BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £5, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> OD Developments v Oak Dry Lining Ltd [2020] EWHC 2854 (TCC) (02 April 2020) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2020/2854.html Cite as: [2020] EWHC 2854 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
THE TECHNOLOGY AND CONSTRUCTION COURT (QBD)
7 Rolls Buildings Fetter Lane London EC4A 1NL |
||
B e f o r e :
____________________
OD DEVELOPMENTS | Claimant | |
and | ||
OAK DRY LINING LIMITED | Defendant |
____________________
MR A HICKEY QC (instructed by Pinsent Masons LLP) appeared on behalf of the Defendant
____________________
Crown Copyright ©
WAKSMAN J:
Introduction
The Dispute
"6. Regarding the possible Conditions of sub-Contract, the LOI states the intention is that the JCT 2011 Design & Build Sub-Contract will apply. To an extent ODL and OD proceeded on the basis that the JCT 2011 Design & Build Sub-Contract Conditions applied during the delivery of the Sub-Contract Works occasionally referring to the conditions albeit absent of reliance on any completed Sub-Contract Particulars.
7. The sub-contract sum was subsequently adjusted to £11,244,901.90 under Site Instruction No, 10 dated 22July 2016.
8, However, the JCT 2011 Design & Build Sub-Contract was never executed and the woks proceeded with no regulated terms and conditions.
Adjudication Provisions
9' There were no Contract Particulars executed and no regulated terms and conditions and therefore ODL's option for adjudication falls to be regulated under part 1 of the Schedule to The Scheme for Construction Contracts (England and Wales) Regulations 1998 (Amendment) (England) Regulations 2011.
The Dispute
10' Although a formal contract was never executed the Parties acted as though clause 4.9, 4.10, 4.13, 4.19 and 4.20 of the intended sub-contract (JCT 2011 Design and Build Sub-Contract, applied for the purposes of Interim payments."
The Adjudication
"244. The Letter of Intent states the intention that the 2011 JCT Design and Build Subcontract will apply.
245. It is clear the parties proceeded on the basis that the 2011 JCT Design and Build Subcontract Condition applied, referring to the Conditions albeit absent any completed subcontract particulars.
246. I further agree with OD Developments that whilst parties did not complete the Subcontract Particulars, there was nothing further to be agreed and hence a contact was formed.
247. I therefore agree with the Parties that the Conditions of the JCT Design and Build Subcontract are incorporated and apply."
a. The final payment notice was itself non-compliant and had no effect.
b. If it was compliant, it was not conclusive because the conclusively terms within clause 1.8 invoked by OD conflict with clause 4.12 of the terms and, in any event, conflicted with section 1.1.1. of the Act as amended, so that clause 1.8 must be disregarded.
c. A further consequence of the non-compliance of OD's final payment notice was that Oaks' deferred payment notice was itself valid and became conclusive, meaning that Oak is now owed from OD, the sum claimed of £765,000. That argument did not run if clause 1.8 were to be removed.
a. His appointment was invalid because it was not made in accordance with the adjudication provision in the LOI, which in any event applied.
b. The final payment notice was itself conclusive at the outset and, therefore, there was no true dispute.
"There were no Contract Particulars executed and no regulated terms and conditions and therefore ODL's option for adjudication falls to be regulated under Part 1 of the Schedule to The scheme for construction contracts (England and Wales) Regulations 1998."
'We confirm that it is our intention to enter into formal contractual relations with yourselves, for the Dry Lining, as domestic subcontractor based on JCT 2011 Design & Build. The following information will be incorporated into, and form part of, any order with ourselves.'
Let me stop there. The intention was to enter into formal relations as per the JCT contract. The reference to 'order', clearly to the contemplated executed JCT contract. This is then followed up with the next paragraph which contains a "List of correspondence forming the basis of the order documentation". That list included a subcontract, the sub-contract sum of £1.2 million, the timetable, a post-tender interview and a schedule of tender information.
'This Letter of Intent is based on your knowledge and acceptance of the JCT contracts stated'.
This was heavily relied upon by OD. It submitted that this means that Oak was agreeing there and then to the incorporation of the JCT terms. I disagree. What it means is that Oak agreed in advance that any form of subcontract will indeed be on the basis of JCT Design and Build 2011 subcontract and that Oak if familiar with such terms. I do not regard that as helping OD at all, I am afraid.
'If the contract is cancelled for any reason prior to your subcontract issue, you will be reimbursed on a quantum meruit basis. This Letter of Intent shall expire on 30 July 2016, on the basis that the subcontract shall be entered into by this time.'
'If at any time prior to receipt of the official Contract, it is foreseen that the value will be exceeded, you must request an extension of this instruction'.
Again, reference to the "receipt of the official Contract" must be to the executed JCT contract.