England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Petroleum Company of Trinidad and Tobago Ltd v Samsung Engineering Trinidad Co Ltd [2017] EWHC 3055 (TCC) (30 November 2017) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2017/3055.html Cite as: [2017] EWHC 3055 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT
Rolls Building, Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
____________________
Petroleum Company of Trinidad and Tobago Limited |
Claimant / Respondent in Arbitration |
|
- and - |
||
Samsung Engineering Trinidad Co. Limited |
Defendant / Claimant in Arbitration |
____________________
(instructed by AFA Law) for the Claimant
Mr Jonathan Acton Davis QC and Ms Felicity Dynes
(instructed by DLA Piper UK LLP) for the Defendant
Hearing date: 22 November 2017
____________________
Crown Copyright ©
The Hon. Mr Justice Coulson :
1. INTRODUCTION
2. THE THREE AGREEMENTS
"(a) CONTRACTOR acknowledges that a delay in completion of the WORK will cause damage to COMPANY, the amount of such damage being difficult to calculate with great precision. Therefore if any UNIT OF WORK has not achieved MECHANICAL COMPLETION on or before the relevant COMPLETION DATES, and may be extended pursuant to Article 3.5 CONTRACTOR shall pay COMPANY liquidated damages for each full calendar day of delay from 30 calendar days after the COMPLETION DATE until MECHANICAL COMPLETION in respect of each UNIT OF WORK is actually achieved, in the following per diem amounts:
UNIT OF WORK PER DIEM AMOUNT
CCR Platformer Complex US$ 90,000
New 66kV/12kV Substation US$ 15,000
(b) Any such liquidated damages may be recovered by COMPANY against the irrevocable performance bank guarantee provided by CONTRACTOR in accordance with Article 7.4 hereof or by taking credit against payments otherwise due to CONTRACTOR, or by some other method mutually agreed.
(c) In the event that CONTRACTOR does not attain the COMPLETION DATE set for each UNIT OF WORK then as the remedy for late completion COMPANY shall recover liquidated damages from CONTRACTOR at the applicable per diem amounts for each day until completion is attained as evidenced by MECHANICAL COMPLETION for each UNIT OF WORK, up to a maximum liability of ten percent (10%) of the CONTRACT PRICE."
"33.1 The Parties shall use their best efforts to settle amicably any dispute, controversy or claim arising out of related to the CONTRACT, or the breach, termination or invalidity of the said CONTRACT.
33.2 Any dispute, controversy or claim arising out of or related to the CONTRACT, or the breach, termination or invalidity of the said CONTRACT that cannot be settled amicably between the Parties shall be referred to mediation.
33.3 The mediator shall be appointed and approved by both Parties. The costs of mediation shall be borne by both Parties equally or as determined by the said mediator except that each Party will be responsible for its own expenses. The mediator shall determine the structure of the mediation process. Any opinion expressed by the mediator will be strictly advisory and will not be binding on the Parties. Any disputes not otherwise settled shall be referred to arbitration.
33.4 Disputes resolved by arbitration shall be binding and each Party irrevocably waives any right to trial by jury with respect to any such dispute. Arbitration shall be conducted in New York, USA in accordance with the rules of the International Chamber of Commerce."
"1. Notwithstanding the dual contract approach to the Contracts, the operations of both the Onshore Contractor and the Offshore Contractor must be closely integrated for ensuring the success of the Complete Works. It is understood and agreed that if any aspect of the Complete Works has been omitted and is not clearly described as a result of the creation of the dual contract system, the Offshore Contractor shall assume responsibility for that portion of the Complete Works that is affected.
2. That the dual contract approach shall not result in any additional cost to PETROTRIN nor result in any scheduling changes. It is understood and agreed that the cost and schedule for the Complete Works shall be strictly maintained in spite of implementation under the Contracts. It is understood and agreed that all additional responsibilities and liabilities with respect to PETROTRIN, the Offshore Contractor and the Onshore Contractor contained in either the Offshore Contract or the Onshore Contract shall be construed as if it were one agreement for the Complete Works instead of dual agreements.
3. That any errors, omissions, negligence, or delays in performance by either the Onshore Contractor or Offshore Contractor shall be mutually attributable and shall not constitute grounds for schedule or price relief under the Onshore Contract or Offshore Contract.
4. The Parties' Rights And Obligations Under The Contracts
4.1 That notwithstanding the separation of the Onshore Contract and the Offshore Contract, it is recognized and agreed, for the purpose of determining the respective obligations and entitlement of PETROTRIN and Contractors that, the Onshore Contract and Offshore Contract shall be administered and interpreted as though they were one and notices received or issued under the Offshore Contract shall be valid under the Onshore Contract.
