England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Caledonian Modular Ltd v Mar City Developments Ltd [2015] EWHC 1855 (TCC) (29 June 2015) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2015/1855.html Cite as: [2015] BLR 694, 160 Con LR 42, [2015] EWHC 1855 (TCC), [2015] CILL 3705, [2015] TCLR 6 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
CALEDONIAN MODULAR LTD |
Claimant |
|
- and – |
||
MAR CITY DEVELOPMENTS LTD |
Defendant |
____________________
Mr Christopher Lewis (instructed by Fenwick Elliott LLP) for the Defendant
Hearing Date: 19 June 2015
____________________
Crown Copyright ©
Mr Justice Coulson:
1. INTRODUCTION
2. THE CONTRACT
"110A Payment notices: contractual requirements
(1) A construction contract shall, in relation to every payment provided for by the contract –
a) require the payer or a specified person to give a notice complying with subsection (2) to the payee not later than five days after the payment due date, or
b) require the payee to give a notice complying with subsection (3) to the payer or a specified person not later than five days after the payment due date.
(2) A notice complies with this subsection if it specifies –
a) in a case where the notice is given by the payer –
i) the sum that the payer considers to be or to have been due at the payment due date in respect of the payment, and
ii) the basis on which that sum is calculated;
b) in a case where the notice is given by a specified person-
i) the sum that the payer or the specified person considers to be or to have been due at the payment due date in respect of the payment, and
ii) the basis on which that sum is calculated
(3) A notice complies with this subsection if it specifies -
a) the sum that the payee considers to be or to have been due at the payment due date in respect of the payment, and
b) the basis on which that sum is calculated.
(4) For the purposes of this section, it is immaterial that the sum referred to in subsection (2)(a) or (b) or (3)(a) may be zero.
(5) If or to the extent that a contact does not comply with subsection (1), the relevant provisions of the Scheme for Construction Contracts apply.
(6) In this and the following sections, in relation to any payment provided for by a construction contract –
'payee' means the person to whom the payment is due;
'payer' means the person from whom the payment is due;
'payment due date' means the date provided for by the contract as the date on which the payment is due;
'specified person' means a person specified in or determined in accordance with the provisions of the contract.
110B Payment notices: payee's notice in default of payer's notice
(1) This section applies in a case where, in relation to any payment provided for by a construction contract –
a) the contract requires the payer or a specified person to give the payee a notice complying with section 110A (2) not later than five days after the payment due date, but
b) notice is not given as so required
(2) Subject to subsection (4), the payee may give to the payer a notice complying with section 110A (3) at any time after the date on which the notice referred to in subsection (1)(a) was required by the contract to be given.
(3) Where pursuant to subsection (2) the payee gives a notice complying with section 110A(3), the final date for payment of the sum specified in the notice shall for all purposes be regarded as postponed by the same number of days as the number of days after the date referred to in subsection (2) that the notice was given.
(4) If –
a) the contract permits or requires the payee, before the date on which the notice referred to in sub-section (1)(a) is required by the contract to be given, to notify the payer or a specified person of –
i) the sum that the payee considers will become due on the payment due date in respect of the payment, and
ii) The basis on which that sum is calculated, and
b) The payee gives such notification in accordance with the contract, that notification is to be regarded as notice complying with section 110A(3) given pursuant to subsection (2) (and the payee may not give another such notice pursuant to that subsection).
111 Requirement to pay notified sum
(1) Subject as follows, where a payment is provided for by a construction contract, the payer must pay the notified sum (to the extent not already paid) on or before the final date for payment.
(2) For the purposes of this section, the 'notified sum' in relation to any payment provided for by a construction contract means –
a) In a case where a notice complying with section 110A(2) has been given pursuant to and in accordance with a requirement of the contract, the amount specified in that notice;
b) In a case where a notice complying with section 110A(3) has been given pursuant to and in accordance with a requirement of the contract, the amount specified in that notice;
c) In a case where a notice complying with section 110A(3) has been given pursuant to and in accordance with section 110B(2), the amount specified in that notice.
