BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Supablast (Nationwide) Ltd. v Story Rail Ltd. [2010] EWHC 56 (TCC) (21 January 2010) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2010/56.html Cite as: [2010] EWHC 56 (TCC), [2010] BLR 211 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
SUPABLAST (NATIONWIDE) LIMITED |
Claimant |
|
- and - |
||
STORY RAIL LIMITED |
Defendant |
____________________
Steven Walker (instructed by Dickinson Dees LLP) for the Defendant
Hearing dates: 14 January 2010
____________________
Crown Copyright ©
Mr Justice Akenhead :
Introduction
The Factual Background
"Further to our recent quotation for the grit blasting, painting and scaffolding works for the above named tender we have pleasure in confirming our subsequent agreed prices:
1. Grit Blasting and Painting for the fixed price of £222,000.00
2. Scaffolding and Encapsulation for the fixed price of £158,459.60"
They looked forward to receiving Story's "official order".
"Further your quotation…dated 17th December 2007 for grit blasting, painting and scaffolding works on the above contract. We confirm our acceptance of your price in the sum of £380,459.60 nett plus VAT.
Please treat this letter as our order to carry out the works. Our sub contract order amended in line with the main contract will follow in due course. The terms and conditions of subcontract shall be the ICE sixth edition form of subcontract. The sub contract reference number that should be quoted on all correspondence is SUB0000232/SR12960…
Please note that it is a condition of the sub-contract that you have the requisite insurance cover as required under the Main Contract. We would be obliged if you would send a copy of your certificate(s) of insurance to our head office…"
This letter is headed "Letter on [sic] Intent"
"8(1) The Sub-Contractor shall make such variations of the Sub-Contract Works, whether by way of addition, modification or omission, as may be:
(a) ordered by the Engineer under the Main Contract and confirmed in writing the Sub-Contractor by the Contractor; or
(b) agreed to be made by the Employer and the Contractor and confirmed in writing to the Sub-Contractor by the Contractor; or
(c) ordered in writing by the Contractor…
(9) (1) All authorised variations of the Sub-Contract Works shall be valued in the manner provided by this Clause and the value thereof shall be added to or deducted from the price specified in the Third Schedule hereto or as the case may require.
(2) The value of all authorised variations shall be ascertained by reference to the rates and prices (if any), specified in the Sub-Contract for the like or analogous work, but if there are no such rates and prices, or if they are not applicable, then such values shall be such as is a fair and reasonable [sic] in all the circumstances. In determining what is fair and reasonable valuation, regard shall be had to any valuation made under the Main Contract in respect of the same variation…
18(1) If any dispute or difference shall arise between the Contractor and the Sub-Contractor in connection with or arising out of the Sub-Contract, or carrying out of the Sub-Contract Works…whether arising during the progress of the Sub-Contract Works or after their completion it shall be settled in accordance with the following provisions…
(4) (a) The Contractor and the Sub-Contractor each has the right to refer any dispute under the Sub-Contract for adjudication and either party may at any time give notice in writing (hereinafter called the Notice of Adjudication) to the other of his intention to refer the dispute to adjudication. The Notice of Adjudication and the appointment of the adjudicator shall…be as provided at paragraphs 2 and 3 of the Institution of Civil Engineers' Adjudication Procedure (1997). Any dispute referred to adjudication shall be conducted in accordance with the Institution of Civil Engineers' Adjudication Procedure (1997)…"
Sub-Contractor Name | Supablast Nationwide Ltd |
Description of Works to be Sub-Let | Scaffold and encapsulation Steelwork repairs inc new walkway, bracings etc Blasting and painting |
MAIN CONTRACT DETAILS | |
Main Contract Form | RT3 form of contract based on ICE 6th Edition |
LA Damages | £2500.00 per day |
Sub-Contract Details | |
Conditions applicable | ICE 6th Edition amended in line with the main contract |
Further documents to be incorporated in subcontract agreement | Documents listed in subcontract enquiry 18th of September 2007 Schedule of application and payment dates |
Subcontract Price (EXC VAT) | Scaffold £158,459.60 Steelwork £552,203.40 Blasting and painting £222,000.00 |
Fixed or Fluctuating Price | Fixed Price |
Payment Details: (Clause 15) | |
Insurance's-Cover/Expiry Date/Provide Details | Expires 31/3/08 SNL to renew and maintain for the duration of the contract |
Retention | 3% till practical completion 1.5% till making good defects certificate |
Applications for payments-Submission dates | As per payment schedule handed over in this meeting |
The first date for application for payment | 26th January 2008 |
Programme | |
Main contract commencement date | 28th January 2008 |
Main contract completion date/period | 14 weeks |
Period for submission and approval of all subcontractor's drawings… | SNL to supply programme by 21/1/08 |
Period of notice to subcontractor to commence on site. | Notice given in meeting |
The date for commencing of the subcontract works on site will, subject to the progress of the Main Contract programme be… | Scaffold to commence 21st Jan 08 |
Overall period carrying out and completion of the subcontract works on site: | 60 Days |
Number of separate visits | One continuous |
