BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £5, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Enterprise Managed Services Ltd v McFadden Utilities Ltd [2010] EWHC 1506 (TCC) (23 June 2010) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2010/1506.html Cite as: [2011] Bus LR D11, [2010] EWHC 1506 (TCC) |
[New search] [Printable RTF version] [Buy ICLR report: [2011] Bus LR D11] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
ENTERPRISE MANAGED SERVICES LIMITED |
Claimant |
|
- and - |
||
TONY McFADDEN UTILITIES LIMITED |
Defendant |
____________________
Mark Chennells (instructed by Mishcon de Reya) for the Defendant
Hearing dates: 16 June 2010
____________________
Crown Copyright ©
Mr Justice Akenhead:
Introduction
"(a) Was the NLSDA Sub-Contract between Subterra and TML novated in favour of Enterprise?
(b) What rights and liabilities were the subject of the Deed of Assignment of 15th June 2009 between TML and Utilities?
(c) Was the Deed a valid assignment?
(d) Can Utilities as assignees adjudicate the NLSDA claim against Enterprise?
(e) Does the Adjudicator have the necessary jurisdiction to undertake this adjudication?"
On the first two of these issues, the learned judge decided in favour of TMUL in that he found that the NLSDA Sub-Contract was novated and that it was the net balance envisaged by Rule 4.90 of the Insolvency Rules which was assigned to TMUL by the liquidators of TML. Delete "However, on the three remaining issues, he effectively" and replace it with "On the third issue, he decided that whilst the right to an account and any payment arising on that account under Rule 4.90 of the Insolvency Rules had been validly assigned, none of the sub-contracts nor the right to make claims under or for breach of them had been assigned. On the two remaining issues, he"
"In my judgment, the adjudicator ought to have taken more of a grip on this adjudication at the start, and reached early views both as to jurisdiction and as to whether it could be dealt with fairly in the time period. Had he done so, I think it likely that for one, or maybe even both, of these reasons he would have concluded that the adjudication could not be properly or fairly progressed and that the right course was resignation. That would have obviously saved a good deal of time and money, not least the costs of these Part 8 proceedings which, as I understand it, are now put at the barely credible figure of £240,000. The fact that, as a matter of practicality and fairness, this claim was not suitable for the summary adjudication process only supports my conclusion that the reference to adjudication was inappropriate as a matter of law."
It seems clear that the adjudicator, in broad terms, had simply acceded to a course of action urged upon him by TMUL.
The Costs
"(a) conduct before, as well as during, the proceedings…
(b) whether it was reasonable for a party to raise, pursue or contest a particular allegation or issue;
(c) the manner in which the party has pursued or defended his case or a particular allegation or issue;
(d) whether a claimant who has succeeded in his claim, in whole or in part, exaggerated his claim.2 (CPR Part 44.3(5))
(a) The first step is obviously to determine which of the parties has been successful in overall terms; if one can not determine that, it may be that one needs to consider the issues-based approach.
(b) One needs to consider the overall context of the litigation, including the reasons which led to its genesis; that involves considering the conduct of the parties which led to the need for the litigation in the first place.
(c) The reasonableness, or unreasonableness, of each party taking the various points or issues upon which it lost, should be considered by the Court. The more unreasonable the position of the losing party, the more likely that, even if the court orders only standard, as opposed to indemnity, based costs, it will attach weight to this factor.
(d) Whilst one needs to have regard to the issues upon which each party has succeeded, a simple mathematical approach on the basis of the number of issues "won" by each party will often not be an appropriate basis for fixing the percentage; thus, simply because the overall successful party has won 3 out of 5 issues, should not mean automatically that it should recover 60% of its costs. One needs to have regard to the likely amount of resources applied as well as to the impact overall of the success or failure on the various issues.
(e) Similarly, the Court should be cautious about fixing a proportion by reference to the amount of time or space applied by the judge in his or her judgement to the issues upon which each party has been successful or unsuccessful. The judge may simply have had to take up more time and space in the written judgement to address what may be more complex issues. The fact that 80% of the judgement addresses a legal issue upon which the overall successful party lost should not, at least generally, mean that it can only recover 20% of its costs.
(f) The Court needs also to have regard to the fact that the overall unsuccessful party will have incurred cost in dealing with the issues upon which it has "won".
(g) Where the parties have put before the court summary costs bills for assessment, the Court can have regard to the likely cost and resource which each party will have applied in relation to the issues upon which they have won or lost.
(h) Where the parties can not put such information before the Court, and in any event, the Court must do the best that it can in fixing a proportion.
(a) There is no doubt that, overall, Enterprise has succeeded in the litigation. It has effectively succeeded in securing its strategic objective of ensuring that the adjudication could not legitimately go ahead.
(b) I do bear in mind the conduct of TMUL in not only unjustifiably but also prematurely in any event pursuing the adjudication and in not agreeing a full suspension of the adjudication whilst the Part 8 proceedings were pursued. That undoubtedly put, and must have been intended to put, tactical pressure on Enterprise. The points taken by Enterprise upon which it failed need to be looked at in that context.
(c) Whilst the novation issue, upon which TMUL "won", did involve the deployment by its solicitors of evidence, the large bulk of that evidence was not disputed and part of the issue involved a consideration of what inferences could sensibly be drawn from that undisputed evidence.
(d) So far as the validity of the assignment was concerned, this issue, although, again, TMUL "won" it, was on analysis simply part of a wider issue upon which Enterprise "won" namely, in the context of what was assigned, did the adjudicator in practice have jurisdiction? In any event, the issue relating to the validity of the assignment was one which did not and did not need to involve, so far as I can judge, a substantial application of resources.
(e) I do have regard to the fact that Enterprise had to commence and pursue these proceedings to ensure that the adjudication could not legitimately be continued. Although its pleaded case and position at the hearing went wider than was necessary, the basic costs of claim and hearing preparation would have had to have been incurred in any event.
(f) I have no doubt that some time and resource would have been saved and avoided if Enterprise had not pursued its arguments on the issues upon which it lost albeit that I do not consider that it acted unreasonably in pursuing those arguments. Enterprise would have had to have submitted evidence and documentation and incurred brief and other hearing fees in any event.
Decision