BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?

No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!



BAILII [Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback]

Scottish Court of Session Decisions


You are here: BAILII >> Databases >> Scottish Court of Session Decisions >> SRB CIVIL ENGINEERING UK LTD AGAINST RAMBOLL UK LTD [2022] ScotCS CSOH_93 (20 December 2022)
URL: http://www.bailii.org/scot/cases/ScotCS/2022/2022_CSOH_93.html
Cite as: [2023] PNLR 11, 2023 GWD 2-22, 2023 SLT 423, [2022] ScotCS CSOH_93, [2022] CSOH 93

[New search] [Printable PDF version] [Help]


OUTER HOUSE, COURT OF SESSION
[2022] CSOH 93
CA43/21
OPINION OF LORD ERICHT
In the cause
SRB CIVIL ENGINEERING UK LIMITED
Pursuer
against
RAMBOLL UK LIMITED
Defender
Pursuer: Ellis KC; BTO Solicitors LLP
Defender: Barne KC; CMS Cameron McKenna Nabarro Oslwang LLP
20 December 2022
Introduction
[1]
The issue in this case is whether when a contract is novated the obligations under it
are extinguished or transferred to a new party.
[2]
SRB Civil Engineering Limited ("SRBCE") and Scottish Ministers entered into a
Design and Build Agreement (the "Design and Build Agreement") for the design and
construction of up-grading works to Junction 1A of the M9 at the Queensferry Crossing.
The defender contracted with SRBCE (the "Ramboll Contract") to provide design services to
SRBCE in relation to the Design and Build Agreement. As a result of a company
reorganisation, there was a wish for the pursuer and not SRBCE to be the party to the
2
Design and Build Agreement. A Novation Agreement was entered into by SRBCE, the
pursuer and the Scottish Ministers substituting the pursuer for SRBCE in the Design and
Build Agreement, and an Assignation was entered into between SRBCE and the pursuer.
[3]
In this action the pursuer is seeking damages from the defender for breach of
contract and breach of duty in respect of the Ramboll Contract. The pursuer pleads a
Principal Claim, a First Alternative Claim, and a Second Alternative Claim. The case called
before me for debate on the defender's motion for dismissal. Various other legal issues had
been raised by the parties, but parties were agreed that these other issues should be dealt
with by proof before answer should the case survive the debate.
Facts and contractual terms
[4]
The background to the dispute, as averred by the pursuer, is as follows.
[5]
SRBCE as Contractor and the Scottish Ministers as Employer entered into the Design
and Build Agreement on 20 July 2011. SRBCE was operated as a vehicle for a joint venture
between the John Sisk Group and the Roadbridge Group. The defender played a central role
in assisting SRBCE to formulate its tender. The conceptual or tendered design produced,
adopted, put forward and certified by the defender was an essential part in SRBCE being
able to formulate a tender. The defender was also responsible for and undertook the
detailed design of all elements on the Junction 1A Works. The Ramboll Contract was
formed between SRBCE and the defender in respect of all of these services.
[6]
From about July 2012 onwards SRBCE planned to transfer to the pursuer its whole
right title and interest in the Design and Build Agreement. From 28 September 2012
onwards all invoices for the defenders' services were rendered to the pursuer. Thereafter all
payment of the agreed fee for those services was made by the pursuer. On or about
3
19 November 2012 a letter on notepaper headed with logos of the stakeholders in the joint
venture and in the name of the pursuers was sent to all suppliers of SRBCE, including the
defender. It was headed "Corporate Structure Changes". It related specifically inter alia to
the M9 works which SRBCE was obliged to perform. It advised that from November 2012
the UK business was to be conducted through the pursuer which was itself a joint venture
between John Sisk and Roadbridge. It said that the pursuer would be working with "the
same terms and conditions". It requested that all invoices relating to SRBCE orders be
addressed to the pursuer. It made known to the defender that the pursuer would be
responsible for fulfilment of SRBCE obligations to the Scottish Ministers and that the
services the defender were obliged to provide to SRBCE should thereafter be and would
have to be provided to the pursuer. The pursuer's position is that the defender did not
object and by its conduct accepted the substitution of the pursuers as the contracting party;
that the defender took instruction from and provided services to the pursuer and that the
parties acted on the basis of the substitution of the pursuers from November 2012 onwards.