Information | |
Subcontractor's Requirements | Full set of contract issue drawings requested. JW [of Story] to action |
Subcontractor to prepare shop drawings/As Built/Maintenance Manual | Prior to final payment |
Particular client and specification requirements | …JP [Supablast] proposed alternative steel specification JP to TQ [raise Technical query] SRL |
Materials and Equipment | |
Contract Manager/Tel no: | Lauront Hostache 07766 776696 Blast and paint Rob Broadhurst for scaffold Steelwork to be advised |
Number of men, average/peak | 6 for scaffold 6 for painting 6 for steelwork |
Any Proposed sub-contractors? | Scaffold by Lyndon Steelwork to be advised |
Attendance at Progress/Technical Meetings? (Date of 1st meeting) | Every two weeks first to be held 5th February 08 |
Additional Issues | |
All terms and conditions of subcontractors quotation deleted in favour of the Main Contractor conditions | |
It is noted that the subcontractor fully under-stands the work and has quoted in relationship to the drawings and specification. No work will be entertained through lack of knowledge of these documents. |
There was an "Any Other Business" box to be filled in as required. Mr Smithson of Story says in his witness statement of 8 January 2010 that, at the end of 16 January 2008 meeting, he "anticipated that Supablast would be carrying out the steelwork repairs"
"Further your revised quotation dated 3rd January 2008 for steelwork repair works on the above contract. We confirm our acceptance of your price in the sum of £552,203.40 nett plus VAT."
Thus this letter specifically also said that the "subcontractor reference number that should be quoted on all correspondence is SUB0000232/SR12960" which was the same reference given in the earlier letter.
"In accordance with Clause 6(5) of the Sub-Contract Agreement, we hereby formally confirm that we have been issued with an Extension of Time under the Main Contract revising the Completion Date as the [21st September 2008/1st May 2009 respectively]"
The Adjudication
"I noted that at 16 January 2008 (the date of the Preliminary Meeting) the Responding Party was dealing with the works of grit blasting, painting, scaffolding and steel repair works as one body of work and I was of the view that the said minutes were evidence of this position. I noted that the Subcontract Price included the steel works sum; the sub contract period related to all work; the client's particular specification requirements included a steel and bolt specification (i.e. for the steel repair works); the name and contact details for the Responding Party's steelwork Contracts Manager was to be advised; and the number of men the Referring Party proposed to have on the steel repair works was minuted.
I also noted that the Referring Party's applications for interim payments sought monies for all works, including steel repair works and I noted that the Responding Party's payments and payment notices dealt with the sums applied for on an all encompassing basis and payments were not separated out on a "two contracts" basis, as now alleged.
Also, it appeared to me that the argument now raised regarding "two contracts", was a new argument raised in resistance of the adjudication proceedings…I noted the Responding Party's email dated 25 March 2009 in respect of the Referring Party's "fully substantiated Final Account" and was again not appraised by the Responding Party that two separate "final accounts" were being sought or required at that time.
I am of the view that whilst the Responding Party issued two similar "standard form" orders of the works of (1) grit blasting, painting and scaffolding and (2) steel repair works, the true intent for the Parties was that these works were to be carried out as one sub contract and as a fact they were administered as such during the period (and after) the subcontract works…"
"The Contract
5. There was a dispute (and a jurisdictional challenge) as to whether the works, the subject of the adjudication reference, comprised one or two contracts. Further to the provision of my view that the works were the subject of a single contract, the adjudication proceedings continued (with the Responding Party reserving its position) on the basis that the works were subject to one contract.
Jurisdictional Issues
13. The Responding Party, in its representative's letter dated 8 September 2009, set out three (separate) jurisdictional challenges. I received submissions from the Parties on these challenges and I set out my views in my letter dated 10 September 2009 and I do not add to my view except to note that the Responding Party stated in the Response (paragraph 6.4) it had granted the Referring Party an extension of time of 58 weeks from 21 March 2008 and it appeared to me that such statement which was not caveated/caught by any contractual issue and thereby any reservation to my jurisdiction, constituted an admission on the Responding Party's part as to a defined Contract period for all elements of the Works."
These Proceedings
The Law
"In practical terms, it is thought likely that a notice to refer will usually fall foul of the stipulation that it must contain a reference to only one dispute only where, as in Grovedeck, there is an attempt to refer disputes under more than one contract in a single notice of adjudication…"
It might well be the case that the adjudicator in this case did have jurisdiction in any event to address the disputed claims arising under the works which were specifically the subject matter of the December 2007 Sub-Contract. However, neither party has sought to argue that and I take the point no further.
