BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £5, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> AC Yule & Son Ltd v Speedwell Roofing & Cladding Ltd [2007] EWHC 1360 (TCC) (31 May 2007) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2007/1360.html Cite as: [2007] EWHC 1360 (TCC), [2007] BLR 499, [2007] CILL 2489 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Fetter Lane London, EC4 |
||
B e f o r e :
____________________
AC YULE & SON LIMITED |
Claimant |
|
- and - |
||
SPEEDWELL ROOFING & CLADDING LIMITED |
Defendant |
____________________
6th Floor, 12-14 New Fetter Lane, London EC4A 1AG
Telephone No: 020 7936 6000. Fax No: 020 7427 0093
DX 410 LDE [email protected]
MR. SIMON HENDERSON (instructed by Weightmans) for the Defendant
____________________
Crown Copyright ©
HIS HONOUR JUDGE PETER COULSON QC:
"It is only too easy in a complex case for a party who is dissatisfied with the decision of an adjudicator to comb through the adjudicator's reasons and identify points upon which to present a challenge under the labels 'excess of jurisdiction' or 'breach of natural justice' ... In short, in the overwhelming majority of cases, the proper course for the party who is unsuccessful in an adjudication under the scheme must be to pay the amount that he has been ordered to pay by the adjudicator. If he does not accept the adjudicator's decision is correct, whether on the facts or in law, he can take legal or arbitration proceedings in order to establish the true position to seek to challenge the adjudicator's decision on the ground that he has exceeded his jurisdiction or breached the rules of natural justice (save in the plainest cases) is likely to lead to a substantial waste of time and expense ..."
(a) In Barnes and Elliot Ltd. v Taylor Woodrow Holdings Ltd. [2004] BLR 117, His Honour Judge Humphrey Lloyd QC differentiated between the completion of the decision itself, which he said had to be completed within the 28 days or the agreed extended period, and its subsequent communication to the parties which could, he said, occur a day or two days thereafter.
(b) In Ritchie Brothers (PWC) Ltd v David Philp (Commercials) [2005] BLR 384, the Court of Session in Scotland, the only appellate court to consider this point thus far, concluded by a majority that the adjudicator's jurisdiction expired at the end of the 28 days (or any agreed extended period) and that an adjudicator's failure to reach his decision within that time limit rendered any subsequent decision a nullity. Lord Nimmo Smith said, in an admirably succinct judgment:
"If a speedy outcome is an objective it is best achieved by adherence to strict time limits. Likewise, if certainty is an objective, it is not achieved by leaving the parties in doubt as to where they stand after the expiry of the 28-day period. These considerations reinforce the view that paragraph 19 [of the Scheme] means exactly what it says, so that it is not open to an adjudicator to purport to reach his decision after the expiry of the time limit."
(c) In reaching their decision in Ritchie, the court expressed the view that Simons Construction Ltd v Aardvark Developments Ltd [2004] BLR 117, in which His Honour Judge Richard Seymour QC concluded that a decision was valid whenever it was completed, provided that no further adjudication had been commenced in the meantime, was wrongly decided.
(d) In Hart Investments Ltd v Fidler and another [2006] EWHC 2857 (TCC) and Cubitt Building & Interiors Limited v Fleetglade Limited [2006] EWHC 3413 (TCC), I concluded that the word "shall" in the 1996 Act and the Scheme was mandatory. In the latter case I held that the obligation at paragraph 19 of the Scheme, that the adjudicator "shall" reach his decision not later than 28 days, or any extended time, meant what it said, such that the adjudicator was obliged to complete his decision within the 28 days or any extended period, no more and no less. For what it is worth, I expressed the view that Ritchie was correctly decided.
(e) In Epping Electrical Company Ltd. v. Briggs and Forrester (Plumbing Services) Limited [2007] BLR 1126, and Aveat Heating Ltd. v Jerram Falkus Construction Ltd [2007] EWHC 121 (TCC), His Honour Judge Havery QC also concluded that Ritchie was right, and that in any event, given that it was a decision of an appellate court, it was appropriate for him to follow it. He therefore concluded that the decision had to be completed within the 28 days or any agreed extended period.
"In addition, hard copy of correspondence (and other documents) is only due to be received tomorrow 28th March 2007 and we request time to respond to these if you consider it appropriate".
"Communication No. 30.
Gentlemen.
I agree that SR [Speedwell] require time to respond until Friday [30th March] at noon and I require the parties to agree that I have two more days to issue my Decision."
In his written statement provided for the purposes of these enforcement proceedings Mr. Bunton said of this e-mail:
"10. I wrote to the parties on the same day, Tuesday, 27th March 2007 timed at 16.47 p.m. I agreed that Speedwell required time and I stated that 'I require the parties to agree that I have two more days to issue my decision'. This would mean that the date of my decision was now to be no later than 5th April 2007.
"11. I thought I was being clear in my directions, namely that Speedwell should be given time to respond and that I required more time to reach my decision. Both elements were inextricably linked and were not intended to be severable. On 28th March 2007 Dickinson Dees consented to extending the time for making my decision to 5th April 2007."
(a) On 29th March 2007 the adjudicator asked Speedwell to clarify various matters;
(b) On 30th March 2007 at 9.14 a.m. the adjudicator said he had "concluded my audit trail of the information sent to me as part of Yule's response number 10". He said he expected Speedwell to comment on that material "today".
(c) At 12.45 p.m. on the same day, Speedwell provided those comments. By 13.52 p.m. the adjudicator had read those responses and raised queries of both parties arising out of them. Although the adjudicator sought responses to those queries that afternoon, both Yule and Speedwell made clear to him that that would not be possible. Since 30th March was a Friday, this meant that the parties were saying that they could not respond to his latest request for information until Monday, 2nd April 2007 at the earliest.
(d) On 2nd April at 11.02 a.m. the adjudicator asked Speedwell for copies of certain invoices. This request was a further reflection of his request for further information made on 30th March. Speedwell promised those copy invoices by that afternoon. In fact, they were not provided until 12.30 p.m. on the following day, 3rd April 2007. Moreover, they ran to about 65 pages. They were not provided to Yule until later in the afternoon of 3rd April. At 14.27 p.m. on 3rd April, Yule reserved their position with the adjudicator in respect of this late documentation. Yule also provided the information that had been requested by the adjudicator on 30th March.
(e) At 8.55 a.m. on 4th April 2007, the adjudicator indicated that he would provide his decision that day. There was no response to that e-mail by either party. There was certainly no response from Speedwell to say that this was or might be out of time.
(a) After the adjudicator's request they continued to participate in the adjudication.
(b) On 30th March they failed to respond to the adjudicator's request for information, thus causing a delay (along with Yule) until at least 2nd April.
(c) On 2nd April they promised further documentation that day, but caused delay by failing to provide that documentation until after noon on 3rd April 2007.
(d) They did not say on 3rd April, whilst they were providing copies of the 65 pages of invoices, that in their view this was the last day that the adjudicator had for completing his decision.
(e) They did not, on 4th April, challenge the adjudicator's stated intention to provide his decision that day.
"Nonetheless the dictum which I have cited seems to me to be most persuasive authority for the proposition that the duty necessary to found an estoppel by silence or acquiescence arises where 'a reasonable man would expect' the person against whom the estoppel is raised 'acting honestly and responsibly' to bring the true facts to the attention of the other party known by him to be under a mistake as to their respective rights and obligations."