4.2 Where one or both of the Contractors is required to perform the same obligations under one or both of the Contracts and the performance of that obligation by any one Contractor under one Contract is capable of being the performance of that obligation under the other Contact, then the performance of that obligation by that Contractor in accordance with the relevant Contract shall mean that the other Contractor shall not have to perform the same obligation under the other Contact.
4.3 Where PETROTRIN is required to perform the same obligation under both Contacts and the performance of that obligation under one Contract is capable of being the performance of that obligation under the other Contract, then the performance of that obligation by PETROTRIN under one Contract shall mean that PETROTRIN shall not have to perform the same obligation under the other Contract.
5. Liquidated Damages
5.1 Each Contractor shall be liable to pay liquidated damages under Article 3.6(a) of its respective Contract, provided that, if one of Contractors has paid liquidated damages in accordance with Article 3.6(a) of its respective Contract, the other Contractor, notwithstanding Article 3.6(a) of the other Contract, shall not be liable to pay the same liquidated damages in accordance with Article 3.6(a) of that Contract.
5.2 The maximum liquidated damages under each Contract and this Agreement shall be an amount equal to ten percent (10%) of the Total Agreement Amount.
5.3 For the purposes of this Clauses 5 and 6, 'Total Agreement Amount' shall mean the aggregate of the Contract Price payable under the Onshore Contract and the Contract Price payable under the Offshore Contract as each may be adjusted from time to time in accordance with the terms of the Contracts.
…
10. The Parties agree that if there is any dispute as to the interpretation of this Agreement, the Onshore Contract and/or the Offshore Contract, this Agreement shall take precedence over such Contracts.
11. This Agreement shall be governed by and construed in accordance with the laws of England and Wales. Any dispute or controversies pertaining to this Agreement or any breach thereof, which cannot be settled by amicable discussion by the Parties shall be finally submitted and settled by arbitration in New York, USA in accordance with the Rules of the International Chamber of Commerce."
3. THE TERMS OF REFERENCE
"If and insofar as the Request is valid (which is denied), the Respondent will counterclaim inter alia for damages for the Claimant's failure to complete the Works by the Completion Date and also damages for any identified defects in the Works."
'The Claimant' was of course a reference to Samsung, who were party to the Onshore Agreement. 'The Completion Date' was a term defined in the Onshore Agreement. There was no reference to SECL, or to the Offshore Agreement or to the Linkage Agreement.
"In so far as may be relevant [Petrotrin] reserves the right to contend that it is entitled to rely upon the provisions of the Linkage Agreement made between the Claimant, the Respondent and [SECL] on 15 December 2006 and/or the Offshore Agreement made between the Respondent and [SECL] on 15 December 2006."
No other information was given as to what this reservation of position might go to, or how or why either of the other Agreements might be relevant.
4. THE PARTIES' PLEADINGS
5. THE PARTIAL AWARD
"The Claimant's case on the cap
18.11 The Claimant deals with this issue in its Reply and Defence to Counterclaim at paragraphs 188-192, in Section 13 of its Closing Submissions, and in Section 13 of its Responsive Closing Submissions. It argues that the provisions of Article 5.2-5.3 of the Linkage Agreement can be effective only where a claim is made for liquidated damages and is referred to arbitration in respect of both Contracts, between the parties to both Contracts, and under the Linkage Agreement between the parties to the Linkage Agreement. However the present dispute and this arbitration arise only under the provisions of the Onshore Agreement, and concern only the parties to the Onshore Agreement. The provisions of the Onshore Agreement apply exclusively. Hence, the limit on the liquidated damages is defined in Article 3.6(c) of the Onshore Contract, and is 10% of the Contract Price of that Onshore Agreement. Petrotrin construes Article 5.2 of the Linkage Agreement in a manner which contradicts the provisions of both the Onshore and Offshore Contracts instead of in a manner which is consistent with them.