[7]
A Novation Agreement was entered into between SRBCE, the pursuer and the
employer dated on 12 July and 7 November 2013 (the "Novation Agreement").
[8]
The recitals were in the following terms:
"RECITING
A.
By an Agreement dated 20 July 2011 (the "Agreement") made by the [Scottish
Ministers] and [SRBCE, SRBCE] agreed to design, execute and complete the works
described in the Agreement ("the Works").
B.
The Works to be performed under the Agreement have by way of certificates
issued for Section A on the 19 June 2012, Section B on the 1 February, 2013 and
Section C on 29 March, 2013 been completed (with the exception of the list of defects
attached to the relevant Certificate), but [SRBCE's] obligations relating to the Defects
Notification Periods (as defined by the Agreement) remain outstanding.
4
C.
[SRBCE] and [the pursuer] have agreed, with the consent of [Scottish
Ministers], that [the pursuer] will take over the rights, obligations and liabilities of
[SRBCE] under the Agreement.
D.
The parties to this novation agreement have agreed to novate the Agreement
from [SRBCE] to [the pursuer] upon and subject to the terms of this novation
agreement."
[9]
The operative part of the Novation Agreement included the following clauses:
"2.
RELEASE BY [SRBCE] OF [SCOTTISH MINISTERS]
[SRBCE] releases and discharges the [Scottish Ministers] from the further
performance of the [Scottish Ministers] duties and obligations under the
Agreement.
3.
RELEASE BY THE [SCOTTISH MINISTERS] OF [SRBCE]
[Scottish Ministers] releases and discharges [SRBCE] from the further
performance of [SRBCE's] duties and obligations under the Agreement save
for any obligations in the Agreement as to confidentiality.
4.
ACCEPTANCE OF LIABILITY OF [SRBCE] BY [THE PURSUER]
[The pursuer] undertakes to perform all the duties and to discharge all the
obligations of [SRBCE] under the Agreement and to be bound by the terms of
the Agreement in every way as if [the pursuer] was and always had been
named as a party to the Agreement in lieu of [SRBCE] and as if all acts and/or
omissions of [SRBCE] under or pursuant to the Agreement prior to the last
date of execution of this novation agreement were the acts and omissions of
[the pursuer].
5.
ACCEPTANCE OF LIABILITY TO [THE PURSUER] BY [SCOTTISH
MINISTERS]
[Scottish Ministers] undertakes to perform all the duties and discharge all the
obligations of [Scottish Ministers] under the Agreement and to be bound by
the terms and conditions of the Agreement in every way as if [the pursuer]
was and always had been named as a party to the Agreement in place of
[SRBCE].
6.
VESTING OF REMEDIES AGAINST [SCOTTISH MINISTERS]
All rights of action and remedies against [Scottish Ministers] under and
pursuant to the Agreement vested in [SRBCE] will from the last date of
execution of this novation agreement vest in [the pursuer].
5
7.
VESTING OF REMEDIES AGAINST [SRBCE]
All rights of action and remedies under or pursuant to the Agreement
vested in [Scottish Ministers] will from the last date of execution of this
novation agreement lie against [the pursuer] and not [SRBCE].
8.
AFFIRMATION OF AGREEMENT
The terms and conditions of this novation agreement represent the entire
agreement between the parties relating to the novation of the Agreement and,
except as specifically amended by the provisions of this novation agreement,
all of the terms and conditions of the Agreement remain in full force and
effect.
9.
