United Kingdom Statutory Instruments |
||
You are here: BAILII >> Databases >> United Kingdom Statutory Instruments >> The Water Resources (Environmental Impact Assessment) (England and Wales) Regulations 2003 No. 164 URL: http://www.bailii.org/uk/legis/num_reg/2003/20030164.html |
[New search] [Help]
Made | 30th January 2003 | ||
Laid before Parliament | 31st January 2003 | ||
Coming into force | 1st April 2003 |
1. | Citation, commencement and extent |
2. | Interpretation |
3. | Requirement for an environmental impact assessment |
4. | Determination whether a project is a relevant project |
5. | Environmental statement to be provided in relation to an application for authorisation |
6. | Environmental statement, and opinions of the Agency on the contents of an environmental statement |
7. | Publicity for environmental statement |
8. | Determination of application and notice of determination |
9. | Restriction on abstracting or impounding water |
10. | Agency's decision on an application for consent |
11. | Appeals in relation to consents |
12. | Validity of decisions of appropriate Minister |
13. | Called-in applications in relation to abstraction or impounding licences |
14. | Variation of abstraction or impounding licence at instance of Agency or Secretary of State |
15. | Modifications where regulation 14 applies |
16. | Register of environmental statements and further information |
SCHEDULE 1 | Selection criteria for relevant projects |
SCHEDULE 2 | Information about proposed project |
Requirement for an environmental impact assessment
3.
- (1) An environmental impact assessment shall be carried out in accordance with these Regulations in relation to a relevant project.
(2) A project is a relevant project if -
(3) A project is not a relevant project if it involves -
(3) Where the Agency considers that it has insufficient information to determine the request, it shall by notice in writing inform the applicant and specify what further information it requires.
(4) In determining whether a project is a relevant project the Agency shall take into account such of the selection criteria set out in Schedule 1 as are relevant.
(5) The Agency shall give the applicant written notice of its determination before the expiry of -
(b) such longer period as may be agreed in writing with the applicant.
(6) Where -
the applicant may apply to the appropriate Minister for a determination on the matter by notice in writing not later than twenty-eight days after the expiry of that period or, as the case may be, after the date of the determination of the Agency.
(7) Where an application is made to the appropriate Minister under paragraph (6), the appropriate Minister shall send a copy of the application to the Agency.
(8) The appropriate Minister shall by notice in writing given to the applicant and the Agency -
(9) A determination under this regulation shall be accompanied by a written statement of the reasons for that determination.
(10) The Agency or, as the case may be, the appropriate Minister shall take such steps as are considered appropriate to make a determination under this regulation available to the public.
(11) The applicant shall include a copy of any determination made under this regulation when he subsequently applies for, or for a variation of, an authorisation in relation to the project in question.
Environmental statement to be provided in relation to an application for authorisation
5.
An environmental statement which complies with regulation 6 shall be provided in relation to an application made after 31st March 2003 for, or for the variation of, an authorisation in connection with a relevant project.
Environmental statement, and opinions of the Agency on the contents of an environmental statement
6.
- (1) An environmental statement shall include such of the information set out in Schedule 2 as is relevant to the relevant project and at least the following -
(2) If a person so requests before making an application for, or for the variation of, an authorisation, the Agency shall, having consulted the person making the request and the consultation bodies, give an opinion on the information which should be contained in an environmental statement accompanying such an application.
(3) The fact that the Agency has given an opinion under paragraph (2) shall not preclude it from subsequently requiring the person making the request to provide further information.
(4) The Agency and the consultation bodies shall, if requested by a person proposing to make an application for which an environmental statement is required, enter into consultation with him to determine whether they have in their possession any information which may be relevant to the preparation of an environmental statement and, if they have, they shall make it available to him.
(5) Paragraph (4) shall not require the disclosure of information which is capable of being treated as confidential or must be so treated under regulation 4 of the Environmental Information Regulations 1992[10].
(6) Any body which provides information to a person under paragraph (4) may require him to pay a charge which reflects the cost of making that information available.
