BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £5, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Vitpol Building Service v Samen [2008] EWHC 2283 (TCC) (16 September 2008) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2008/2283.html Cite as: [2008] EWHC 2283 (TCC), [2009] Bus LR D65, (2009) 25 Const LJ 319 |
[New search] [Printable RTF version] [Buy ICLR report: [2009] Bus LR D65] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
VITPOL BUILDING SERVICE |
Claimant |
|
- and - |
||
MICHAEL SAMEN |
Defendant |
____________________
6th Floor, 12-14 New Fetter Lane, London EC4A 1AG
Telephone No: 020 7936 6000. Fax No: 020 7427 0093
DX 410 LDE [email protected]
Ms Sian Mirchandani (instructed by Judge Sykes Frixou) for the Defendant
____________________
Crown Copyright ©
MR. JUSTICE COULSON:
(a) At a meeting on 12th January 2007, the parties agreed that the contract would incorporate the JCT Intermediate Form, 2005 edition (the IFC Form);(b) There were then further e-mails from the defendant's agent, Mr. Bennett, dated 13th and, more importantly, 18th January 2007, the latter of which is said to confirm the detailed arrangements that had been agreed at the meeting of 12th January;
(c) Thereafter, at a meeting on 21st February 2007, the claimant says that it was noted, in respect of the IFC Form, that the defendant had sent a letter confirming the contract, and that this was a reference back to the e-mail of 18th January.
"As agreed at the site meeting on 12th January 2007 ... the contract was to be by exchange of letter. On 18th January 2007 Mr. Samen sent such a letter by means of an e-mail to Vitpol in which he set out the agreed terms of the contract for the complete building renovation works at the property ... the scope of work was to be based on the schedule of works Rev 9 but in the event of dispute the IFC 2005 contract terms and conditions would apply ...".
In the same letter, the defendant's solicitors pointed out that "there was never any formal contract document ..."
(a) There was a letter of claim dated 21st December 2007;(b) There was a letter of response from the defendant dated 26th February 2008. That was the letter to which I have already referred at paragraph 4 above;
(c) There was a letter of reply from the claimant dated 25th May 2008.
There has not yet been a pre-action meeting but that is currently fixed for next week, 23rd September.
"6. There was never any formal contract document and therefore never any formally agreed terms of contract on the terms of the latest edition of the JCT standard form for Minor Works or the JCT Intermediate form of contract.
7. The Schedule of Works formed the basis of the defendant's invitation to tender and the terms therein were proposed conditions of contract. However, the proposed conditions did not become conditions of contract as no contract was ever agreed or executed.
8. Accordingly, it is the defendant's position that the claimant has no contractual entitlement to seek adjudication."
I note that, whilst paragraph 6 above reflects the defendant's letter of response of 26th February 2008, the contentions in paragraphs 7 and 8 go considerably further than anything that can be found in those letters.
"9.4. Other proceedings arising out of adjudication.
9.4.1 As noted above the TCC will also hear any applications for declaratory relief arising out of the commencement of a disputed adjudication. Commonly, these will concern…b) disputes over whether there is a written contract between the parties…."
She then goes on to say in her skeleton argument that in the present case there are no commenced adjudication proceedings, and that therefore the claim does not arise out of the commencement of a disputed adjudication and does not fall within the scope of this paragraph of the TCC guide. She therefore concludes that "the court is therefore without jurisdiction to hear this matter".
(a) Whilst, for the reasons noted above, there is a clear dispute as to the existence and terms of the contract, it is much less clear to me that that dispute would regard any significant oral evidence. The pre-action protocol material reflects a large degree of unanimity on the facts surrounding the alleged contract. No specific factual disputes have been identified. As things presently stand, I am bound to say that this looks to me like a relatively straightforward contract dispute where all (or almost all) of the relevant material will be found in the contemporaneous documents. In those circumstances paragraph 3.3.2 of the TCC guide would seem to apply, making this an appropriate case for Part 8.(b) However, I quite accept that, as things develop, that conclusion may turn out to be wrong, and there may be issues which can only be determined by the hearing of oral evidence. That again is not an uncommon situation in the TCC. However, if that situation arises, in my experience it is never necessary to make detailed amendments to the claim form, much less insist on the production of a second claim under Part 7. The TCC guide emphasizes that the court is there to deal, in a flexible way, with the disputes as they arise and develop. There have been a number of cases in this court in recent years, many presided over by Jackson J, in which the parties have agreed a hybrid between Parts 7 and 8 so as to ensure that any necessary oral evidence can be accommodated within the final hearing.
(a) The point that I have already made that the directions cannot start to be effective until after the pre-action protocol meeting, and a time for the parties to reflect; and(b) The requirement that any timetable must allow the defendant proper time to prepare his evidence to deal with the issues relating to the contract.