BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Prater Ltd v John Sisk & Son (Holdings) Ltd [2021] EWHC 1113 (TCC) (30 April 2021) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2021/1113.html Cite as: [2021] BLR 474, (2021) 196 Con LR 207, [2021] EWHC 1113 (TCC), 196 Con LR 207 |
[New search] [Printable PDF version] [Help]
QUEEN'S BENCH DIVISION
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT
Rolls Building Fetter Lane, London, EC4A 1NL |
||
B e f o r e :
SITTING AS A DEPUTY HIGH COURT JUDGE
____________________
PRATER LIMITED |
Claimant |
|
- and – |
||
JOHN SISK & SON (HOLDINGS) LIMITED |
Defendant |
____________________
Sarah Hannaford Q.C. (instructed by Hawkswell Kilvington Limited) for the Defendant
Hearing date: 20 April 2021
____________________
Crown Copyright ©
BEFORE VERONIQUE BUEHRLEN Q.C.:
The Parties
The Subcontract and the Adjudications to date
(1) In the First Adjudication (Adjudication 1), Prater sought an amendment to the Subcontract Completion Date. No payment was sought. Mr Molloy issued his decision on 15 June 2020 (Decision 1). He decided that Prater was entitled to an adjustment to the Subcontract Completion Date from 15 March 2019 (the original completion date) to 15 July 2019.
(2) In the Second Adjudication (Adjudication 2), Prater sought decisions on a number of matters including (a) the correct Subcontract Completion Date following upon the findings in Decision 1, (b) the status of provisional sums within the Subcontract and (c) Sisk's entitlement to deduct certain indirect losses from any sums due to Prater. As in Adjudication 1, no payment was sought by Prater. Mr Molloy's decision is dated 5 October 2020 (Decision 2).
(3) In the Third Adjudication (Adjudication 3), Sisk sought a declaration that certain Compensation Events claimed by Prater were not Compensation Events under the Subcontract. Mr Collier was the Adjudicator, and he issued his decision on 28 October 2020 (Decision 3).
(4) In the Fourth Adjudication (Adjudication 4), Prater sought payment of the sum of £2,253,731.65 plus VAT following Decisions 1 – 3. Again, the Adjudicator was Mr Molloy. His decision was issued on 2 February 2021 following a slip rule correction (Decision 4). As already noted, he awarded Prater the sum of £1,757,821.35 plus VAT. Decision 4 is (in part) based on the findings made in Decision 2.
The Parties' respective cases
(i) Firstly, that it is not open to Sisk to challenge Decision 2 in the context of Adjudication 4. Decision 2 is binding and enforceable against Sisk as a matter of principle as well as contractual obligation unless and until revised by the Court pursuant to clause W2.3(11) of the Subcontract.
(ii) Secondly, Sisk's argument does not give rise to a right to impugn Decision 4 on grounds of lack of jurisdiction of the Adjudicator, fraud or breach of the rules of natural justice which are the only bases on which enforcement of Decision 4 can be challenged. Even if correct, the complaint is that Mr Molloy based Decision 4 on a mistake of law by treating Decision 2 as binding or as recording matters that could not be revisited.
(iii) Thirdly, any challenge to the jurisdiction of the Adjudicator in Adjudication 4 would need to be based on the dispute referred to him in that Adjudication and the Adjudicator's jurisdiction to make a decision in Adjudication 4 and not his jurisdiction in respect of Adjudication 2. A challenge based on an assertion that an earlier decision upon which an adjudicator is asked to proceed is not a challenge to the Adjudicator's jurisdiction in the current Adjudication.
(v) Fourthly, if (contrary to Prater's primary case) a lack of jurisdiction in relation to Decision 2 is relevant to the enforcement of Decision 4, Sisk's case that the Adjudicator lacked jurisdiction in relation to Adjudication 2 because the referral included multiple disputes is misplaced. The genesis of the dispute was Sisk's "assessment" of Prater's account issued on 20 December 2019 and its 22 January 2020 Payment Certificate and the referral simply included a number of issues arising out of that disputed certificate.
The Issues on the Application
(i) Firstly, is a lack of jurisdiction in relation to Decision 2 capable of impugning the Adjudicator's jurisdiction in Adjudication 4 by virtue of the fact that Decision 4 is, in part, based on findings made in Decision 2?
(ii) Secondly, if it is, did the Adjudicator lack jurisdiction in relation to Adjudication 2?
Issue 1: The alleged lack of jurisdiction in respect of Adjudication 4
"The fundamental principle that governs all enquiries into the adjudicator's jurisdiction can be simply stated. If a dispute has arisen between two parties to a construction contract and the adjudicator is validly appointed to decide that dispute, then, provided his decision attempts to answer that dispute, his decision will be binding in accordance with the 1996 Act, regardless of errors of fact or law or procedure. If, on the other hand, he was not validly appointed, or he decided something other than the dispute that was referred to him, his decision will be unenforceable because it would have been made without jurisdiction. Thus it follows that it is not enough for the defendant to show an error on the part of the adjudicator. What matters, in the words of Sir Murray Stuart-Smith in C&B Scene, is whether the error on the part of the adjudicator went to his jurisdiction, or was merely an erroneous decision of law (or fact) on a matter within his jurisdiction. If it was the former, the decision would be unenforceable; if it was the latter, the decision would be enforceable by way of summary judgment."
