BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Ruttle Plant Hire Ltd v The Secretary of State for the Environment, Food and Rural Affairs [2007] EWHC 1773 (TCC) (16 July 2007) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2007/1773.html Cite as: [2007] EWHC 1773 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
131-137 Fetter Lane London EC4A 1HD |
||
B e f o r e :
____________________
RUTTLE PLANT HIRE LIMITED |
Claimant |
|
- and - |
||
THE SECRETARY OF STATE FOR THE ENVIRONMENT, FOOD AND RURAL AFFAIRS
|
Defendant |
____________________
Cliffords Inn, Fetter Lane, London EC4A 1LD
Tel: 020 7269 0370; Fax: 020 7405 9884
____________________
____________________
Crown Copyright ©
MR JUSTICE JACKSON
Part 1: Introduction
Part 2: The Facts
"2. Was it a term of the contract between the parties that the claimant would deduct from its labour charges a 30-minute meal break per labourer or working foreman per day?
3. Was a term to be implied into the contract between the parties to the effect that the Claimant was entitled to charge the Defendant an additional 'administration charge' of 3% on labour charges?
3a. Is the work described by Mr Carrol at paragraphs 49 to 53 of his witness statement dated 20th October 2006 properly described as tasks carried out by 'working foremen' so as to permit the claimant to recover at the agreed labour rate of £17.70 per hour for that work under the express alternatively applied term pleaded at paragraph 62 of the defence and counterclaim or is the value of that work recoverable if at all elsewhere?
4. What, if any, plant hire rates were agreed between the parties for plant and equipment supplied by the claimant to the defendant to deal with the outbreak of CSF in Bury St Edmunds between August 2000 and June 2001?
5. In particular, did Clause 1A of the 'Schedule of Dayworks Carried Out Incidental to Contract Work' produced by the Federation of Civil Engineering Contractors, dated 22nd January 1990, form part of the agreement between the parties to the effect that for those items of plant which the claimant obtained from subcontractors, the claimant was only entitled to charge the defendant cost plus 12.5%?
6. If Clause 1A of the Schedule of Dayworks Carried Out Incidental to Contract Work produced by the Federation of Civil Engineering Contractors, dated 22nd January 1990, forms part of the agreement between the parties, is plant to be considered as having been obtained from subcontractors for the purposes of the schedule, in circumstances where plant was provided to Ruttle Plant Hire Limited from within the Ruttle Group?
7. It being agreed between the parties that the CPA model conditions for the hiring of plant applied to the contract, what is the meaning of clause 24 and what is its application to this contract?
8. If there was no concluded agreement between the parties as to the aforementioned plant hire rates, what would have been a reasonable rate for the claimant to have charged the defendant for plant and equipment supplied by it to the defendant to deal with the outbreak of CSF in Bury St Edmunds between August 2000 and June 2001?
9. Was the claimant contractually entitled to charge the defendant hourly hire rates for vehicles such as vans and station wagons where mileage was also charged for the use of those vehicles by foremen and senior staff?
10. Was the claimant contractually entitled to charge the defendant for plant (apart from scaffolding) that remained on site during close-down over holiday periods, e.g. Christmas and New Year, when there was no labour on site to use the plant? If so, at what rates and for what period of time was the claimant entitled to make such charges?
11. Was the claimant contractually entitled to charge the defendant for plant in the following circumstances:
(a) whilst plant remained unused on site at an infected premises pending demobilisation (for example, after cleansing and disinfection had been completed) and during the period when plant remained on site, there was no longer any labour on site to operate the plant;
(b) where the claimant has removed plant from an infected premises, stored it at another location pending demobilisation and, during the period when the plant was stored at another location, no use was being made of the plant;
(c) where the claimant has been instructed by the defendant to remove the plant from site as recorded in the defendant's APO/CPH records?
If so, at what rates and for what period of time was the claimant entitled to make such charges?
13. Was the claimant contractually entitled to charge the defendant for those items set out in paragraph 106 of the defence and part 20 counterclaim?
15. Pursuant to section 5 of the Late Payment of Commercial Debts
(Interest) Act 1998, should any interest be paid on any sums due to the claimant for the period from 30th May 2004 to 11th February 2005 and, if so, how much?"
