BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just Β£1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Barkby Real Estate Developments Ltd v Cornerstone Telecommunications Infrastructure Ltd [2022] EWHC 1892 (TCC) (21 July 2022) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2022/1892.html Cite as: [2022] EWHC 1892 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (QBD)
Rolls Building London, EC4A 1NL |
||
B e f o r e :
Sitting as a Deputy High Court Judge
____________________
BARKBY REAL ESTATE DEVELOPMENTS LIMITED (FORMERLY KNOWN AS TARNCOURT AMBIT DEVELOPMENTS LIMITED) (COMPANY NUMBER: 12195490) |
Claimant |
|
- and |
||
CORNERSTONE TELECOMMUNICATIONS INFRASTRUCTURE LIMITED (COMPANY NUMBER 08087551) |
Defendant |
____________________
Peter Petts (instructed by Osborne Clarke LLP) for the Defendant
Hearing dates: 12, 13, 14 July 2022
____________________
Crown Copyright ©
Mr Roger ter Haar QC :
A. Introduction
B. The Parties
C. The Project
D. BREDL's team
(1) For the design stage, Roberts and Cartwright Design Limited ("RCD") as utilities engineer;
(2) Mitchell Design and Construction Limited ("MDCL") as the main contractor for the development work itself;
(3) Rex Procter and Partners ("RPP") as the Employer's Agent/QS;
(4) The Harris Partnership ("THP") as the architect;
(5) JPG Limited as the engineer;
(6) Ambit as the Development Manager to oversee the whole project from acquisition to planning to advance letting to construction to handover (to Hastings Borough Council).
E. Initial exchanges
"Further to your query through our website on the site move costs, the site you have identified looks to be a 'streetworks' installation in the public highway:
[there are two photographs inserted]
"Depending on availability of alternative location, planning, decommissioning and build costs you'd probably be looking at a rough cost of C£60k and timescale of c9 months.
"The matter would be dealt with by our 'Lift and shift' team."
" I hope you are keeping well.
The project is now moving forward and we have been asked to find out what the process is for getting this mast relocated.
The client [has] proposed a new location which is really just moving the mast back a few feet from the road to make way for the bus lane. This is now with planning for their approval. We are aware that your company will obviously need to confirm this location is suitable too.
We now need to know the following and [wondered] if you could help.
5. How do we start getting the mast relocation going?
6. What forms do we need to complete with you?
7. How do we go about getting a formal quote from you?
8. What are the timescales you work to?
I would be grateful if you could provide the information and please feel free to call me if it is easier to discuss over the phone."
"Your enquiry has been passed on to me. In answer to your questions:
1. How do we start getting the mast relocation going?
-The notice provided is sufficient. If you have drawings of the proposed scheme this will help our suppliers to find a relocation option.
2. What forms do we need to complete with you?
-If you wish to proceed our client CTIL will need to set the developer up as a supplier and need request some basic payment info. I will forward the forms once it is confirmed that they wish that they wish to proceed with relocating the telecoms Site.
3. How do we go about getting a formal quote from you?
- The process is in 2 stages.
1 the initial Acquisition & Design (A&D) this involves surveying the site/area, finding an alternative location, obtaining planning if required, and design of the site at the relocation option.
2 The Construction phase build of the tower & cabinets, supply of power and BT/Virgin transmission to the telephone network.
We will raise an initial quote for the 1st stage. At which point if your client wishes to proceed they will need to complete the forms (@2.) and once payment has been received, CTIL will instruct their A&D partner to progress.
Once this stage is complete, we can then request the quote for the 2nd phase. Your client will then have the option to progress or not prior to this stage starting. If they wish to proceed, payment will need to be made to CTIL. Again once payment received CTIL will instruct their partner to proceed with the construction of the new site and then the decommissioning of the old site once the new one is Live.
A total ballpark if a new site is required £120,000.
4. What are the time scales you work to?
- 12-18 months."
F. Cornerstone's team
"14. As I have set out above, my role at Cornerstone is to oversee the build and decommissioning project, as Cornerstone has overall responsibility for the mast infrastructure. Cornerstone check that the new site designs are viable, oversee the project, raise purchase orders and ensure health and safety procedures are followed. However, Cornerstone does not carry out much of the build and decommissioning work itself and is instead assisted in its projects by a number of suppliers who carry out [discrete] roles. I have set out below a brief explanation of the different parties' roles in this project to give some context to the documents and emails that have been disclosed by the parties.
" 14.1 Cluttons LLP Cornerstone's agent who manage the site on a day-to-day basis.
" 14.2 Galliford Try Cornerstone's acquisition, design and build partners. They are responsible for all the necessary works to get the new site built including preparing the site designs.
" 14.3 Dael Cornerstone's decommissioning suppliers. They are responsible for ensuring the Old Site is decommissioned once the New Site is connected to the network.
" 14.4 Sinclair Dalby Limited Galliford Try's sub-contractors. They are responsible for the acquisition stage.