(7) If the Agency considers that an environmental statement does not contain all the information required by paragraph (1), it shall by notice in writing -
and the applicant shall provide that information to the Agency.
Publicity for environmental statement
7.
- (1) Where an environmental statement or further information is provided in accordance with regulation 6, the applicant shall publish, in the London Gazette and at least once in each of two successive weeks in one or more newspapers circulating in the relevant locality, a notice -
(2) By not later than such date as may be specified by the Agency, the applicant shall send a copy of the notice published in the London Gazette and the environmental statement or, as the case may be, the further information, to -
under cover of a letter stating that any representations in relation to the application should be made in writing to the Agency within a period of twenty-eight days beginning on the date of the letter.
(3) The applicant shall send to the Agency a copy of any notice published (other than in the London Gazette) under paragraph (1) and any letter sent under paragraph (2).
(4) Notice of an environmental statement under paragraph (1) may be combined with any notice required under other legislation which publicises the application in question.
Determination of application and notice of determination
8.
- (1) The Agency shall not determine an application for, or for the variation of, an authorisation relating to a relevant project before the latest date allowed under these Regulations for making representations or concluding any consultation.
(2) In determining the application the Agency shall take into consideration the environmental statement, any further information provided, and any representations relating to the environmental effects of the project made to the Agency in accordance with these Regulations.
(3) Within twenty-eight days of the decision on the application, the Agency shall publish in those newspapers in which a notice was published under regulation 7 a notice stating that the Agency has granted or refused the application and stating a place and times where any person may inspect -
(4) No appeal shall be brought under section 43 of the 1991 Act (appeals to the Secretary of State) on the grounds that the Agency has failed to give notice as required by subsection (1)(b) of that section before the expiry of a period of four months commencing with -
whichever is the later.
(2) Consent under regulation 10 is not needed in relation to a project if an abstraction or impounding licence is required.
(3) A person may rely on a consent granted under regulation 10 even though he is not the person to whom the consent was granted.
(4) A person who contravenes paragraph (1) shall be guilty of an offence and liable -
Agency's decision on an application for consent
10.
On an application made in writing to the Agency for a consent for the purposes of regulation 9, the Agency may, subject to the requirements of Part II -
taking into account any significant effects the relevant project is likely to have on the environment.
Appeals in relation to consents
11.
- (1) Subject to the following provisions of this regulation, where an application has been made to the Agency for a consent under regulation 10, the applicant may by notice in writing appeal to the appropriate Minister if -
(2) A notice of appeal under paragraph (1) shall be served within a period of twenty-eight days from -
whichever is the later.
(3) The applicant shall serve a copy of the notice of appeal on the Agency before the expiry of the period of twenty-eight days referred to in paragraph (2).
(4) Where any representations in writing with respect to the application were made within the period specified in accordance with regulation 7(1)(d), the Agency shall serve a copy of the notice of appeal on each of the persons who made those representations; and any person so served with a copy of the notice of appeal may make further representations to the appropriate Minister in writing within a period of twenty-one days from the date on which the copy of the notice is served on him.
(5) No appeal shall be brought by virtue of paragraph (1)(b) before the expiry of a period of four months commencing with -
whichever is the later.
(6) The appropriate Minister -
(7) Before determining the appeal, the appropriate Minister may -
and the appropriate Minister shall act as mentioned in sub-paragraph (a) or (b) if so requested by the applicant or the Agency.
(8) Subsections (2) to (5) of section 250 of the Local Government Act 1972[11] (local inquiries, evidence and costs) apply in relation to inquiries or other hearings under this regulation as they apply to inquiries under that section, but as if -
(9) The appropriate Minister, in determining the appeal, shall take into account -
(10) Where the decision on the appeal is that a consent is to be granted, the decision shall include a direction to the Agency to grant a consent containing such provisions as may be specified in the direction.
Validity of decisions of appropriate Minister
12.
- (1) Except as provided by the following provisions of this regulation, the validity of a decision of the appropriate Minister on any appeal under regulation 11 shall not be questioned in any legal proceedings whatsoever,
(2) If the Agency or the applicant desires to question the validity of the decision of the appropriate Minister on the grounds -
the Agency or, as the case may be, the applicant may, at any time within the period of six weeks beginning with the date on which the decision is made, make an application to the High Court under this regulation.