RIGHTS OF THIRD PARTIES
A person who is not a party to this novation agreement will have no right at
common law to enforce any term of this novation agreement."
[10]
On 20 July 2018, SRBCE as assignor and the pursuer as assignee entered into an
Assignation (the "Assignation"). The recitals to the Assignation stated:
"WHEREAS
A.
The Assignor entered into a contract with the Scottish Ministers on or about
20 July 2011 (the "D&B Contract") for the design and construction of upgrading
works to Junction 1A of the M9 (the "Works");
B.
The Assignor entered into contractual relations with [the defender]
("Ramboll") whereby Ramboll provided design services to the Assignor in respect of
the tender stages and to ultimately fulfil its obligations in the D&B Contract (the
"Ramboll Contract");
.....
D. The Assignor novated its rights and obligations in the D&B Contract to the
Assignee as formally recognised in a novation agreement in November 2013;
E. Defects in the pavement of the motorway which formed part of the Works
caused by breaches of the Ramboll Contract and failures in the delictual duty
of Ramboll first became apparent in about August 2013;
F. The Assignee paid substantial costs, expenses and liability in relation to the said
defects and carrying out of remedial works thereto;
6
G. The Parties hereto consider Ramboll to be liable and wish Ramboll to make
good the loss and damage caused by its breaches of the Ramboll Contract and its
failures in its delictual duty;
H. The Assignee stepped into the Ramboll Contract in or about September 2012
but said agreement was not embodied in a formal document at the time. An
assignation of various rights and interests of the Assignor to the Assignee may
assist in recovery of the true extent of that said loss and damage;
..."
[ ] In terms of the Assignation SRBCE and the pursuer agreed as follows:
"1. ASSIGNATION
1.1. The Assignor hereby assigns to the Assignee with immediate effect:
1.1.1. its whole right, title and interest, past, present and future in and to the
Ramboll Contract.......;
1.1.2. all claims past, present and future competent to it and/or which it has title
to bring for damages for its own loss and/or losses sustained as a result of
breaches of any contractual or delictual obligations incumbent on Ramboll as a
result of or arising from the Ramboll Contract....;
1.1.3. all claims, past, present and future, competent to it, and/or which it has
title to bring, to claim damages for, and/or recover loss and damage suffered
by, the Assignee as the party vested in the rights and obligations in the D&B
Contract after 7 November 2013, which were formerly held by the Assignor,
whether on behalf of the Assignee or otherwise, resulting and/or arising from
any breaches of contractual or delictual obligations incumbent on Ramboll as a
result of or arising from the Ramboll Contract....."
The Principal and Alternative Claims
[11]
The Principal and Alternative Claims are set out in article 1 of condescendence.
"Principal Claim
The principal position of the Pursuers is that the damages sued for in the
circumstances hereinafter averred are a measure of a loss sustained by [SRBCE]. The
Pursuers sue for recovery of that loss as assignee of SRBCE's whole right title and
interest to the contractual relations between SRBCE and the Defenders averred in
this action and of all SRBCE claims against the Defenders arising therefrom... under
paragraphs 1.1.1 and 1.1.2 of the Assignation .. The Pursuer contends that the loss
sustained by SRBCE is properly measured by the measure of damages averred,
7
notwithstanding substitution of the Pursuers as the contracting party in the [Design
and Build Agreement]. It was not the intention of the parties to the contractual
relations with the Defenders hereinafter averred that any loss caused to SRBCE
would disappear because of an internal reorganisation of the structure of the joint
venture by the stakeholders which substituted the corporate vehicle for the joint
venture with another for the performance of obligations in the contract with the
Scottish Ministers.