The Respondent's case on the cap
18.12 Petrotrin deals with the cap on liquidated damages In its Counterclaim at paragraph 15.1, in its Reply to Defence to Counterclaim at paragraph 94, and in its Closing Submissions at Section 13. It says that, given the way in which the agreements were set up, it should not be a matter of surprise that there is a contradiction to be resolved by reliance on Article 10 of the Linkage Agreement. It characterizes the Claimant's argument as relying only on a jurisdictional point, namely, that the matter referred to arbitration by the Claimant is purportedly brought pursuant to the Onshore Contract alone. However, Petrotrin has validly brought its counterclaim under all three agreements: Onshore, Offshore and Linkage: see paragraph 16 of the Terms of Reference, paragraph 2.1 of the Respondent's Statement of Case and Counterclaim and paragraph 94 of the Reply to the Defence to Counterclaim. Moreover, even if Petrotrin were jurisdictionally confined to a counterclaim under the Onshore Contract, Articles 2 and 3 of the Linkage Agreement require the Tribunal to treat the Onshore and Offshore Contracts as a single contract, and the Linkage Agreement at Article 5.2 overrides and amends the cap. As to practicalities, the Respondent observes that the On and Offshore Contracts both have the same Mechanical Completion date and in reality the counterclaim spans both the On and Offshore Contracts in that the work which was late was carried out under both Contracts."
"The Tribunal's decision on the cap
18.13 The Tribunal's understanding of the Claimant's position differs from the Respondent's submission. The Tribunal understands the Claimant to rely on both a construction argument and a jurisdiction argument.
18.14 As regards jurisdiction, while it is right to say that in paragraph 16 of the Terms of Reference the Respondent reserved the right to contend that it was entitled to rely upon provisions of the Linkage Agreement, in paragraph 17 of the Terms of Reference the relevant Arbitration Agreement was identified as being contained in Article 33 of the Onshore Agreement. This reflects paragraph 3 of the Request for Arbitration which states:
Although there is a network of inert-related [sic, means 'inter related'] agreements which have a bearing on the disputes which the Claimant required to be referred to arbitration under the International Chamber of Commerce (ICC) Rules for Arbitration, 2012 edition, this Request for Arbitration is made pursuant to Article 33.4 of the On-shore Agreement … …
18.15 Moreover, paragraph 2.1 of the Respondent's Statement of Case and Counterclaim and paragraph 94 of the Reply to the Defence to Counterclaim do not show that Petrotrin has brought its counterclaim under any agreement other than the Onshore Agreement.
18.16 In the Tribunal's view it is plain that its jurisdiction in the present arbitration arises from Article 33.4 of the Onshore Agreement, and is limited thereby. Accordingly it is the provisions of the Onshore Agreement that govern the position.
18.17 As regards the question of construction, we accept the Claimant's submission that a construction which interprets the three agreements as consistent with one another is to be preferred to a construction which regards them as being in conflict. The conflict relied on by the Respondent, which the Respondent resolves by reliance on the precedence of the
Linkage Agreement over the other two Contracts, only arises from reading clause 5.2 of the Linkage Agreement in the way that the Respondent proposes. Clause 5.2 does not in our view require to be read as being in conflict with clause 3.6(c) of the Onshore Agreement; it can be read as a long-stop limit for the aggregate of liquidated damages under all three agreements, which sits above the lower cap applicable under a single agreement. We acknowledge the Respondent's argument that as a matter of practicality it could never apply, but, even if that were so, this would not change our view, since there is nothing unusual in provisions being inserted in contracts out of an abundance of caution.
18.18 Accordingly, we determine that the cap on liquidated damages is 10% of the Contract Price under the Onshore Contract."
6. IS THIS A CHALLENGE CONCERNING THE TRIBUNAL'S "SUBSTANTIVE JURISDICTION"?
"67. - Challenging the award: substantive jurisdiction.
(1) A party to arbitral proceedings may (upon notice to the other parties and to the tribunal) apply to the court—
(a) challenging any award of the arbitral tribunal as to its substantive jurisdiction; or
(b) for an order declaring an award made by the tribunal on the merits to be of no effect, in whole or in part, because the tribunal did not have substantive jurisdiction.
A party may lose the right to object (see section 73) and the right to apply is subject to the restrictions in section 70(2) and (3).
(2) The arbitral tribunal may continue the arbitral proceedings and make a further award while an application to the court under this section is pending in relation to an award as to jurisdiction.
(3) On an application under this section challenging an award of the arbitral tribunal as to its substantive jurisdiction, the court may by order—
(a) confirm the award,
(b) vary the award, or
(c) set aside the award in whole or in part.
(4) The leave of the court is required for any appeal from a decision of the court under this section."