(3) On any application under paragraph (2), the High Court may by interim order suspend the operation of the decision to which the application relates until the final determination of the proceedings.
(4) If the High Court is satisfied, on an application under paragraph (2) -
the High Court may quash the decision.
(4) The notice required by section 52(4) of the 1991 Act (notice of proposals formulated under that section) -
Modifications where regulation 14 applies
15.
- (1) This regulation applies where it is determined under regulation 14 that the proposals would amount to or form part of a relevant project.
(2) The Agency shall prepare an environmental statement in accordance with regulation 6(1).
(3) Regulations 6(2) to (7), 7 and 8 shall not apply.
(4) Section 52(4) to (8) of the 1991 Act (notice of proposals under that section) shall apply as if the environmental statement were part of the proposals formulated by the Agency.
(5) The Agency shall, not later than the date of publication of the notice for the purposes of section 52(4) of the 1991 Act, send to the appropriate Minister and the consultation bodies a copy of the proposals and the environmental statement under cover of a letter stating that any representations on the proposals should be made in writing to the Agency within a period of twenty-eight days beginning on the date of that notice.
(6) The Agency or, as the case may be, the appropriate Minister shall not determine an application for, or for the variation of, an authorisation relating to a relevant project before the latest date allowed under these Regulations for making representations or concluding any consultation.
(7) In determining whether a licence should be varied, the Agency or, as the case may be, the appropriate Minister shall have regard to the environmental statement and any representations relating to the environmental effects of the project made to the Agency or the appropriate Minister within the period referred to in paragraph (5).
(8) Where a licence is varied in pursuance of proposals to which this regulation applies, the Agency shall, within twenty-eight days of the variation, publish in those newspapers in which a notice was published under section 52(4) of the 1991 Act a notice stating that the Agency has varied the licence, and stating a place where any person may inspect -
Signed by authority of the Secretary of State
Elliot Morley
Parliamentary Under-Secretary of State, Department for Environment, Food and Rural Affairs
30th January 2003
2.
Location of projects
The environmental sensitivity of geographical areas likely to be affected by projects must be considered, having regard, in particular, to -
3.
Characteristics of the potential impact
The potential significant effects of projects must be considered in relation to criteria set out under paragraphs 1 and 2, and having regard in particular to -
2.
An outline of the main alternatives studied by the developer and an indication of the main reasons for his choice, taking into account the environmental effects.
3.
A description of the aspects of the environment likely to be significantly affected by the proposed project, including, in particular, population, fauna, flora, soil, water, air, climatic factors, material assets, including the architectural and archaeological heritage, landscape and the inter-relationship between the above factors.
4.
A description[14] of the likely significant effects of the proposed project on the environment resulting from:
and the description by the developer of the forecasting methods used to assess the effects on the environment.
5.
A description of the measures envisaged to prevent, reduce and where possible offset any significant adverse effects on the environment.
6.
A non-technical summary of the information provided under the above headings.
7.
An indication of any difficulties (technical deficiencies or lack of know-how) encountered by the developer in compiling the required information.
[3] OJ L175, 5.7.1985, p.40.back
[4] OJ L73, 14.3.1997, p.5.back
[8] See the Government of Wales Act 1998, Schedule 2, paragraph 2.back
[10] S.I. 1992/3240, amended by S.I. 1998/1447.back
[11] 1972 c.70; section 250(4) was amended by Part II of Schedule 12 to the Housing and Planning Act 1986 (c.63).back
[12] O.J. No. L103, 25.4.1979, p.l. Directive as last amended by the 1994 Act of Accession.back
[13] O.J. No. L206, 22.7.1992, p.7.back
[14] This description should cover the direct effects and any indirect, secondary, cumulative, short, medium and long-term, permanent and temporary, positive and negative effects of the project.back
© Crown copyright 2003 | Prepared 11 February 2003 |