`First Alternative Claim
Alternatively failing recovery of the damages claimed on the basis of the principal
claim, the Pursuers seek payment of the damages claimed as loss suffered by them as
the party which was obliged under the terms of the contract with the Scottish
Ministers having been substituted as the contracting party and which has actually
incurred the costs of the works and others which form the measure of th e damages
claimed and which (a) succeeded to the right and title of SRBCE in the contractual
relations between SRBCE and the Defenders in the circumstances hereinafter averred
and had done so at the time the relevant costs were incurred; and (b) enjoys the
benefit of an assignation of any right title and interest of SRBCE in said contractual
relations under paragraph 1.1.1 of the Assignation.'
`Second Alternative Claim
Alternatively failing recovery of the damages on the basis of either the primary claim
or the first alternative claim, the Pursuers seek recovery of the damages claimed in
the circumstances averred as assignee of SRBCE under Clause 1.1.3 of the
Assignation in respect of any right which SRBCE has to claim damages on the
Pursuers' behalf as a loss suffered by the Pursuers as a party subsequently vested in
SRBCE's rights and liabilities under the D&B contract with Scottish Ministers
hereinafter averred.'"
Submissions for the defender
[12]
Senior counsel for the defender did not insist on his plea of no title to sue but invited
me to dismiss the action, which failing to put the case out by order for discussion of deletion
of pleadings to give effect to my decision.
[13]
He submitted that the nub of the dispute was the Novation Agreement. SRBCEs
obligations under the Design and Build Agreement had been extinguished. Any loss which
SRBCE may have suffered was avoided and therefore not recoverable in damages. This was
8
the legal effect of SRBCE being discharged from all liabilities under the Design and Build
Agreement in terms of the Novation Agreement (Swynson v Lowick Rose [2018] AC 313).
[14]
In relation to the First Alternative Claim, counsel submitted that the pursuer could
not recover loss suffered by SRBCE in its own right. There were no averments that indicate
that the breach occurred after the pursuer stepped into the Ramboll Contract.
Paragraph 1.1.1 of the assignation was irrelevant since SRBCE could not assign a right to the
pursuer for the pursuer to recover what on the pursuer's analysis was pursuer's own loss.
The substitution did not transfer anything to the defender in relation to past breaches. The
pursuer had failed to plead how substitution had taken place (MRS Distribution Ltd v DS
Smith (UK) Ltd 2004 SLT 631, Blyth and Blyth v Carillion 2002 SLT 961).
[15]
In relation to the Second Alternative Claim, Counsel for the defender submitted that
clause 1.1.3 of the assignation was intended to assign to the pursuer any right that SRBCE
may have had to recover losses suffered by the pursuer as the party vested in the Design
and Build Agreement. The pursuer voluntarily gave up the ability to seek damages by
entering into the Novation Agreement. The loss suffered by SRBCE was avoided as a result
of the Novation Agreement. There was, therefore, no question of there being a transferred
loss recoverable by SRBCE. This was not a situation where the law allowed one party to
recover loss suffered by another party in order to avoid a legal black hole. The black hole
had been created by SRBCE's own actings. (Alfred MacAlpine Construction Ltd v Panatown Ltd
(No.1) [2001] 1 AC 518, Swynson v Lowick Rose, BV Nederlandse Industrie v Rembrant Enterprises
Inc [2020] QB 551, Mclaren Murdoch & Hamilton Ltd v Abercromby Motor Group Ltd 2003
SCLR 323).
9
Submissions on behalf of the pursuer
[16]
Senior counsel for the pursuer invited me to allow a proof before answer with all
pleas standing.
[17]
The averments as to the substitution of the pursuer for SRBCE depended on the
defender starting to invoice the pursuer for its services in September 2012, a letter in about
November 2012 and acceptance by conduct. The presumption against delegation could be
displaced by informal arrangements (WJ Harte Construction v Scottish Homes 1992 SC 99).
Analogous situations depended on the facts (Skene v Greenhill 1825 4S 25; Blyth and Blyth v
Carillion).