"The expressly agreed contractual rates for plant were the full plant hire rates notified by the Claimant to the Defendant on 21st and 31st August 2000. Further, consequent upon this finding by the Court, the parties have agreed that:
(i) where an item of plant does not feature in the lists of plant rates notified by the Claimant to the Defendant on either 21st or 31st August but does nevertheless have a rate specified in the FCEC 1992 schedules, that rate should apply to that item of plant; and(ii) where an item of plant does not feature in the lists of plant rates notified by the Claimant to the Defendant on either 21st or 31st August and does not have a rate specified in the FCEC schedules, then in those circumstances a reasonable rate should be agreed between the parties for that item of plant based upon industry custom and practice."
The short term which is used commonly to refer to rates of the kind referred to in sub-paragraph (ii) is "Star Rates".
"Clause 24 of the CPA conditions sets out a procedure for terminating the contract between the Defendant and the Claimant. During the currency of that contract, reasonable notice for taking any specific piece of plant off hire was seven days notice in writing".
Part 3: The Present Application
"12A. The Preliminary Issue Judge found that the rates set out in the Claimant's faxes of 21 August 2000 and 31 August 2000 were the contractual rates to be paid by the Defendant to the Claimant in respect of the items of plant and equipment identified in those faxes.
"12B. Following and consequential upon such finding, the parties reached the following further agreement in relation to the rates to be paid in respect of items of plant or equipment which did not feature in the lists of plant rates notified by the Claimant to the Defendant on either 21 or 31 August:(1) Where a rate is specified in the FCEC 1992 schedules in respect of any item of plant or equipment, that rate should apply to that item of plant;
(2) Where no rate is specified in the FCEC 1992 schedules in respect of any item of plant or equipment, a reasonable rate should be agreed between the parties for that item of plant based upon industry custom and practice. Such rates have been referred to by the parties previously and are referred to in this statement of case as 'star rates'. As found by the Preliminary Issue Judge, the parties expressly agreed. a number of star rates in August 2000, in that some of the rates specified in the faxes of 21 and 31 August 2000 were star rates because they related to items of plant or equipment for which no rate is specified in the FCEC 1992 Schedules. Paragraph I2C below sets out the Claimant's case as to the manner in which those star rates which have not yet been agreed ('outstanding star rates') should be arrived at.
The said agreements were incorporated by consent into the Preliminary Issue Judge's order made at the conclusion of the trial.
I2C. The Claimant's case on outstanding star rates is that a reasonable rate for each of the relevant items of plant or equipment is the same rate as the star rate agreed by the parties for the same or a similar item of plant or equipment in respect of the FMD Works. The Claimant avers that the only industry custom and practice that was applicable, relevant or comparable to the CSF Works was that adopted by these parties in respect of the FMD Works. In further support of its case, the Claimant relies on the fact that, where the parties specifically agreed star rates for items of plant hired to the Defendant for the CSF Works (namely the star rates contained in the faxes of 21 and 31 August faxes), such star rates were the same as the star rates agreed for the same or similar items of plant when such items of plant were hired to the Defendant for the FMD Works.
I2D. In the Final Account submitted to the Defendant in May 2007, particulars of which appear in paragraph 17 below, the Claimant has applied the approach set out in paragraph 12C above in arriving at the outstanding star rates.
Plant and other equipment - Charges Due for Failure to Give Notice to Off-Hire
12E. At the trial of the preliminary issues, it was an issue between the parties whether the Defendant was required to give the Claimant notice when the Defendant wished to off-hire the Claimant's plant or equipment and, if so, what the period of notice should have been. The Claimant contended that seven days' notice was required pursuant to Clause 24 of the CPA Conditions. The Preliminary Issue Judge found that Clause 24 set out a procedure for determining the contract between the parties, and not for determining the hire of any individual item of plant or equipment.
12F. The Preliminary Issue Judge went on to find that there was a requirement on the Defendant to give notice to the Claimant when it desired to off-hire any item of plant or equipment, in that a term was implied into the Contract requiring the Defendant to give the Claimant reasonable notice in the circumstances and context of the Contract was seven days ("the implied term concerning notice to off-hire").
12G. The Claimant's case is that, as at the date of the preliminary issue trial, it had not invoiced the Defendant for hire of plant and other equipment for any part of the seven-day notice to which it was entitled following receipt of the Defendant's instruction to take the item of plant or equipment off hire. Following the Preliminary Issue Judge's findings set out at paragraph 12F above, the Claimant submitted its Final Account to the Defendant on or about 4 May 2007, which includes charges, pursuant to the implied term concerning notice to off-hire, in respect of such seven days period for each item of plant or equipment hired to the Defendant. The submission to the Defendant of the Claimant's Final Account amounts to a demand for payment of the said sum. The Defendant's unparticularised case at the trial of the preliminary issues was (and it is understood still to be) that the Claimant did not charge the Defendant within the invoices specified in Appendix 3 to the Particulars of Claim for hire during periods following the giving by the Defendant of notice of off-hire of certain unspecified items of plant or equipment. The Claimant's case at the trial of the preliminary issue was and remains that this is not so and that there is no overlap between the plant hire charges contained in the invoices specified in Appendix 3 to the Particulars of Claim and the said further plant hire charges now contained with the Final Account. Subject to determination of this issue of the fact, the Claimant avers that the Defendant is liable to pay the said further plant hire charges as a consequence of the Preliminary Issue Judge's findings set out in paragraph 12F above.
