part of the works covered by the Provisional Sum for external façade repairs and cleaning".
That concluded the series of correspondence concerning TC1 and TC2.
"This statement is to provide clear understanding concerning the hierarchy of information that is included within the Contract Documents relating to the Employers' Requirements and Contractor's Proposals.
Any detailed information drawing or schedule and the like included within the Contract Documents that have conflicting issues/reference elsewhere within the contract documentation must be read in a chronological order with the latest date issue/reference taking precedence".
"47. It was made clear from the conclusion to this exchange and particularly by reference to the words placed in emphasis above, that the Respondents retained the risk of those unforeseen works to be existing structure of the building which might be necessary before, or as a consequence of, the specified works of design, refurbishment and conversion could proceed. This was not a transfer of all the structural risk in the Contract but it was a transfer of risk in relation to these particular structural works. The Claimant was accepting to carry out within its price all structural works which would be a necessary component of the specified works but not structural works (or demolition or other works) which were, at that point in time, undefined and unforeseen.
48. All the correspondence referred to above forms part of the contract documentation.
49. At that point in time no further detailed investigations into the condition of the building had been carried out by the Respondents since the submission of the tender, and no relevant adjustment to the prices or programme allowances contained within the Claimant's tender had been made, or could reasonably have been made.
50. Therefore the unforeseen structural works to the underlying fabric of the Long Grove buildings carried out prior to performing the specified contract works constitute a change in the Employers' Requirements which require evaluation under Clause 12 of the Contract".
Part 3 – Present Proceedings
"1. Did the Employers retain the risk of unforeseen works to the existing structure of the building which might be necessary (a) before the specified works of design, refurbishment and conversion could proceed, or (b) as a consequence of the said works?
2. Did the allegedly unforeseen structural works to the underlying fabric of the buildings carried out prior to, during or after performing the specified contract works constitute a change in the Employers' Requirements which require evaluation under Clause 12 of the JCT WCD?"
Part 4 – The Contractor's preliminary objection
to this action proceeding
"The Parties hereby agree pursuant to S.45(2)(a) and S.69(2)(a) of the Arbitration Act 1996 that either party may (upon notice to the other party and to the arbitrator):
39B.4.1. apply to the court to determine any question of law arising in the course of this reference, and
39B.4.2 appeal to the courts on any question arising out of an award made in an arbitration under this arbitration agreement".
"The judge has to consider the application on its inherent merits. If he is not satisfied that the question of law proposed for determination ought to be determined at that stage he should refuse the application...
Section 2 is the successor in title to the old consultative case which more aptly describes its nature. Put colloquially the arbitrator or the parties nip down the road to pick the brains of one of Her Majesty's judges and, thus enlightened, resume the arbitration. It is essentially a speedy procedure designed to interrupt the arbitration to the minimum possible extent and it is an exception to the general rule that the courts do not intervene in the course of an arbitration".
Although much has changed in the law of arbitration since Babanaft was decided, in my view the passage just quoted from the judgment of Donaldson LJ is apposite to section 45 of the Arbitration Act 1996.
Part 5 - The Question of Law
"2.1 The Contractor shall upon and subject to the Conditions carry out and complete the Works referred to in the Employer's Requirements, the Contractor's Proposals (to which the Contract Sum Analysis is annexed), the Articles of Agreement, these Conditions and the Appendices in accordance with the aforementioned documents, and for that purpose shall complete the design of the Works including the selection of any specifications for any kinds and standards of the materials and goods and workmanship to be used in the construction of the Works so far as not described or stated in the Employer's Requirements or the Contractor's Proposals...
2.5.1 Insofar as the design of the Works is comprised in the Contractor's Proposals and in what the Contractor is to complete under clause 2 and in accordance with the Employer's Requirements and the Conditions (including any further design which the Contractor is required to carry out as a result of a change in the Employer's Requirements), the Contractor shall have in respect of any defect or insufficiency in such design the like liability to the Employer, whether under the statute or otherwise, as would an architect or, as the case may be, other appropriate professional designer holding himself out as competent to take on work for such design who, acting independently under a separate contract with the Employer, had supplied such design for or in connection with works to be carried out and completed by a building contractor not being the supplier of the design.
2.5.2 Where and to the extent that this Contract involves the Contractor in taking on work for or in connection with the provisions of a dwelling or dwellings the reference in clause 2.5.1 to the Contractor's liability includes liability under the Defective Premises Act 1972..."
(1) This seems to me to be the natural and obvious interpretation of the letter in the context of the surrounding correspondence.
(2) The phrase "all structural works necessary following alterations made to the buildings by us in order to complete the development proposed" must embrace all structural works necessary in order to achieve a completed development. It cannot be limited to some only of the structural works which were necessary, as suggested by Mr. Fernyhough.
(3) The whole tenor of the Contractor's letter suggests that the Contractor is agreeing with LFP's letter dated 14th July. There is no suggestion that the Contractor is putting forward a new and restrictive counter-proposal.
(4) The second sentence of the Contractor's letter reinforces the first sentence. The second sentence makes it clear that the provisional sum of £180,000.00 relates only to works to the external façade (i.e. what was formerly the subject matter of TC2).
Part 6 – Conclusion
(End of Judgment)