[18]
All the losses averred were sustained by SRBCE and it was appropriate for the loss
measured by these investigations and remedial works to be recovered by the pursuer. The
transfer of the interest in the Design and Build Agreement to the pursuer was irrelevant to
the claim against the defender (McLaren, Murdoch & Hamilton v Abercromby Motors). The
damage had already occurred before SRBCE transferred its interest to the pursuer by the
Novation Agreement (GUS v Littlewoods 1982 SC (HL) 157). As assignee the pursuer may
recover SRBCE's losses to the extent that SRBCE could have recovered damages if it had not
granted the assignation and had not transferred the interest in the Design and Build
Agreement (Offer-Hoar v Larkstore [2016] 1 WLR 2926, followed in Pegasus Management v
Ernst & Young [2012] PNLR 24). The Novation Agreement did not remove the loss already
sustained by SRBCE and sued for by the pursuer's assignee. The Novation Agreement was
a transfer not a discharge.
[19]
Counsel submitted that the First Alternative came into question only if the
expenditure incurred by the pursuer itself was not recoverable as a measure of loss suffered
by SRBCE. The pursuer could recover that expenditure as losses of the pursuer in its own
10
right as successor to SRBCE in the Design and Build Agreement. The pursuer incurred the
expenditure. If the loss was not that of SRBCE it was that of the pursuer. The loss in
relation to the detailed design failures may, after the facts are elucidated, have been incurred
after the "substitution in" of the pursuer for SRBCE in the contract with the defen der. If it
turned out that the substitution invested in the pursuer all rights of SRBCE including those
to claim for prior breaches, the pursuer would be able to sue in its own right for the losses
which it incurred in respect of pre-substitution breaches. This would be inherently more
likely in the event that the losses were not those of SRBCE. In the circumstances it was
appropriate for the averments to remain on record as a fall back pending determination of
the facts.
[20]
Counsel submitted as a fall back that if the loss was not recoverable on the Principal
or First Alternative basis, it was recoverable on the basis that SRBCE had the right to recover
losses incurred by subsequent parties' vested in the rights and obligations of the Design and
Build Agreement (McLaren, Murdoch & Hamilton at paragraph 42; Alfred McAlpine v
Panatown; Axon Well v Craig [2015] CSOH 4). If the loss was not recoverable on the Principal
Claim or the First Alternative Claim, a breach of contract (and associated breach of duty)
had produced a loss which the pursuer had no direct right to recover. The law would not
tolerate that such a loss should go unrecovered. The transfer of rights and obligat ions to the
pursuer and to the Design and Build Agreement was irrelevant to the measure of loss
(GUS v Littlewoods at page 177).
Analysis and decision
[21]
The defender seeks dismissal of the action on the basis of the following argument.
As a result of the Novation Agreement, the Scottish Ministers have no claim for past or
11
future breaches of the Design and Build Agreement against SRBCE. This was because the
Novation Agreement effected a novation by delegation in terms of which a new debtor is
substituted and the obligations that lay on the original debtor are discharged. Since SRBCE's
liability to the Scottish Ministers under the Design and Build Agreement was discharged in
relation to any past breaches, any corresponding obligation on the defender to relieve
SRBCE from the consequences of those breaches was also discharged. Any loss that SRBCE
may have incurred to the Scottish Ministers was discharged and as therefore SRBCE had
suffered no loss there was nothing for the pursuer to recover. The loss suffered by SRBCE
was avoided as a result of the Novation Agreement and there was therefore no question of
there being a transferred loss recoverable by SRBCE. Therefore the action fell to be
dismissed.
[22]
I do not accept that argument. The legal effect of the Novation Agreement is not, as
the defender submits, that the obligations and liabilities of SRBCE to the Scottish Ministers
disappear, but that they are transferred to the pursuer.