" 14.5 Telefonica Cornerstone's ultimate customer. They provide the active equipment on the site and arrange the transmission link between the new site and their network.
" 14.6 Openreach Limited Telefonica's sub-contractors who supply the fibre link from the site into Telefonica's network."
G. The Design and Acquisition Phase
"10.1 No work would be carried out by Cornerstone under this phase until the acquisition and design costs were agreed and paid by the site provider.
"10.2 Once payment is made, the operator whose equipment is located on the mast (in this case Telefonica UK Limited) ("Telefonica") would inform their radio planning team so that they can carry out site searches and select a new site location.
"10.3 Cornerstone would then send an acquisition surveyor to the site of the existing mast to look for suitable potential new sites within a search area identified by the radio planner.
"10.4 Once the acquisition surveyors have identified potential sites the radio planner would then select their preferred option and a Multi Skilled Visit ("MSV") would take place to assess the viability of that site on the ground. At this stage, trial holes would be dug to check whether there are services running under the proposed site and to assess ground conditions up to 1.2 metres depth.
"10.5 If the site is deemed suitable after the MSV, general arrangement planning drawings are produced and planning permission is sought.
"10.6 Once planning has been granted construction permission is sought.
"10.7 The costs are then raised with either Cornerstone or the site provider (if [it is] the site provider that is paying for the works) who will then decide whether to go ahead with the build or not.
"11 Cornerstone would then negotiate terms and enter into a Code agreement to acquire the necessary rights over the new mast site to allow the site to be built."
H. The Build Phase
"The CTIL selected suppliers for these works are Galliford Try, Dael and Telefonica.
"Upon receipt of full payment from the customer, Cornerstone will proceed to instruct works. Any unused funds will be credited back to the customer once Cornerstone have accepted the final cost of works from our suppliers."
"Nice to meet you too, we pre-started this site on Friday and our supervisor has advised there is a supermarket being built behind where our site is meant to be going. Our supervisor has stated that the boarding put up around where the supermarket is to be built/being built is where our kit should be going ."
"Our contractor arrived as planned on site yesterday. However, the principal contractor redeveloping the site had not cleared the required area and brought the ground level up to what will be the finished ground level as part of the whole are development, as agreed at the site meeting. The PC was looking to have this cleared/ground made this morning. I have left a message with our contractor for an update and will forward the latest on as soon as I get it."
"Latest on site. The PC for the redevelopment has only this afternoon completed the operation to bring the ground level up to what will be the approx.. finished ground level when the whole redevelopment gets completed. This in turn has impacted on us as we've been unable to progress much while waiting. However, we can now progress with the excavation of the cab and pole base tomorrow ready to install the roots and concrete.
"Tomorrow morning's update should confirm the excavations are ongoing the afternoon update should confirm if the pour has gone ahead (current plan to pour by finish tomorrow)."
"Further to discussion on the call, the latest on this site below:
- Excavation down to 1800mm and hitting running gravel/standing water.
- Machine has backed away from the excavation due to danger of collapse.
- PICW has spoken to the site manager of the supermarket build they dug down to 4m for the building foundations and were still hitting gravel.
- Works are on hold at present as contractor and design lead discuss a solution.
- Potential for excavation to be widened and shuttered with additional mass fill concrete to enclose the pole root.
- Larger machine will be required if this progresses."
"Please see attached POW[19] for the above site.
"We are starting work on 23/04/20 with Piling and the pole installation date on 14/04/20. The gap between SOS[20] and pole install is down to Council rejecting our symology and Easter being in between.
"we are looking to install the cabinet and pole on 14/04/20. Both sites will have a power supply on 14/04/20, so TX can be delivered any day after 14th April.
"We currently have a REC date of 9th April, however we suspect the Council will reject their permit. If REC cannot be delivered in time then we will submain over to the new cabinets."
"Further to our conversation (and [your] email this evening, I have been working on the plan to get the new equipment installed, this has been scuppered by the Council as they have rejected my request to close a lane and bus stop for 01/04/20. You say that you have had similar issues with the Council due to Gas works a lot further up the road. They have advised that I can plan this job in after 9th April. However, this is Easter weekend, so I will be completing the pole install on 14/04/20.
"We are looking to start work on 23/03/20 with excavations and piling then concrete pour happening shortly after and then the ground will be re-instated. We will be working from your land and within the heras fencing that is currently on site.
"Please see attached drawings that we are working to. Page 17 shows the base that we will be installing and page 4 shows the area that we will be working in.
"POW is attached, outline below
23/03/20 start on site with piling
25/03/20 excavation and concrete pour complete
14/04/20 New pole and cabinet delivery
15/04/20 We will be leaving site ready for O2 to return.
"The Electricity company have provided dates of 8th and 9th April, however I suspect the council might reject their request. I have attached their plan. We will be installing their duct and the DNO will need to do a joint pit by the existing meter cabinet ."
