BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Qatar Airways Group QCSC v Airbus SAS [2022] EWHC 1248 (TCC) (26 May 2022) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2022/1248.html Cite as: [2022] EWHC 1248 (TCC) |
[New search] [Printable PDF version] [Help]
Neutral Citation Number: [2022] EWHC 1248 (TCC)
Claim No:
IN THE HIGH COURT OF JUSTICE
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT
QUEEN’S BENCH DIVISION
Date:
B e f o r e :
QATAR AIRWAYS GROUP Q.C.S.C.
|
||
- and - |
||
|
|
Akhil Shah QC and Harrison Denner (instructed by Crowell and Moring LLP, Solicitors) for the Claimant
Rosalind Phelps QC and Samuel Ritchie (instructed by Clifford Chance LLP, Solicitors)
for the Defendant
JUDGMENT
Hearing date: 26 April 2022
INTRODUCTION
Further background
The Condition - the Present Position
“As part of its continuous improvement approach, Airbus has investigated and continues to investigate how the effects of the matters which gave rise to the Condition… might be addressed or mitigated. However, as set out above, it is inevitable that the paint on any aircraft will degrade or become damaged over time.…”
The SCL
“An “AOG” means (i) and Aircraft being grounded on an unscheduled basis for 12 hours or more, as a result of the Condition,… For each AOG of an Aircraft, the Seller will pay the Buyer an amount of ,000 per each day, or part thereof the aircraft is AOG…. For the avoidance of doubt in the event all the Aircraft in the Buyer’s fleet grounded due to the Condition, then the above compensations shall apply as long as the AOG of such Aircraft continues.”
Airworthiness
Speedy Trial
The preliminary issue application
Introduction
The Law
Analysis
The relief sought at trial
“(1)
(2) An order for specific performance that the Defendant perform and deliver to the Claimant a full root-cause analysis for each of the defects comprising the Condition.
(3) Payment of AOG Compensation…
(4) Alternatively, damages for the Defendant's failure to pay AOG Compensation in breach of Clause 3.2 of the SCL and/or the Warranties.
(5) A declaration that the design of the A350 is defective.
(6) A declaration that pending rectification of the Condition and the design defects giving rise to it, the Claimant is not obliged to accept any further undelivered A350 aircraft.
(7) A declaration that pending rectification of the Condition and the design defects giving rise to it, any written notice served by the Defendant that any of the Undelivered A350 QR Fleet (including but not limited to MSN 409 and/or MSN 430) is in a condition to begin the Acceptance Procedure is invalid and of no contractual effect.
(8) A declaration that pending rectification of the Condition and the design defects giving rise to it, any purported delivery of any of the Undelivered A350 QR Fleet (including but not limited to MSN 409 and /or MSN 430) is invalid and of no contractual effect.
(8a) A declaration that the Defendant is not entitled to terminate the purchase of MSN 409 or the purchase of MSN 430, and/or that the MSN 409 Termination and the MSN 430 Termination and the Further MSN 409 Termination were invalid and/or ineffective.
(8b) A declaration that the Defendant is not entitled to terminate the SCL and/or that the SCL Termination was invalid and/or ineffective.
(9) Injunctive relief to restrain the Defendant from purporting to deliver any of the Undelivered A350 QR Fleet pending rectification of the Condition and the design defects giving rise to it.
(9a) Injunctive relief to restrain the Defendant from terminating or purporting to terminate the purchase of any or all of the Undelivered QR A350 Fleet.
(10) Interest pursuant to statute as pleaded above.
(11) Further or other relief as the Court considers appropriate; and
(12) Costs.”
The injunction applications
Introduction
(1) tender any new aircraft for delivery, through the Technical Acceptance Process;
(2) deliver any Certificate of Acceptance in relation to any new aircraft; and
(3) seek any pre-delivery payments for new aircraft
(“The Delivery Injunction”).
(1) restrain the Defendant from implementing or by any means howsoever acting on:
(a) a Notice of Termination dated 17 January 2022 with reference CT2200370 relating to an A350XWB aircraft MSN 409; or
(b) a Notice of Termination dated 28 January 2022 with reference CT2200595 relating to an A350XWB aircraft MSN 430; (collectively the "Notices"); or
(c) any other such Notice of Termination;
(2) restrain the Defendant from marketing or selling or otherwise disposing of in any way to third parties or otherwise howsoever aircraft MSN 409 or MSN 430;
(3) restrain the Defendant from issuing any further Notice(s) of Termination in respect of any A350XWB Aircraft scheduled for delivery by the Defendant pursuant to the Aircraft Specific Purchase Agreement dated 18 June 2007
(“the Termination Injunction”).