[23]
The Novation Agreement is an example of delegation. Delegation is a form of
novation. The nature of delegation is apparent from the following:
"Innovation is the turning of one obligation into another; and if it be a third person
becoming debtor for relief of a former debtor, it is called Delegation "(Stair
Institutions of the Law of Scotland I.18.8) (emphasis added)
"Obligations are also dissolved by novation or innovation, which, in the strict
acceptance of the word, denotes the change of one obligation to another in such
manner that both the debtor and creditor continue the same. The first obligation
being thus extinguished by novation, the cautioners in it must necessarily get free;
and all the penalties or damage arising from it are understood to be purged or rather
discharged: so that the debtor remains bound only by the new
obligation....Delegation, which may be accounted a species of novation, is the
changing of one debtor for another, by which the obligation laid on the first debtor
is discharged."(Erskine's Institutes III.iv.22). (emphasis added)
12
"Delegation is the extinction of the liability of one party by the substitution of the
liability of another. It is a form of novation ­ the extinction of one debt by the
substitution of another". (Gloag on Contract (2
nd
Edn) p 258) (emphasis added)
"Delegation is a kind of novation, by which the original debtor, in order to be
liberated from his creditor, gives him a third person, who becomes obliged in his
stead to the creditor.." Pothier Treatise on the Law of Obligations part III Chapter II
ArticleVI.1 (emphasis added)
[24]
Where there is delegation the obligations owed by the original party under the
contract are extinguished, but that is not all that happens. A new party is substituted for the
original party. The new party takes over these obligations and becomes obliged in the
original party's place.
[25]
These two elements - extinction and substitution - are found in the Novation
Agreement in this case.
[26]
Extinction is dealt with in clause 2 in respect of the obligations of the Scottish
Ministers and clause 3 in respect of the obligations of SRBCE. Clause 3 states:
"3.
RELEASE BY [SCOTTISH MINISTERS] OF [SRBCE]
The [Scottish Ministers] releases and discharges [SRBCE] from the further
performance of [SRBCE's] duties and obligations under the Agreement ...."
[27]
Substitution is dealt with in clauses 4 and 5, which impose obligations on the pursuer
in substitution of the extinguished obligations of SRBCE. The new obligations replicate the
extinguished obligations and are retrospective:
"4.
ACCEPTANCE OF LIABILITY OF [SRBCE] BY [THE PURSUER]
[The Pursuer] undertakes to perform all the duties and to discharge all the
obligations of [SRBCE] under the Agreement and to be bound by the terms of the
Agreement in every way as if [the pursuer] was and always had been named as a
party to the [Design and Build] Agreement in lieu of [SRBCE] and as if all acts
and/or omissions of [SRBCE] under or pursuant to the Agreement prior to the last
date of execution of this novation agreement were the acts and omissions of [the
Pursuer].
13
5.
ACCEPTANCE OF LIABILITY TO [THE PURSUER] BY [SCOTTISH
MINISTERS]
[Scottish Ministers] undertakes to perform all the duties and discharge all the
obligations of the [Scottish Ministers] under the Agreement and to be bound by the
terms and conditions of the Agreement in every way as if [the pursuer] was and
always had been named as a party to the Agreement in place of [SRBCE] (emphasis
added)."
[28]
The effect of the substitution in respect of rights of action and remedies is set out in
clauses 6 and 7. Clause 6 provides that rights of action and remedies against Scottish
Ministers vest in the pursuer. Clause 7 provides:
"7.
VESTING OF REMEDIES AGAINST [SRBCE]
All rights of action and remedies under or pursuant to the Agreement vested in
[Scottish Ministers] will from the last date of execution of this novation agreement lie
against [the pursuer] and not [SRBCE]".
[29]
The legal effect of the Novation Agreement is that the pursuer has been substituted
for SRBCE. The pursuer is are liable to the Scottish Ministers as if the pursuer and not
SRBCE had been the original party to the Agreement. SRBCE's obligations to Scottish
Ministers have been extinguished, but liability to Scottish Ministers has not vanished:
SRBCE's obligations to Scottish Ministers have been replaced with new obligations of the
pursuer to the Scottish Ministers. Under these new obligations, the pursuer is liable to
Scottish Ministers in respect of breach of contract and breach of duty in respect of the Design
and Build Agreement as if the pursuer, and not SRBCE, was the original party to that
Agreement.
