BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £5, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> RHP Merchants And Construction Ltd v Treforest Property Company Ltd [2021] EWHC B40 (TCC) (22 October 2021) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2021/B40.html Cite as: [2021] EWHC B40 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (QBD)
Fetter Lane London EC4A 1NL |
||
B e f o r e :
SITTING AS A JUDGE OF THE HIGH COURT
____________________
RHP MERCHANTS AND CONSTRUCTION LTD | ||
and | ||
TREFOREST PROPERTY COMPANY LTD |
____________________
291-299 Borough High Street, London SE1 1JG
Tel: 020 7269 0370
[email protected]
MR J STEEL appeared on behalf of the Defendant
____________________
Crown Copyright ©
ROGER STEWART QC:
Introduction
a) the general policy of the Housing Grants, Construction Regeneration Act 1996 which has, in relation to adjudications, often being expressed as, "pay now, dispute later";
b) the general and important right of parties to have access to the courts;
c) the importance of litigation being conducted promptly and efficiently;
d) the existence of two adjudication decisions; and, of course,
e) the particular facts of this case.
The Facts
a. the claimant submitted a final statement seeking a payment of £5,116,638.20 which resulted in a net payment of £144,895.40 plus VAT, leading to a total sum alleged to be due of £152,140.17;
b. the employer's agent on 25 November 2019 issued a statement for £100,000 less than this but accordingly accepted that £52,140.17 was not paid, although it appears from the papers that the agent wrongly identified the amount which had in fact be paid;
c. On 16 March 2020, Treforest issued a pay less notice and a dispute notice, seeking total deductions of £1,070,000. Those were under four heads which can be described as asbestos, where the dispute was whether or not RHP was entitled to be paid the sums which were included, apparently, within the contract but not carried out; contingency; snagging; late completion and remedying of defective works. It will be apparent that the dispute covered a number of different and related topics but it can be seen that all of these matters were properly raised as being the subject of a final account dispute.
d. On 24 June 2020, RHP commenced adjudication which led to Mr Peter Garcia, the adjudicator, deciding on 7 August 2020 that RHP was required to pay £264,274.60 with 50% of his fees. This adjudication appears to have covered the whole final account dispute which is now at issue in these proceedings;
e. Following the non-payment of this award, enforcement proceedings were issued on 3 September 2020, which led to the decision of HHJ Parfitt to which I have referred; and
f. RHP in the meantime issued a second adjudication which became before Mr Derek Pye. The basis of this second application was said to be a breach of contract in respect of the schedule of defects during a period of suspension which the first adjudicator had found to be in existence and which was alleged to lead to an instruction that Treforest was not required to be rectify any defects;
g. Perhaps unsurprisingly, there was a jurisdictional challenge to the second adjudication on the grounds, essentially, that the substance of the dispute had already been decided by the first adjudication. The second adjudicator rejected the submission that he did not have jurisdiction and found that RHP was entitled to damages in the sum of £223,170 for breach by Treforest;
h. These proceedings were issued by a claim form and particulars of claim on 9 July 2021;
i. Arbitration proceedings were also issued on 12 July 2021 apparently covering the same grounds as these Part 7 proceedings – the apparent reason for this being a concern there was an arbitration clause in the underlying contract. I understand that Treforest has said that the arbitration proceedings should be stayed, and I anticipate that this is agreed; see the letter from Treforest's solicitors at page 573 of the bundle;
j. The application for a stay was issued on 30 July 2021. The order sought in that application was an order that, until the claimant complied with the order of Judge Parfitt, the action would be stayed. I interpose to say that there was no request in that application for any strike-out or consequential orders.
k. On 2 August, RHP, by its then solicitors, wrote an email saying it agreed to a stay but would not be making any payment; also, by separate email, that it would not agree to pay any costs; it appears therefore at that stage the parties were either in agreement or very close to agreement, although neither party has stated that there was in fact a binding agreement as to the terms by which this matter should be disposed.
l. On 9 August 2021, RHP resiled from that position but, by an email from its solicitors at page 619, offered to pay in £57,637.62. That is shown by the letter which accompanied it to be made up on the basis that it was the net figure netting off the sums due on the first judgment's sum and the sums due under the second adjudication award.
m. That offer was refused by Treforest on 10 August;
n. On 11 August 2021, ICC Judge Briggs dismissed Treforest's partition for a winding-up order against RHP and ordered indemnity costs at £23,000 to RHP. I have no substantive information or evidence as to the basis of the judge's decision in relation to that but it appears to be the case that it was based on the fact that the petition sum, i.e. the judgment, was disputed substantially by reference to these proceedings;
o. On 26 August 2021, Treforest's solicitors offered to set off the costs order which they were subject to with the costs order which HHJ Parfitt had made.
p. On 29 September 2021, RHP offered to pay the sum of £36,494.69 to Treforest on the basis that this application was withdrawn.
q. Following the taking of instructions in relation to that, Treforest's solicitors wrote on 7 October, stating that the application was not accepted and making a number of detailed points, saying that the total amount due to their client was £297,010.63, and that the conduct of RHP amounted to a flagrant disregard of the pay-now-argue-later regime imposed by the HGCRA.
Discussion
"i. The Court undoubtedly has the power and discretion to stay any proceedings if justice requires it.
ii. In exercising that power and discretion, the Court must very much have in mind a party's right to access to justice and to issue and pursue proceedings.
iii. The power is one that is to be used sparingly and in exceptional circumstances.
iv. Those circumstances include bad faith and where the claimant has acted or is acting particularly oppressively or unreasonably".
Discussion