BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Ravestein BV v Trant Engineering Ltd [2023] EWHC 11 (TCC) (09 January 2023) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2023/11.html Cite as: 206 Con LR 136, [2023] EWHC 11 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS IN LEEDS
TECHNOLOGY AND CONSTRUCTION COURT (KBD)
Oxford Row Leeds LS1 3BG |
||
B e f o r e :
____________________
RAVESTEIN B.V. |
Claimant |
|
- and – |
||
TRANT ENGINEERING LIMITED |
Defendant |
____________________
Mr Dalton Hale (instructed by KT Construction Law Limited) for the Defendant
Hearing date: 21 July 2022
Date draft circulated to the Parties: 22 December 2022
Date handed down: 9 January 2023
____________________
Crown Copyright ©
Her Honour Judge Kelly
Background
(1) determination of the question will substantially affect the rights of the parties because the effect of the arbitration decision was that the tribunal did not have jurisdiction to determine the dispute and so the adjudication decision became final and binding;
(2) the question was the only one which the tribunal was asked to determine;
(3) the decision of the tribunal was obviously wrong because:
a. the tribunal incorrectly held that to comply with the relevant clauses, the Notice of Dissatisfaction had to both notify the matter in dispute and state the intention to refer it to the tribunal; and
b. the tribunal incorrectly held that the Notice of Dissatisfaction served by the Claimant challenged only the jurisdiction of the adjudicator rather than contesting his underlying decision;
(4) alternatively, the question was one of public importance given the widespread use of the standard NEC3 Engineering and Construction Subcontract and the decision of the tribunal was open to serious doubt for the reasons set out in (1) to (3) above;
(5) it was just and proper in all the circumstances for the court to determine the question.
(1) the decision of the arbitrator was not "obviously" wrong:
a. The arbitrator had correctly interpreted the relevant notice provisions. A Notice of Dissatisfaction requires the dissatisfied party both to identify the matter disputed and to indicate an intention to refer the matter to arbitration, although the notice does not need to condescend into any particular detail.
b. The adjudicator had correctly interpreted the relevant email alleged to be the Notice of Dissatisfaction as disputing the jurisdiction of the adjudicator only, rather than identifying a dispute concerning the underlying merits of the adjudicator's decision.
c. The decision of the arbitrator that the relevant email alleged to be the Notice of Dissatisfaction did not identify the two separate elements required for the notice to be valid – that is it did not identify that it took issue with the underlying merits nor did it state any intention to refer the dispute to arbitration.
(2) Although the correct interpretation of notice provisions in the standard form is capable of being a matter of public importance, it was denied that it was in this case and the decision of the arbitrator was open to serious or any doubt.
(3) In any event, it was not just and proper in all the circumstances for the court to determine the question because the Claimant's continued to refusal to pay goes against the "pay now, argue later" objectives of the 1996 Act.
The Law
(a) that the determination of the question will substantially affect the rights of one or more of the parties,
(b) that the question is one which the tribunal was asked to determine,
(c) that, on the basis of the findings of fact in the award—
(i) the decision of the tribunal on the question is obviously wrong, or
(ii) the question is one of general public importance and the decision of the tribunal is at least open to serious doubt, and
(d) that, despite the agreement of the parties to resolve the matter by arbitration, it is just and proper in all the circumstances for the court to determine the question.
(1) Transport for Greater Manchester v Keir Construction Ltd [2021] EWHC 804 (TCC)
(2) Bunge SA v Nibulon Trading BV [2013] EWHC 3936 (Comm)
(3) MBE Electrical Contractors v Honeywell Control Systems [2010] BLR 561
(4) Covington Marine Corp & Ors v Xiamen Shipbuilding Industry Co [2006] 1 CLC 624
(5) The Council of the City of Plymouth v D R Jones (Yeovil) Ltd [2005] EWHC 2356 (TCC)
(6) Finelvet A.g. v Vinava Shipping Co. Ltd [1983] 1 WLR 1469
(7) BTP Tioxide Ltd v Pioneer Shipping Ltd [1982] AC 724
(8) Fehn Schiffahrts GmbH v Romani Spa [2018] 2 Lloyd's Rep 385
(9) The Pera [1985] 2 Lloyd's Rep 103
(10) The Antaios [1985] A.C. 191
(11) Forrest v Glasser [2006] 2 Lloyd's Rep 392
(12) The Abqaiq [2012] 1 Lloyd's Rep 18
(13) Rainy Sky SA v Koomin Bank [2011] UKSC 50.
From those cases, I summarise the legal position.
(1) The arbitrator ascertains the facts. This process includes the making of findings on any facts which are in dispute.