I. The Completion of BREDL's development
"Under the terms (clause 2.27.2) of the above mentioned Contract, Sectional Completion of Section 1 (ie 4nr retail units and associated external works) of the Works was achieved on: 25 June 2020."
J. The Terms of Cornerstone's Contract with BREDL
"26. Although not pleaded, it is understood that there is little difference between the parties as to the contract date, it was either 28/08/2019, when payment was made by C for the Phase 2 works, or 05/09/2019, when payment was accepted by D as having been made for those works.
"27. Not a great deal turns on it, but it is submitted the latter date is to be preferred, D's quote being an invitation to treat; C's acceptance of the quote being an offer, which D accepted by acknowledging payment, on 05/09/19."
"Implied term about time for performance.
"(1) Where, under a [relevant contract for the supply of a service] by a supplier acting in the course of a business, the time for the service to be carried out is not fixed by the contract, left to be fixed in a manner agreed by the contract or determined by the course of dealing between the parties, there is an implied term that the supplier will carry out the service within a reasonable time.
"(2) What is a reasonable time is a question of fact."
"When the language of a contract does not expressly, or by necessary implication, fix any time for the performance of a contractual obligation, the law implies that it shall be performed within a reasonable time. The rule is of general application, and is not confined to contracts for the carriage of goods by sea. In the case of other contracts the condition has been frequently interpreted; and has invariably been held to mean that the party upon whom it is incumbent duly fulfils his obligation, notwithstanding protracted delay, so long as such delay is attributable to causes beyond his control, and he has neither acted negligently nor unreasonably."
K. What was a reasonable time for completion of the works, in the light of the matters raised at paragraph 14 of the Defence?
"It is the Claimant's contention that the Defendant ought to have carried out and completed its works by no later than 30 June 2020. From the date of payment by the Claimant (4 September 2019), that would have allowed the Defendant a period of ten months to remove and replace a single telephone master. In fact, a reasonable period for such works would have been considerably shorter, but for the purpose of its claim the Claimant will proceed on the basis that ten months was the contractually required time for performance."
L. Did the Defendant fail to carry out and complete its works within a reasonable time?
M. If the Defendant breached its obligation as to time, is the Claimant entitled to damages, and, if so, in what amount?
N. Were the Claimant's losses too remote?
"a. Additional project finance costs: £41,360.24;
"b. Rent free period allowed to the Claimant's tenants: £47,585.00;
"c. Additional project management costs: £15,000;
"d. Laying new tarmac: £7,500.00."
Additional project finance costs
"a. July 2020 - £3,637 monthly and £20,545 interest.
"b. August 2020 - £3,637 monthly fee and £18,255.90."
"29. More recently, Professor Andrew Burrows [now Lord Burrows JSC] in A Restatement of the English Law of Contract (2016), in which he was assisted by an advisory body of academics, judges and practitioners, described the general rule on remoteness of damage in contract in these terms (p 128):
"The general rule is that loss is too remote if that type of loss could not reasonably have been contemplated by the defendant as a serious possibility at the time the contract was made assuming that, at that time, the defendant had thought about the breach." (Emphasis added.)
"Drawing on The Achilleas [2009] AC 61, the text went on to state a further restriction on recoverability for the loss. But, as the Board has stated, the question of such a restriction does not arise on this appeal.
"30. From this brief review of the main authorities, the position may be summarised as follows:
"31. First, in principle the purpose of damages for breach of contract is to put the party whose rights have been breached in the same position, so far as money can do so, as if his or her rights had been observed.
"32. But, secondly, the party in breach of contract is entitled to recover only such part of the loss actually resulting as was, at the time the contract was made, reasonably contemplated as liable to result from the breach. To be recoverable, the type of loss must have been reasonably contemplated as a serious possibility, in the sense discussed in paras 27 and 28 above.
"33. Thirdly, what was reasonably contemplated depends upon the knowledge which the parties possessed at that time or, in any event, which the party, who later commits the breach, then possessed.
"34. Fourthly, the test to be applied is an objective one. One asks what the defendant must be taken to have had in his or her contemplation rather than only what he or she actually contemplated. In other words, one assumes that the defendant at the time the contract was made had thought about the consequences of its breach.
"35. Fifthly, the criterion for deciding what the defendant must be taken to have had in his or her contemplation as a result of a breach of their contract is a factual one."
Additional project management costs
O. Conclusion
Note 19 Programme of Works [Back] Note 23 Mr. Frances witness statement, paragraph 24 at page A 88 [Back] Note 24 Mr. Frances witness statement, paragraph 25 at page A 88 [Back] Note 27 Mr. Langridge-Browns witness statement paragraph 25 at A 63 [Back] Note 29 C 729 -736. A further copy of the Certificate and Schedule (in a slightly different format) is at B238--B245 [Back] Note 30 Paragraphs 4 to 9 of the Particulars of Claim at A 7 A 8 [Back] Note 31 Defence paragraphs 8 to 10 at A 19 A 20 [Back] Note 34 E mail at C 112 [Back]