The Delivery Injunction
The Termination Injunction
27…The primary obligation of a party is to perform the contract. The requirement to pay damages in the event of a breach is a secondary obligation, and an agreement to restrict the recoverability of damages in the event of a breach cannot be treated as an agreement to excuse performance of that primary obligation. I share Mance LJ's rejection of the position advanced by Mowlem that, even where a provision limited the victim of a breach to damages which bore no relation to its loss, those damages had nevertheless to be regarded an adequate remedy: see the end of para 14 of his judgment. Mr Bergin's stance was the same before us, as logically it had to be: even in the case of the most gross and cynical breach of contract, if—as was likely to be the case—the only losses suffered which would sound in damages were of a kind which were excluded by the contract, no injunction would lie and the contract-breaker would be able to walk away from his obligations with impunity. That does not seem to me to be just. The rule—if "rule" is the right word—that an injunction should not be granted where damages would be an adequate remedy should be applied in a way which reflects the substantial justice of the situation: that is, after all, the basis of the jurisdiction under section 37.
28. Viewed in this way, there is no question of, as Mr Bergin contended, the commercial expectations of the parties being undermined. The primary commercial expectation must be that the parties will perform their obligations. The expectations created (indeed given contractual force) by an exclusion or limitation clause are expectations about what damages will be recoverable in the event of breach; but that is not the same thing.
29. This approach also seems to me to sit better with the acceptance by this court that an injunction may in an appropriate case be granted even where the loss caused by a threatened breach would not sound in damages. That is apparent both from the Regent International case The Times, 13 May 1985 and from the judgments of Aldous and Carnwath LJJ in the SmithKline case [2003] FSR 544 approved by Mance LJ, at paras 18-19 of his judgment in Bath v Mowlem [2015] 1 WLR 785. That is a separate but similar instance of the court refusing to allow a mechanistic application of the "damages an adequate remedy" rule to prevent the victim of a breach being able to enforce compliance with the primary obligations under the contract.
30. Mr Bergin argued that it could not be right that in every case where the victim of a threatened breach of contract sought an interim injunction he could rely on the existence of an exclusion or limitation clause to claim that damages would not be an adequate remedy. I think that that overstates the consequences of the case which I have accepted. A claimant will still have to show that if the threatened breach occurs there is (at least) a substantial risk that he will suffer loss that would otherwise be recoverable but for which he will (or at least may) be prevented from recovering in full, or at all, by the provision in question. If he does, then certainly it will not be sufficient for the defendant to say that the restriction in question was agreed; and to that extent the claimant will indeed have established that his remedy in damages may not be adequate. But that only opens the door to the exercise of the court's discretion; and in the exercise of that discretion the fact that the restriction in question was agreed may, depending on the circumstances of the case, be a relevant consideration—as may the scale of any shortfall and the degree of risk of it occurring. Mr Ter Haar made it clear that he did not contend to the contrary.”
“32. … would wish to emphasise the expression of principle set out by Underhill LJ, at para 25. On the facts of this case the court's remedies are available in support of a contractual right and are not excluded by the terms of the contract. Injunctive relief is a remedy available to the court to give effect to commercial expectations where it is in the interests of justice that agreed obligations should continue to be binding on the parties, whether that be for an interim period or the term of the contract. The construction of the contract clause in the context of the description of legal principle set out by Underhill LJ has the effect of tending to support rather than undermine parties who have entered or seek to enter into a contract which contains their commercial expectations. There are different reasons on the facts of individual cases why this may be so and although it would be unwise to categorise them, it is surely the policy of the law to help to give effect to the parties' intentions and in particular their acceptance of commercial risk by performance. For that reason, I favour re-casting the question to be asked on an application for injunctive relief, which is: "Is it just in all the circumstances that a [claimant] be confined to his remedy in damages?", per Sachs LJ in Evans Marshall & Co Ltd v Bertola SA…”
“33. I agree with both judgments. Where a party to a contract stipulates that if he breaches his obligations his liability will be limited or the damages he must pay will be capped, that is a circumstance which in justice tends to favour the grant of an injunction to prohibit the breach in the first place.”
Conclusion