(2) The arbitrator ascertains the law. This process comprises not only the identification of all material rules of statute and common law, but also the identification and interpretation of the relevant parts of the contract, and the identification of those facts when the decision is reached.
(3) In the light of the facts and the law so ascertained, the arbitrator reaches his decision.
"…it is clear that he has erred in law and in his interpretation and application of the express terms of contract between the parties in a number of fundamental respects.
"However, and without prejudice to TfGM's right and intention to seek formal resolution to reverse the outcome of the Decision, TfGM is prepared to comply with the Decision on a provisional basis."
"Further to the issue of Payment Assessment nr 48 and the subsequent payments to Kier in accordance with the Adjudicator's decision dated 25th November 2019, we record that it has been issued on a provisional basis only and without prejudice to TfGM's right and intent to seek formal resolution to reverse the Decision."
"42. Clauses W2.3(11) and W2.4 of the Contract provided that the Adjudicator's decision would be final and binding unless one of the parties notified the other within four weeks of notification of the decision that (i) it was dissatisfied with a matter decided by the Adjudicator and (ii) it intended to refer the matter to the Court.
"43. The Contract did not stipulate the form of words that had to be used, or the level of detail that was required in any notice of dissatisfaction. The purpose of the notice was to inform the other party within a specified, limited period of time that the adjudication decision was not accepted as final and binding. A valid notice would have to be clear and unambiguous so as to put the other party on notice that the decision was disputed but did not have to condescend to detail to explain or set out the grounds on which it was disputed."
"46. The substance of the email was sufficient to notify Kier that the adjudication decision was disputed. It confirmed that the payment made to Kier in accordance with the decision was without prejudice to TfGM's right and intent to seek formal resolution to reverse the decision. This was consistent with the letter sent a few days earlier. Although the main purpose of the email was to clarify the status of the payment made, in particular to ensure that the payment was not construed as acceptance of the adjudication decision, it also contained notification that the decision was disputed and would be referred to Court. That would have been sufficient for the purpose of clauses W2.3(11) and W2.4. However, the email was not sent in compliance with clause 13.2 and WI 920; nor was it sent to Kier's solicitors in accordance with the notification by Walker Morris. Therefore, it would not have constituted valid notice of dissatisfaction."
"At the very least the use of the word in the present context is ambiguous, in the sense that it is fairly capable of more than one meaning. In those circumstances it ought to be construed against the charterers for two quite separate but interrelated reasons: first, this is not the case of a standard form of clause… It is what one might call a "Do it yourself" clause which has been prepared by Petroship themselves, for use in connection with their business. If it is ambiguous, it ought to be construed contra proferentem."
The Issues
(1) Will the determination of the validity of the Notice of Dissatisfaction substantially affect the rights of the Claimant / Defendant?
(2) Was the decision on a point of law 'obviously wrong'?
(3) Alternatively is the question one of general public importance and is the decision at least open to 'serious doubt'?
(4) Despite the agreement of the parties to resolve the matter by arbitration, is it just and proper in all the circumstances for the court to determine the question?
The Dispute
"(11) the Adjudicator's decision is binding on the Parties unless and until revised by the tribunal and is enforceable as a matter of contractual obligation between the Parties and not as an arbitral award. The Adjudicator's decision is final and binding if neither Party has notified the other within the times required by this subcontract that he is dissatisfied with a matter decided by the Adjudicator and intends to refer the matter to the tribunal."
"(2) If, after the Adjudicator notifies his decision a Party is dissatisfied, that Party may notify the other Party of the matter which he disputes and state that he intends to refer it to the tribunal. The dispute may not be referred to the tribunal unless this notification is given within four weeks of the notification of the Adjudicator's decision."
"Mister Cousins,
After seven days you weren't entitled to make any rulings. You must also
follow the rules of the UK in 1996 by the Housing Grants, Construction and
Regeneration Act (Construction Act).
If you do not withdraw your ruling before tomorrow, our solicitor mister
Hugh Smit will file request at ICE to reverse the ruling.
All rights reserved.
Kind regards"
"Dear Mister Cousins,
As stated many times we do not accept this adjudication and your jurisdiction in this case, therefore we do not recognition your ruling,
The referral notice we didn't receive within the 7 days, we received it at the 8th March 2021 at time 13.08, therefore the entire process is null and void.
All rights reserved."
"…Ravestein did not raise this particular challenge to my jurisdiction before I reached my decision. If they had raised it, I would have considered it. However, I am afraid that they are too late now, as I do not have the jurisdiction to change or withdraw my decision.