"22. However, there are two further factors which effectively override considerations as to whether or not there were one, two, three or four contracts between the parties which establish that the Adjudicator was acting within his proper jurisdiction:
(a) The substantive decision-making process upon which the Adjudicator had to embark in relation to the disputed claim put before him necessarily involved a consideration of whether there was more than one contract. It was thus within his jurisdiction to decide in effect that there was one contract, albeit one that may have been varied by agreement.
(b) It was thus a part of his jurisdiction to decide whether or not and if so to what extent the Basebuild Contract had been varied by the CPA and BMS Arrangements and indeed whether there were yet further variations ordered to the Basebuild Contract. There may be cases, and this is clearly one, where substance and jurisdiction overlap so that it is within the Adjudicator's jurisdiction to decide as matters within his or her substantive jurisdiction whether there have been in effect variations to the contract pursuant to which he or she has properly been appointed Adjudicator. It cannot then in those circumstances be a valid challenge to his or her jurisdiction that upon analysis he or she may be wrong as a matter of fact or law in determining that such variations were made to the originating contract as opposed to a series of later legally unconnected contracts.
(c) The Supplementary Agreement is one which recognises in a way which has contractual effect that the parties were treating their contractual relationship as being in one "main contract". The total of the three sums agreed originally to be due with regard to the Basebuild, CPA and BMS Works are said to be a "contract sum"; the variations are being treated as a single variation list to be addressed; maintenance and defects liability obligations are being treated as arising in effect as a unified obligation. It is this one "main contract" which is effectively being varied. Thus, whatever the arrangement or arrangements contractually were before, as from the Supplementary Agreement the parties clearly agreed to treat their contractual relationship as stemming from one contract.
23. I have therefore formed the view that the Adjudicator did have jurisdiction to rule on all the matters which he did decide in his Decision. Whether he was right or wrong to find or make the assumption that there was effectively one contract which was varied and whether he was wrong as a matter of fact or law in any other part of his decision is immaterial. Any such errors do not mean that he does not have jurisdiction. Even if I was wrong about that conclusion, then my analysis that effectively the CPA and BMS Arrangements and the Supplementary Agreement were simply variations of the Basebuild Contract would apply.
24. Additionally, the adjudication clause is drawn widely and relates to "a dispute or difference [arising] under this Sub-Contract". In the Fiona Trust case [2007] UKHL 40, the House of Lords adopted a pragmatic and commercial approach to construing arbitration clauses. Lord Hoffmann said at Paragraph 13:
"In my opinion the construction of an arbitration clause should start from the assumption that the parties, as rational businessmen, are likely to have intended any dispute arising out of the relationship into which they have entered or purported to enter to be decided by the same tribunal. The clause should be construed in accordance with this presumption unless the language makes it clear that certain questions were intended to be excluded from the arbitrator's jurisdiction."
Whilst it could be argued that, if there were entirely separate contracts between the same parties which had obviously different dispute resolution clauses, there should be separate dispute resolution processes, in the current case all the disputes could properly be said to have arisen under the Basebuild Contract and the commercial parties could properly be said to have intended to have agreed to the adjudicator appointed under that contract to have jurisdiction to determine the value of sums due under that contract and any variations to that contract."
"That was a case in which there could be no doubt that the adjudicator was properly appointed under the first contract and there could be no argument that, in that capacity, he had jurisdiction to decide whether later "contracts" were simply variations of the first contract or stood on their own entirely separately as contracts in their own right. I am not convinced that this case is authority for any proposition other than that there may be cases in which adjudicators properly appointed have jurisdiction to resolve jurisdictional issues if and to the extent coincidentally those issues are part of the substantive dispute referred to adjudication."
"32. Let me now return briefly to the editors' commentary in the Building Law Reports. I readily recognise the concern lest this salutary new statutory power to promote early payment in construction contract cases be emasculated by jurisdictional challenges. The solution, however, seems to me not in finding defendants too readily to have, in the full sense, submitted to the adjudicator's jurisdiction, which if properly advised they plainly would not do. Rather, as Dyson J observed in paragraph 8 of his judgment in the Project Consultancy Group case, it is for courts (and adjudicators) to be "vigilant to examine the arguments critically." It is only if the defendant had advanced a properly arguable jurisdictional objection with a realistic prospect of succeeding upon it that he could hope to resist the summary enforcement of an adjudicator's award against him.
33. The position can I think be summarised in the following two propositions. (1) If a defendant to a Part 24(2) application has submitted to the adjudicator's jurisdiction in the full sense of having agreed not only that the adjudicator should rule on the issue of jurisdiction but also that he would then be bound by that ruling, then he is liable to enforcement in the short term, even if the adjudicator was plainly wrong on the issue. (2) Even if the defendant has not submitted to the adjudicator's jurisdiction in that sense, then he is still liable to a Part 24(2) summary judgment upon the award if the adjudicator's ruling on the jurisdictional issue was plainly right.