[30]
Nor has the loss suffered by Scottish Ministers for any breach of the Design and
Build Agreement vanished. The Scottish Ministers are no longer entitled to recover their
loss from SRBCE. SRBCE's obligations have been extinguished and so damages cannot be
recovered from SRBCE for breach of these obligations. However, the actions or omissions of
14
SRBCE are now to be treated as actions or omissions of the pursuer. Scottish Ministers are
entitled to recover from the pursuer the same damages which they could have recovered
from SRBCE had the Novation Agreement never been entered into. The liabilities to Scottish
Ministers under the Design and Build Agreement remain, but are now liabilities of the
pursuer and not SRBCE.
[31]
In the present action, we are one step removed from the Novation Agreement. The
pursuer is suing the defender for breach of contract and breach of duty in relation to the
Ramboll Contract.
[32]
The original parties to the Ramboll contract were the SRBCE and the pursuer. This
action has been raised not by SRBCE but the pursuer. In respect of title to sue, the pursuer
founds on the Assignation. The Assignation provides
"1.1. [SRBCE] hereby assigns to the [the pursuer] with immediate effect:
1.1.1. its whole right, title and interest, past, present and future in and to the Ramboll
Contract.......;
1.1.2. all claims past, present and future competent to it and/or which it has title to
bring for damages for its own loss and/or losses sustained as a result of breaches of
any contractual or delictual obligations incumbent on [the defender] as a result of or
arising from the Ramboll Contract...;
1.1.3. all claims, past, present and future, competent to it, and/or which it has title to
bring, to claim damages for, and/or recover loss and damage suffered by, [the
pursuer] as the party vested in the rights and obligations in the D&B Contract after
7 November 2013, which were formerly held by [SRBCE], whether on behalf of the
[pursuer] or otherwise, resulting and/or arising from any breaches of contractual or
delictual obligations incumbent on [the defender] as a result of or arising from the
Ramboll Contract...."
[33]
The pursuer has title to sue under the Assignation. If the legal effect of the Novation
Agreement had been no more than the extinguishing of SRBCE's obligations, then there
would have been force in the defender's argument that the pursuer had suffered no loss for
which it should be compensated. But that is not what happened here. There was delegation
15
in terms of the Novation Agreement. SRBCE's obligations to Scottish Ministers were
replaced by the pursuer's obligations to Scottish Ministers. The effect of the Novation
Agreement is that the pursuer became liable to the Scottish Ministers to make good the
Scottish Minister's loss from the start of Design and Build Agreement.
[34]
When it comes to quantifying the loss, there is no practical difference in the amount
of the loss which would have been sustained by SRBCE under its extinguished obligations
and the loss sustained by the pursuer. The pursuer is liable to Scottish Ministers as if it had
always been a party, so the amount of the pursuer's loss in respect of the period prior to the
date of the Novation Agreement is the same as SRBCE's loss would have been.
[35]
In addition to its averments on the Novation Agreement, the pursuer also pleads that
there was substitution from November 2012 on the basis of letters and the actings of the
parties. Although it can be difficult to establish delegation on the basis of letters and actings
as there is a presumption against delegation (W J Harte Construction Limited v Scottish Homes,
MRS Distribution Ltd v DS Smith) the appropriate time to assess whether that presumption
has been overcome is after hearing the facts. That issue is best dealt with after the facts have
been established.
Order
[36]
I shall repel the defender's first plea in law (no title to sue) for want of insistence,
refuse the defender's motion to dismiss the action, and allow a proof before answer. I shall
put the case out by order for discussion of further procedure.


BAILII: Copyright Policy | Disclaimers | Privacy Policy | Feedback | Donate to BAILII
URL: http://www.bailii.org/scot/cases/ScotCS/2022/2022_CSOH_93.html