"In my email dated 1 March I directed that TEL could serve the Referral electronically as well as by hard copy. In my email dated 3 March I confirmed to the Parties that I considered the Referral had been served on 2 March and Ravestein did not challenge that date during the adjudication".
"The criticism or complaint, within this email is clearly as to jurisdiction by reason of TEL's (alleged) failure to provide the Referral Notice within 7 days of the Notice of Adjudication (see Clause W2.3(2) and Section 108(2)(b) of the Housing Grants, Construction and Regeneration Act 1996 (as amended)). The reference to "as stated many times" must be a reference to communications prior to the issue of the Decision."
The Parties' Submissions
(1) the Claimant asked the adjudicator to withdraw his ruling, which made it clear that the Claimant did not accept the adjudicator's decision was final and binding;
(2) the Claimant stated it would file a request with the ICE and so therefore made it clear that the merits of the adjudicator's decision was disputed, as ICE could only appoint an arbitrator to deal with the merits. An arbitrator would have no power to deal with a dispute as to the adjudicator's jurisdiction;
(3) the correct interpretation of the judgment of O'Farrell J in Transport for Greater Manchester was that:
a. no particular form of words, nor any particular level of detail, were required in the notice;
b. all that was required was to inform the Defendant that the adjudicator's decision was not accepted as final and binding;
c. it was not necessary to specify the specific matter in dispute;
d. there was no requirement to refer to arbitration in terms and having stated that the ICE would be asked to "reverse the ruling" of the adjudicator would in any event suffice for a requirement to state the intention to refer it to the tribunal.
As such, the arbitrator either did not reach the correct conclusion as to what the clauses required or, if he did, the correct analysis of the facts in the case should have caused him to conclude that the Notice of Dissatisfaction was valid. As he arrived at the opposite conclusion, he cannot have properly understood the principles which he stated;
(4) the wording of the notice did not only indicate a challenge to the adjudicator's jurisdiction but also indicated a challenge to the underlying decision - the wording used was such that the only possible conclusion was that the Claimant did not accept the adjudicator's decision on any basis, including on the merits;
(5) if there was any doubt about the proper construction of the notice, the arbitrator failed to apply The Pera properly because the effect of his decision permitted the stifling of an otherwise legitimate claim.
(1) that the notice requires the identification of the matter which the party disputes and that he intends to refer the matter to the tribunal;
(2) it was not sufficient simply to notify the other party that you do not accept that the adjudication decision is final and binding;
(3) the wording used by the Claimant in the email was not sufficient, objectively read, either to identify the matter about which the Claimant was dissatisfied as including a dispute on the merits nor that there was an intention to refer the matter to the tribunal.
Decision
Will the determination of the validity of the Notice of Dissatisfaction substantially affect the rights of the Claimant / Defendant?
Was the decision on a point of law 'obviously wrong'?
(1) evaluation of the wording of the 13:05 email itself,
(2) evaluation of the wording of the other emails sent by and to the adjudicator after he communicated his decision by email,
(3) the significant differences between the wording used in the notices in the Transport for Greater Manchester case and in this case,
(4) that a reference to the Housing Grants Construction and Regeneration Act 1996 could only be referable to a jurisdictional challenge and not to a challenge to the correctness of the decision itself,
(5) the fact that the alleged notice was an email sent to the adjudicator rather than to the other party (although the other party and their solicitors were copied in to the email) as required by the clause would militate against the email being a notice of dissatisfaction, and
(6) a challenge to the jurisdiction of the adjudicator is very different to a challenge as to the merits of his decision on the underlying dispute.
"Ravestein submits on the basis of The Pera that "if there is residual doubt as to whether Ravestein had complied with the clause, the ambiguity should be resolved in such a way as not to prevent an otherwise legitimate claim being pursued". Leaving aside whether that is a correct interpretation of The Pera, in my view, there is no doubt and no ambiguity. In my experience, true ambiguity when the words are capable of more than one meaning is rare. Ambiguity does not arise simply because Parties advance rival interpretations of a document: to use the words of Lord Wilberforce in Schuler (L) AGV Wickman Machine Tool Sales Ltd:
"… Ambiguity … is not to be equated with difficulty of construction, even difficulty to a point where judicial opinion as the meaning has differed",
and Lord Wright in Scammell v Ouston:
"Difficulty is not synonymous with ambiguity so long as any definite meaning can be extracted"."
Alternatively is the question one of general public importance and is the decision at least open to 'serious doubt'?
Despite the agreement of the parties to resolve the matter by arbitration, is it just and proper in all the circumstances for the court to determine the question?
Conclusion