(a) Paragraphs 188-190 of Samsung's RADTCC set out its case as to why, as a matter of construction, the cap was limited to 10% of the Contract Price as defined in the Onshore Agreement.(b) In Petrotrin's RTDTCC, they summarised this argument as Samsung averring that the cap was 10% of the Onshore Contract Price "and not 10% of the combined Onshore and Offshore Contract Price which is termed as the "Total Agreement Amount' under Article 5 of the Linkage Agreement". Although that is not in fact what Samsung had said (it made no mention of either of the other two Agreements), it is clear that Petrotrin saw this as a question of construction. Indeed, they expressly call it "a matter of contractual interpretation".
(c) Petrotrin then sought to make good their case on construction at paragraphs 19.1.2 and 94 of the RTDTCC, which said that Samsung's reliance on the lower cap "is incorrect and obviously so in light of the express wording of the Linkage Agreement at Article 5.2". Again it was Petrotrin who expressly identified this issue as one of contract interpretation.
(d) In the arbitration itself, Petrotrin's written opening at paragraphs 2.2.6 and 6.1 again confirmed that this was a matter of construction. That was repeated during Petrotrin's oral opening (see pages 760-761 and 763 of the transcript). In constantly reiterating that this was a question of contract interpretation, leading counsel then instructed by Petrotrin was only echoing what Mr Acton Davis (who appeared for Samsung then and now) also said to the Tribunal in his oral opening (see page 717 of the transcript).
(e) In the claimant's written closing in the arbitration, paragraphs 13.4 and 13.16 repeat the construction argument.
7. WAS THE TRIBUNAL'S JURISDICTION IN RESPECT OF LIQUIDATED DAMAGES LIMITED TO THE CAP IN THE ONSHORE AGREEMENT?
"The effects of clause 4.1 inter alia for the purposes of Article 10 of the ICC rules of arbitration, is that in the event of Petrotrin having to issue a Request for Arbitration against SECL, all of the claims in that arbitration will be made under the same arbitration agreement as the instant arbitration. Further and in the alternative if (it is denied) the claims in the arbitrations are made under more than one arbitration agreement, the arbitrations are between the same parties, the disputes in the arbitrations arise in connection with the same legal relationship and the arbitration agreements compatible. Such arbitrations will be consolidated." (Emphasis supplied)
a) the Tribunal found (correctly) that they had been appointed under the Onshore Agreement only;b) the Tribunal's Terms of Reference referred to the Onshore Agreement only;
c) the Tribunal found (correctly) that there had been no other claims under either the Offshore Agreement or the Linkage Agreement; and
d) accordingly, the Tribunal found (correctly) that their jurisdiction was limited to the cap in the Onshore Agreement.
It might be thought that, with respect, this was hardly a surprising result.
"104. Drawing this line of authorities together, the following relevant principles can be derived:
a) the exercise of determining whether a dispute falls within an arbitration clause is one of interpretation requiring a careful and commercially-minded construction. It is a question of determining objectively the intention of the parties as revealed by the agreement or agreements;
b) in construing an arbitration clause, a broad and purposive construction should be followed;
c) in general, parties to an arbitration agreement do not intend that disputes under that agreement should be determined by different tribunals ("the Fiona Trust presumption"). This presumption may apply where there are multiple related agreements between the parties. If there are inconsistent arbitration agreements, it may be necessary to identify where the centre of gravity lies and which agreement lies at the commercial centre of the transaction (or is closer to the claim), or under which series of agreements the dispute essentially arises. It is the arbitration agreement in that agreement that will cover all issues. Fragmentation may of course occur if, on its true construction, the clear wording and inherent scheme leads to that conclusion;
d) the Fiona Trust presumption may not apply where there are two or more agreements with separate and distinct arbitration clauses addressing parallel but different aspects of the overall continuing relationship between the parties. A dispute rising under one contract would not be intended to be caught by an arbitration clause in another contract. But I do not accept C's broader submission that the Fiona Trust presumption does not apply where the overall contractual arrangements between two parties contain two or more differently expressed choices of jurisdiction in respect of different agreements. The position is more subtle, as a proper reading of AmTrust reveals; and
e) where there is an agreement subsequently entered into by the parties for the purpose of terminating the commercial relationship created by an earlier agreement, the Fiona Trust presumption may apply with particular potency."
8. CONCLUSIONS
Note 1 In my experience, these ICC Terms of Reference are time-consuming and expensive to produce, and often beg more questions than they answer. [Back] Note 2 This was not a point that had ever arisen in the arbitration. Because the s.67 challenge is a rehearing, not a review, it was an argument which was open to Petrotrin. But the fact that it was completely new explains why there was no hint of it in the Partial Award. [Back]