"The Adjudicator's decision is binding on the Parties unless and until revised by the tribunal and is enforceable as a matter of contractual obligation between the Parties and not as an arbitral award. The Adjudicator's decision is final and binding if neither Party has notified the other within the times required by this subcontract that he is dissatisfied with a matter decided by the Adjudicator and intends to refer the matter to the tribunal."
"If, after the Adjudicator notifies his decision a Party is dissatisfied, that Party may
notify the other Party of the matter which he disputes and state that he intends to refer it to the tribunal. The dispute may not be referred to the tribunal unless this notification is given within four weeks of the notification of the Adjudicator's decision. (3) The tribunal settles the dispute referred to it. The tribunal has the powers to reconsider any decision of the Adjudicator and to review and revise any action or inaction of the Contractor related to the dispute. A Party is not limited in tribunal proceedings to the
information or evidence put to the Adjudicator."
"23. Sisk's deductions are premised on the basis that the Subcontract contains provisional sums. In Adjudication No.2, there was agreement between the parties that the Subcontract did not contain provisional sums and my Decision reflected this in making a finding to that effect. However, Sisk says that the Decision in Adjudication No.2 is unenforceable. In support of its position, Sisk relies on the challenges to jurisdiction which were advanced and rejected by me in Adjudication No.2. Sisk says that I was wrong to do so and says the fact Prater has not sought to enforce the Decision indicates that it agrees.
24. Prater makes the point that W2.3(11) of the Subcontract expressly provides that "The Adjudicator's decision is binding on the Parties unless and until revised by the tribunal and is enforceable as a matter of contractual obligation between the Parties…". Prater also makes the point that, as it did not claim payment in Adjudication No.2, there was nothing to enforce and it observes that Sisk has taken no steps to obtain a declaration to the effect that the Decision was either unenforceable or wrong. These points are well made. It therefore follows that, for present purposes, the Decision in Adjudication No.2 is binding on the parties. That being the case, it follows that the adjustment in respect of provisional sums adopted by Sisk does not reflect the provisions of the Subcontract and I therefore disallow these deductions."
Issue 2: The jurisdictional challenge in relation to Decision 2
(1) The correct Subcontract Completion Date;
(2) The status of provisional sums within the Subcontract; and
(3) Sisk's entitlement to deduct certain indirect losses from any sums due to Prater.
Was more than one dispute referred?
"Drawing all these threads together, I draw the following conclusions:
(i) A dispute arises generally when and in circumstances in which a claim or assertion is made by one party and expressly or implicitly challenged or not accepted.
(ii) A dispute in existence at one time can in time metamorphose in to something different to that which it was originally.
(iii) A dispute can comprise a single issue or any number of issues within it. However, a dispute between parties does not necessarily comprise everything which is in issue between them at the time that one party initiates adjudication; put another way, everything in issue at that time does not necessarily comprise one dispute, although it may do so.
(iv) What a dispute in any given case is will be a question of fact albeit that the facts may require to be interpreted. Courts should not adopt an over legalistic analysis of what the dispute between the parties is, bearing in mind that almost every construction contract is a commercial transaction and parties cannot broadly have contemplated that every issue between the parties would necessarily have to attract a separate reference to adjudication.
(v) The Notice of Adjudication and the Referral Notice are not necessarily determinative of what the true dispute is or as to whether there is more than one dispute. One looks at them but also at the background facts.
(vi) Where on a proper analysis, there are two separate and distinct disputes, only one can be referred to one adjudicator unless the parties agree otherwise. An adjudicator who has two disputes referred to him or her does not have jurisdiction to deal with the two disputes.
(vii) Whether there are one or more disputes again involves a consideration of the facts. It may well be that, if there is a clear link between two or more arguably separate claims or assertions, that may well point to there being one dispute. A useful if not invariable rule of thumb is that, if disputed claim No 1 cannot be decided without deciding all or parts of disputed claim No 2, that establishes such a clear link and points to there being only one dispute."
"3.1.4 There are significant disparities between the respective Parties positions in regard to the assessment of sums due under the Subcontract. The latest Payment Certificate of Sisk dated 22 January 2020 includes a gross certified sum of £4,984,867.09, the respective Payment Application included a gross sum due of £12,107,519.31 (Appendix 5/p.9). Prior to the recent adjudication decision Sisk maintained that Prater was not entitled to any adjustment to the Completion Date beyond 1 April 2019 and had rejected the majority of issued notification of compensation events. Despite the content of the recent adjudication decision Sisk has only released circa £151k of cash to Prater.
3.1.5 The dispute between the Parties in respect of the appropriate assessment of compensation events and other sums due is complex and considered too cumbersome to be decided appropriately within a single adjudication. This Adjudication therefore is focussed upon the following issues:
…"
Was it open to Prater to refer more than one dispute?
Conclusion