34. Applying those propositions in the instant case, I would hold that this appellant did not submit to the adjudicator's jurisdiction in the full sense and that the adjudicator's ruling was, on any view, not plainly right. Indeed, as already indicated, it seems to me that the adjudicator's ruling was, if anything, plainly wrong. I would accordingly allow the appeal, set aside the order made below and substitute for it an order dismissing the respondent's application for summary judgment."
There is nothing controversial in these observations with which the other members of the Court of Appeal agreed.
Discussion
(a) There undoubtedly was (as is accepted by both parties) a contract created by, contained in or evidenced by the letters of 17 and 18 December 2007. It is at the very least arguable that these letters simply confirm the offer and acceptance, given the references in both letters to each party "confirming" prices and acceptance of the price. This Sub-Contract related only to the grit blasting, painting and scaffolding works.
(b) The factual matrix however is that both parties knew that, albeit unsolicited, Supablast had quoted for the steel work back in October 2007 and had again been asked by Story in November 2007 to quote again for this work. It is an obvious inference that both Story and Supablast must have known, at the time that the December 2007 Sub-Contract was entered into, that there was a distinct possibility (albeit no commitment to that effect) that Supablast could well be engaged to carry out the steel work.
(c) The steel work quotation having been submitted and received no later than 3 January 2008, the price for it was negotiated and agreed before 16 January 2008.
(d) The minutes of the meeting of the 16 January 2008 can properly, sensibly and realistically be taken to evidence what was said and agreed between the parties at that time.
(e) Those minutes unequivocally record, objectively, agreement that all the works, the grit blasting, painting, scaffolding and steel work repairs, were to be carried out under the umbrella of one single agreement. Apart from the fact that the references to the Sub-Contract or subcontract agreement are all in the singular, all the works are described as being "Sub-Let". The Sub-Contract Price is defined as including the prices for all the works including the steel work. The first date for applying for payment is the same, 26th January 2008. There is apparently to be a single practical completion and making good defects certificate. There is a single date for "commencing… of the contract works on site". There is one "overall period for carrying out and completing the subcontract works on site"; this is obviously 60 days from commencement, that is from 21 January 2008, the commencement date. There is to be "one continuous" visit, that is all the work is to be done in one continuous run. The specification requirements include steel specifications. There is to be one set of meetings. The whole tenor of these minutes is that there is to be one Sub-Contract and there is nothing which suggests that there is to be more than one.
(f) Since all the various works were part of a logical and continuous process (erect scaffold-grit blast-repair/replace steel work-paint-dismantle scaffolding), there is no commercially logical reason why having a single subcontract for all this work was anything other than a sensible idea.
(g) If the two sets of work were intended to be the subject matter of two subcontracts, one would have expected in the minutes, at least in the "Additional Issues" or "Any Other Business" boxes, to see some hint or reference to that. If the steel work quotation which would have been an offer in contractual terms was not being legally accepted, again, one would expect to see some hint of this in these minutes.
(h) The fact that the letter of 29 January 2008 was sent, albeit there is no evidence that it was in some way formally acknowledged, does not point to any pre-existing agreement or understanding that there was and could have been no earlier acceptance (in legal terms) of the steel work quotation. If anything, it merely "confirms" a previous "acceptance of [Supablast's] price". The fact that it requires the subcontract reference to be exactly the same as that which covered the December 2007 Sub-Contract points unequivocally to an established mutual intention to treat the steel work as covered by and within the earlier Sub-Contract.
(i) The fact that thereafter there is no hint or suggestion from either party that they were proceeding on the basis of there being two Sub-Contracts or indeed on any basis other than there being only one Sub-Contract covering all the work corroborates the fact that the parties had agreed that there would be one Sub-Contract covering all the work. At the very least these facts point very strongly indeed to there being an agreed convention, to which the parties were working, namely that there was only one Sub-Contract covering all the work. There would thus be an estoppel by convention on which the parties had relied throughout the course of the project, in terms of ordering their affairs (for instance in relation to payments and extensions of time) by reference in effect to there being one subcontract.
(j) The fact, if it really is the case, that Story believed that there were two Sub-Contracts which were really only being run together as a matter of administrative convenience is immaterial in circumstances where that belief was not expressed by words or conduct to Supablast. That is because one judges whether and if so what contract exists objectively primarily by considering what each party says, orally or in writing, to the other and by their conduct as manifested to each other.
Decision
Costs
Total Bill | £24,127.31 |
Less Summary reduction | £4127.31 |
Sub total | £20,000.00 |
Less 20% | £4000.00 |
Total | £16,000.00 |