[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> J Murphy & Sons Ltd v Johnston Precast Ltd (Formerly Johnston Pipes Ltd) [No 2 Costs] [2008] EWHC 3104 (TCC) (16 December 2008) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2008/3104.html Cite as: [2008] EWHC 3104 (TCC), [2009] 5 Costs LR 745 |
[New search] [Printable RTF version] [Help]
QUEENS BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
J MURPHY & SONS LIMITED |
Claimant |
|
- and - |
||
JOHNSTON PRECAST LIMITED (formerly Johnston Pipes Limited) [No 2 - Costs] |
Defendant |
____________________
Ms Nerys Jefford QC (instructed by Mills and Reeve LLP) for the Defendant
Hearing Date: 10 December 2008
____________________
Crown Copyright ©
Mr Justice Coulson :
INTRODUCTION
a) There was a contract between the parties, but it did not contain the fitness for purpose term for which Murphy contended;
b) There was no breach of contract and/or no breach of duty on the part of JP;
c) The cause of the burst water main was not the result of any default on the part of JP; it was instead due to the existence of a large void in the foam concrete within the tunnel, for which Murphy themselves were responsible.
a) The nature and extent of the costs order to be made in JP's favour;
b) The amount of the interim payment in respect of those costs to be made by Murphy;
c) Whether or not JP are entitled to interest on those costs and, if so, whether that interest should be paid at an enhanced rate.
THE APPROPRIATE ORDER AS TO COSTS
"….is to require courts to be more ready to make separate orders to reflect the outcome of different issues. In doing this, the new Rules are reflecting a change of practice which has already started. It is now clear that too robust an application of the 'follow the event' principle encourages litigants to increase the costs of litigation, since it discourages litigants from being selective as to the points they take. If you recover all your costs as long as you win, you were encouraged to leave no stone overturned in your effort to do so"
INTERIM PAYMENT
"Where a party has won and has got an order for costs the only reason that he does not get the money straight away is because of the need for a detailed assessment. Nobody knows how much it should be. If the detailed assessment were carried out instantly he would get the order instantly. So the successful party is entitled to the money. In principle he ought to get it as soon as possible. It does not seem to me to be a good reason for keeping him out of some of his costs that you need time to work out the total amount. A payment for some lesser amount which you will almost certainly collect is a closer approximation to justice. So I hold that where a party is successful the court should on a rough and ready basis also normally order an amount to be paid on account, the amount being a lesser sum than the likely full amount".
INTEREST ON COSTS
"36.14-(1) This rule applies where upon judgment being entered-
a) A claimant fails to obtain a judgment more advantageous than the defendant's Part 36 offer; or
b) Judgment against the defendant is at least as advantageous to the claimant as the proposals contained in a claimant's part 36 offer.
2) Subject to paragraph (6), where rule 36.14(1)(a) applies, the court will, unless it considers it unjust to do so, order that the defendant is entitled to-
a) his costs from the date on which the relevant period expired; and
b) interest on those costs.
3) Subject to paragraph (6), where rule 36.14(1)(b) applies, the court will, unless it considers it unjust to do so, order that the claimant is entitled to-
a) interest on the whole or part of any sum of money (excluding interest) awarded at a rate not exceeding 10% above base rate for some or all of the periods starting with the date on which the relevant period expired;
b) his costs from the indemnity basis from the date on which the relevant period expired; and
c) interest on those costs at a rate not exceeding 10% above base rate…"
"In the light of all these authorities, it seems to me that the court has a broad discretion when deciding whether to award interest on costs from a date before judgment. That discretion must be exercised in accordance with the principles set out in CPR 44.3 and the court must take into account all the circumstances of the case, including such matters as the conduct of the parties and the degree to which a party has succeeded. Further, the discretion must be exercised in accordance with the overriding objective of dealing with a case justly. I am unable to accept the submission that interest on costs should only be awarded in a case which is in some way out of the norm. I find no basis for that in the CPR and I believe it would provide an unwarranted fetter on the court's discretion. This conclusion is in my judgment supported by the decisions of the Court of Appeal in Powell and in Bim Kemi."
a) Should Murphy pay interest on JP's costs from the commencement of proceedings to the 10th December 2008?
b) If so, what is the appropriate rate of interest under CPR 44.3?
c) Should that rate of interest be increased ("enhanced") as a result of the offers referred to above and the provisions of CPR 36.14(2) and (3)?
CONCLUSIONS
18.