…
16A. Alternatively, pursuant to regulation 7 of the 1998 Regulations, the payments outstanding under the Contract became due either (a) on the expiry of 7 days following the completion of the work to which the payment related or (b) on the making of a claim by the Claimant, whichever is the later.
l6B. Where, as in this case, the parties failed to provide any or any adequate mechanism for determining when payments became due under the Contract and/or when the final date for payment would be, the final date for the making of the payments outstanding is, pursuant to regulation 8(2) of the 1998 Regulations, 17 days from the date that the payment became due, as determined in accordance with paragraph 16 or paragraph 16A above."
Part 4: Are the Proposed Amendments Consequential on the Preliminary Issues Judgment?
"By condition 24, where the period of plant hire is indeterminate (as it was in this case), the contract is determinable by seven days notice in writing to the other party. In the event of the Hirer (i.e. the Defendant) desiring to terminate the contract and failing to give notice, hire for the period of the seven day notice period shall be chargeable at idle time rates in lieu of notice. The condition further provides that notice given by the Hirer to the Owner's driver or operator is not deemed to constitute sufficient notice to comply with this condition. It is averred that no such notice was ever given and in so far as the Claimant has not so far charged for hire at idle rates for all plant for seven days in lieu of notice following receipt of the Defendant's instructions to take the plant off hire such charges will be levied after the Court has determined the contractual basis for charging in due course".
Part 5: DEFRA's Grounds for Opposing the Amendments
"In trying this question, I believe I state the rule of the Court correctly when I say that, where a given matter becomes the subject of litigation in, and of adjudication by, a Court of competent jurisdiction, the Court requires the parties to that litigation to bring forward their whole case, and will not (except under special circumstances) permit the same parties to open the same subject of litigation in respect of matter which might have been brought forward as part of the subject in contest, but which was not brought forward, only because they have, from negligence, inadvertence, or even accident, omitted part of their case. The plea of res judicata applies, except in special cases, not only to points upon which the Court was actually required by the parties to form an opinion and pronounce a judgment, but to every point which properly belonged to the subject of litigation, and which the parties, exercising responsible diligence, might have brought forward at the time."
1. The rule in Henderson v Henderson, both as formulated by Sir James Wigram VC, and as recast by other judges over the last two centuries, is a rule focused upon re-litigation.
2. The mischief against which the rule is directed is the bringing of a second action, when the first action should have sufficed.
3. In all of the cases cited by counsel or unearthed by my own researches in which the Henderson rule has been applied, there have been at least two separate actions. So far as I can see, the Henderson rule has never been invoked as a ground for opposing amendment in the original action.
4. There is no need to extend the rule in Henderson v Henderson to the sphere of amendment applications. The powers of the Court to allow or disallow amendments are clearly set out in the Civil Procedure Rules. There already exists an established body of judicial authority to guide first instance judges who are faced with applications to amend. See White Book volume 1 paragraph 17.3.5. It is inappropriate to transplant into this field the Henderson line of cases which are focused upon a different juridical problem.
"(1). These Rules are a new procedural code with the overriding objective of enabling the Court to deal with cases justly.
(2). Dealing with a case justly includes, so far as practicable -
(a) ensuring that the parties are on an equal footing;
(b) saving expense;
(c) dealing with the case in ways which are proportionate:
(i) to the amount of money involved;
(ii) to the importance of the case;
(iii) to the complexity of the issues; and
(iv) to the financial position of each party;
(d) ensuring that it is dealt with expeditiously and fairly; and
(e) allotting to it an appropriate share of the court's resources, while taking into account the need to allot resources to other cases."
Part 6: Upon What Terms should the Amendments be Allowed?
1. Ruttle shall bear the costs of issuing the application to amend.
2. Ruttle shall bear the costs of re-re-amending the Particulars of Claim and the costs of consequential amendments to DEFRA's pleadings.
3. Each party shall bear its own costs of preparing for and attending the hearing of Ruttle's application for permission to amend.
Part 7: Conclusion