(3) The payer or a specified person may in accordance with this section give to the payee a notice of the payer's intention to pay less than the notified sum.
(4) A notice under subsection (3) must specify –
a) The sum that the payer considers to be due on the date the notice is served, and
b) The basis on which that sum is calculated.
It is immaterial for the purposes of this subsection that the sum referred to in paragraph (a) or (b) may be zero.
(5) A notice under subsection (3) –
a) Must be given not later than the prescribed period before the final date for payment, and
b) In a case referred to in subsection (2)(b) or (c), may not be given before the notice by reference to which the notified sum is determined.
(6) Where a notice is given under subsection (3), subsection (1) applies only in respect of the sum specified pursuant to subsection (4)(a).
(7) In subsection (5), 'prescribed period' means –
a) Such a period as the parties may agree, or
b) In the absence of such agreement, the period provided by the Scheme for Construction Contracts."
"Part II
Payment
Entitlement to and amount of stage payments
1. Where the parties to a relevant construction contract fail to agree -
(a) the amount of any instalment or stage or periodic payment for any work under the contract,
(b) the intervals at which, or circumstances in which, such payments become due under that contract, or
(c) both of the matters mentioned in sub-paragraphs (a) and (b) above, the relevant provisions of paragraphs 2-4 below shall apply.
2(1) The amount of any payment by way of instalments or stage or periodic payments in respect of a relevant period shall be the difference between the amount determined in accordance with sub-paragraph (2) and the amount determined in accordance with paragraph (3).
…
Dates for payment
…
4. Any payment of a kind mentioned in paragraph 2 above shall become due on whichever of the following dates occurs later –
(a) the expiry of 7 days following the relevant period mentioned in paragraph 2(1) above, or
(b) the making of a claim by the payee…
Interpretation
12. In this Part of the Scheme for Construction Contracts –
'Claim by the payee' means a written notice given by the party carrying out work under a construction contract to the other party specifying the amount of any payment or payments which he considers to be due and the basis on which it is, or they are calculated…
'Relevant period' means a period which is specified in, or is calculated by reference to the construction contract or where no such period is so specified or is so calculable, a period of 28 days…"
3. PROCEDURE
4. THE RELEVANT FACTUAL BACKGROUND
"Please find attached a document detailing my figures deemed acceptable for the Variation Items 20,31,33,36 – This is strictly in regards exclusively to Final Account negotiations with Peter Martin and Stephen Wightman…
I believe Variations 20,31,33,36 to be worth a total value of £125,792.87 less retention in direct comparison to your valuation and application of £261,216.04 – Variance of (£135,423.17)"
These four variations were all connected with the Combisafe system.
"Given your interim assessment below, please amend/update the current payment notice issued by Gareth [Waton] to take into account the interim assessed figure for the Combisafe hire of £125,792.87.
We ask that you review the instruction given on the variation 020 as issued and we have updated our account as attached."
It is this email, together with its attachments, which is now said by the claimant to amount to a new claim for an interim payment (no 16) and/or a payee's notice to the same effect.
"Re: posted update of the account, there is nothing in the paperfile but I can see from looking at the e-file that James [Stimpson] did an update on the upstream fa and appln as a result of the change of proprietary scaffold dates – previous summary went past 8th"
5. ADJUDICATION No 2
"40. I accept that this Application for Payment was early. It is common ground that the payment cycle is 28 days and this Application was made only 13 days after the previous Application.
41. Caledonian says it did not receive any Payment Notice in respect of this Application and on the 19th March 2015 it issued a Default Notice in the form of an invoice with an accompanying copy of the Application for Payment dated 13 February 2015.
42. The invoice itself referred to Application number 16 and the supporting documentation was still headed Application number 15.
43. On 26th March 2015 Mar City issued a Payless Notice. The covering letter sought to unravel the discrepancies on dates of application numbers.
44. I cannot see how Mar City can argue here that the Application was not valid because it was issued too early when they treated it as a valid application and issued a Payless Notice against it."
6. WERE THE DOCUMENTS SENT OF 13 FEBRUARY 2015 A VALID APPLICATION FOR INTERIM PAYMENT?